Black Iron Releases Feasibility Study Showing 45.9% IRR, 2.2 Year Payback and U.S. $3.5 Billion NPV for Shymanivske Project

TORONTO, ONTARIO -- (Marketwire) -- 11/15/12 -- Black Iron Inc. ("Black Iron" or the "Company") (TSX:BKI)(FRANKFURT:BIN) is pleased to announce the results of the Bankable Feasibility Study ("BFS") completed on its Shymanivske Iron Ore Project located in Kryviy Rih, Ukraine (the "Project"). The BFS outlines an operation producing 9.2 million tonnes per year of high-grade 68% iron ore concentrate, projecting a 45.9% internal rate of return ("IRR") and a U.S. $3.5 billion net present value ("NPV") at an 8% discount rate.

The BFS was completed by WorleyParsons Canada Services Ltd. ("WorleyParsons"), Watts, Griffis and McOuat Limited ("WGM"), Consulting Geologists and Engineers of Toronto, and P&E Mining Consultants Inc. ("P&E"). Mr. Michael Kociumbas, P.Geo., and Mr. Rick Risto, P.Geo., both with independent firm WGM, are Qualified Persons as defined by NI 43-101. WGM has previously visited the site, collected independent core samples and reviewed the QA/QC data received to date. Mr. Risto has reviewed and approved the underlying sampling, analytical and test data used for the estimate and Mr. Kociumbas is responsible for auditing the in-house mineral resource estimate as supplied by Black Iron. The estimate is classified as Measured, Indicated and Inferred mineral resources, consistent with the CIM definitions referred to in National Instrument 43-101. The complete BFS report will be filed on SEDAR and Black Iron's website within 45 days of the publication of this news release.

The Table below summarizes the key elements of the BFS:

High-Grade 68% Concentrate (all currency is USD, pre-tax)


----------------------------------------------------------------------------
NPV at 8% discount rate                                      $  3.5 billion 
----------------------------------------------------------------------------
IRR                                                                    45.9%
----------------------------------------------------------------------------
Total Estimated Capital Costs (excluding sustaining capital) $ 1094 million 
----------------------------------------------------------------------------
Life of Mine FOB OPEX (Beneficiation, Mine & Transportation) $     43.97 /t 
Mine Gate OPEX (Beneficiation & Mine)                        $     29.67 /t 
----------------------------------------------------------------------------
High-Grade 68% Concentrate Sales Price Forecast - based on                  
 long term CFR benchmark price of $95/T @ 62% iron adjusted                 
 for Black Iron's higher iron content and shorter shipping                  
 distance to end users                                                      
  (Year 1, 2016)                                             $          125 
  (Year 2)                                                   $          117 
  (Year 3 onward; long-term)                                 $          115 
----------------------------------------------------------------------------
Average Annual Cash Flow                                     $  593 million 
----------------------------------------------------------------------------
Estimated Mine Life                                                16 years 
----------------------------------------------------------------------------
Final Product Iron Grade (Fine Iron Ore Concentrate)                 68% Fe 
----------------------------------------------------------------------------
Measured and Indicated Resource (at 31.6% iron)                    645.8 Mt 
----------------------------------------------------------------------------
Proven and Probable Reserves (at 31.1% iron)                       448.2 Mt 
----------------------------------------------------------------------------
Annual Production Rate (average life of mine, post ramp-up                  
 year)                                                               9.2 Mt 
----------------------------------------------------------------------------
Projected Plant Start-up and Commissioning                         Q4, 2015 
----------------------------------------------------------------------------
Projected Commencement of Revenue Generation                       Q1, 2016 
----------------------------------------------------------------------------
Projected Years to Payback (at 8% Discount Rate)                  2.2 years 
----------------------------------------------------------------------------

Matt Simpson, Black Iron's President and CEO, commented, "The operation outlined by this BFS for the Shymanivske Project clearly illustrates the potential for a high-value, low net cost iron ore development project. The projected high NPV, net cash flows, and relatively low unit cost for concentrate arise from Black Iron's advantages, which include an iron ore deposit with significant existing infrastructure (railway, power lines and port) in addition to access to low-cost skilled labour. We continue to deliver on our objective timetable and our results to date, coupled with this engineering study, make a compelling case for expediting the development of the Shymanivske Project."

Financial Sensitivities at Various Discount Rates


----------------------------------------------------------------------------
IRR (pre-tax)                                             45.9%             
----------------------------------------------------------------------------
                                                      Pre-Tax               
                                                      NPV USD        Payback
Discount Rate                                      (Millions)        (Years)
----------------------------------------------------------------------------
0%                                           $           8392            1.9
----------------------------------------------------------------------------
6%                                           $           4328            2.1
----------------------------------------------------------------------------
8%                                           $           3524            2.2
----------------------------------------------------------------------------
10%                                          $           2887            2.3
----------------------------------------------------------------------------

The Project has favourable economic potential across a range of discount rates. The operations outlined in this BFS are projected to generate over U.S. $1136 million in average annual revenue over the life of mine.

On the basis of the metallurgical test work completed for this BFS, it is estimated that the process weight recovery of 32.7% would yield a project life of 16 years at an average strip ratio of 1.63:1, according to the current estimated resource. The Company believes that additional exploration and definition drilling work have the potential to expand the existing resource and upgrade the 188.3 Mt of Inferred mineral resource to the Measured and Indicated classification, potentially adding up to 5 years to the Project life. With successful exploration in the North end of Shymanivske and the addition of resources from the nearly adjacent Zelenivske Project, Black Iron expects to be able to support an even higher annual production rate, which would further increase the already favourable Project NPV.

George Mover, Black Iron's Chief Operating Officer, added, "We are pleased with the level of engineering expertise and rigour behind this BFS. Through the process, we implemented several improvements to the work completed last year for our Preliminary Economic Assessment. We have found and verified solutions to optimize the process flow sheet, to reduce the stripping ratio through mine phasing, and to increase our weight recoveries. As a result, we are now considering an initial operation with 26% higher annual production and 16% lower operating costs than in our previous study. The relatively low-unit operating cost of production, coupled with close proximity to Turkish, European, and Middle East customers, means that this operation has the potential to remain profitable despite fluctuations in the iron ore price."

Details and Assumptions

Total initial capital expenditures are estimated at U.S. $1094 million to produce a high-grade 68% iron ore concentrate. The capital cost estimate excludes the sustaining capital cost of U.S. $689 million. The initial assessment of the preferred port facility indicates that sufficient capacity currently exists for the planned production.


----------------------------------------------------------------------------
Summary of Estimated Initial Capital Costs                    USD (millions)
----------------------------------------------------------------------------
Mining Capitalized Pre-Stripping Costs                                    61
----------------------------------------------------------------------------
Mine Fleet Lease Costs                                                    62
----------------------------------------------------------------------------
Concentrator and Site Infrastructure                                     654
----------------------------------------------------------------------------
Environmental and Tailings Management                                     20
----------------------------------------------------------------------------
Rail Spur                                                                  9
----------------------------------------------------------------------------
Port Facilities                                                          nil
----------------------------------------------------------------------------
Indirect Costs and Land Acquisition                                      189
----------------------------------------------------------------------------
Contingency (10%)                                                         99
----------------------------------------------------------------------------
TOTAL                                                                   1094
----------------------------------------------------------------------------

The total average operating costs over 16 years are estimated at U.S. $43.97 per tonne of high grade 68% iron ore concentrate.


----------------------------------------------------------------------------
                                                                USD/tonne of
                                                                 Concentrate
                                                                    (Average
Summary of Estimated Operating Costs                              Mine Life)
----------------------------------------------------------------------------
Mining                                                     $           13.51
----------------------------------------------------------------------------
Concentrator                                               $           14.30
----------------------------------------------------------------------------
Site Infrastructure                                        $            0.75
----------------------------------------------------------------------------
Sales and General Administration                           $            0.75
----------------------------------------------------------------------------
Environmental and Tailings Management                      $            0.37
----------------------------------------------------------------------------
Rail Transportation                                        $            7.39
----------------------------------------------------------------------------
Port Facility                                              $            6.90
----------------------------------------------------------------------------
TOTAL                                                      $           43.97
----------------------------------------------------------------------------

Consistent with practice in the industry, this BFS has been prepared with an engineering accuracy of +/-15%.

Currency Sensitivity

For the purpose of the BFS an exchange rate of 8.1 UAH per USD has been used for the CAPEX (up to Jan. 2016) and 9.0 UAH per USD for the OPEX and Sustaining Capital (2016 and beyond). Variations in the exchange rates from year 2016 and beyond impact the financial analysis as follows.

Impact of Ukraine Hryvna Exposure - BFS Currency Sensitivity


----------------------------------------------------------------------------
                                                      (UAH/USD)             
                                        ------------------------------------
Exchange Rate as of year 2016 onward          8:1      9:1     10:1     11:1
----------------------------------------------------------------------------
NPV @ 8% discount U.S. $ (millions)          3334     3524     3677     3800
----------------------------------------------------------------------------
Total Estimated Capital Cost                 1094     1094     1094     1094
----------------------------------------------------------------------------
Estimated Operating Cost ($/tonne)          46.73    43.97    41.75    39.96
----------------------------------------------------------------------------
Average Annual Cash Flow U.S. $                                             
 (millions)                                   568      593      613      629
----------------------------------------------------------------------------

Bankable Feasibility Study Report

The BFS has been prepared in accordance with the guidelines of National Instrument 43-101, by the independent firms of WorleyParsons Canada Services Ltd., Watts, Griffis and McOuat Limited and P&E Mining Consultants Inc. WorleyParsons is a leading full-service engineering firm and has experience in the sector that includes the design and construction supervision of many components of some of the world's leading iron ore assets. The final BFS technical report, which will also include the current mineral resource estimate, will be filed on SEDAR within 45 days of the publication of this news release.

Pellet Plant Alternative

Black Iron has investigated an alternative production scenario, which would include the production of high-grade iron ore pellets. The pellet production alternative is not included as part of the BFS.

Analyst and Shareholder Conference Call

Black Iron will host a conference call today at 8:00 a.m., EST (November 15, 2012) to discuss the BFS results. To participate in the call please dial the following:

International: +1 416 340 8527

Toll Free North America: 1 877 240 9772

To register and listen to the webcast of the call, please go to Black Iron's website at www.blackiron.com.

Qualified Persons

The contents of this press release have been prepared under the supervision of and reviewed and approved by Qualified Persons, as follows:


--  Rob Spiering, P.Eng., Project Manager, WorleyParsons QP for the Process
    Plant and Infrastructure;

--  Michael Kociumbas, P.Geo. and Rick Risto, P.Geo., Watts, Griffis and
    McOuat Limited, QPs for mineral resources and QA/QC and data
    verification;

--  Eugene Puritch, P.Eng., P&E Mining Consultants Inc., QP for the mine
    engineering aspects.

These persons are Qualified Persons as defined by NI 43-101, are independent of Black Iron, and have reviewed the content of this press release. For further information, please see the technical report of the Company, which is available on SEDAR at www.sedar.com.

Additional information about the Project can be found in the technical report filed on SEDAR at www.sedar.com, entitled "Resource Estimate - Shymanivske Deposit in Ukraine," and dated January 31, 2011.

About Black Iron

Black Iron is an iron ore exploration and development company, advancing its 100 percent-owned Shymanivske project located in Kryviy Rih, Ukraine. This project contains an NI 43-101 compliant resource, with 645.8 Mt Measured and Indicated mineral resources, consisting of 355.1 Mt Measured mineral resources grading 32.0% Total iron and 19.5% Magnetic iron, and Indicated mineral resources of 290.7 Mt grading 31.1% Total iron and 17.9% Magnetic iron, using a cut-off grade of 10% Magnetic iron. Additionally, the project contains 188.3 Mt of Inferred mineral resources grading 30.1% Total iron and 18.4% Magnetic iron. The project is surrounded by five other operating mines, including ArcelorMittal's iron ore complex. The Company believes that existing infrastructure, including access to power, rail and port facilities, will allow for a quick development timeline to production. Further, the Company holds an exploration permit for the adjacent Zelenivske project, which it intends to further explore to determine its potential. Please visit the Company's website at www.blackiron.com or write us at [email protected] for more information.

Forward-Looking Information

This press release contains forward-looking information which may include, but is not limited to, statements about the results of the FS and the development potential of the Company and its project; the timing and amount of future exploration and development of the project; and the future financial or operating performance of the Company and its projects. Often, but not always, forward-looking information can be identified by the use of words such as "plans," "expects," "is expected," "budget," "scheduled," "estimates," "forecasts," "intends," "anticipates" or "believes" or variations (including negative variations) of such words and phrases, or by the use of words or phrases that state that certain actions, events or results "may," "could," "would," "might" or "will" be taken, occur or be achieved.

Forward-looking information is based on certain assumptions and analyses made by the Company and based on known facts at the time. Forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company and/or its subsidiaries to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information contained in this press release, including, without limitation, those described in the Company's public disclosure documents which may be found under the Company's profile on SEDAR. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in such forward-looking information, there may be other factors that may cause actions, events or results to differ from those anticipated, estimated or intended. Should one or more of these risks or uncertainties materialize, or should assumptions underlying such forward-looking information prove incorrect, actual results, performance or achievements may vary materially from those expressed or implied by the forward-looking information contained in this press release. The forward-looking information contained herein is made as of the date of this press release and the Company disclaims any obligation to update or review such information or statements, whether as a result of new information, future events or results or otherwise, except as required by law.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
In his session at DevOps Summit, Tapabrata Pal, Director of Enterprise Architecture at Capital One, will tell a story about how Capital One has embraced Agile and DevOps Security practices across the Enterprise – driven by Enterprise Architecture; bringing in Development, Operations and Information Security organizations together. Capital Ones DevOpsSec practice is based upon three "pillars" – Shift-Left, Automate Everything, Dashboard Everything. Within about three years, from 100% waterfall, C...
Even as cloud and managed services grow increasingly central to business strategy and performance, challenges remain. The biggest sticking point for companies seeking to capitalize on the cloud is data security. Keeping data safe is an issue in any computing environment, and it has been a focus since the earliest days of the cloud revolution. Understandably so: a lot can go wrong when you allow valuable information to live outside the firewall. Recent revelations about government snooping, along...
The explosion of connected devices / sensors is creating an ever-expanding set of new and valuable data. In parallel the emerging capability of Big Data technologies to store, access, analyze, and react to this data is producing changes in business models under the umbrella of the Internet of Things (IoT). In particular within the Insurance industry, IoT appears positioned to enable deep changes by altering relationships between insurers, distributors, and the insured. In his session at @Things...
PubNub on Monday has announced that it is partnering with IBM to bring its sophisticated real-time data streaming and messaging capabilities to Bluemix, IBM’s cloud development platform. “Today’s app and connected devices require an always-on connection, but building a secure, scalable solution from the ground up is time consuming, resource intensive, and error-prone,” said Todd Greene, CEO of PubNub. “PubNub enables web, mobile and IoT developers building apps on IBM Bluemix to quickly add sc...
The cloud has transformed how we think about software quality. Instead of preventing failures, we must focus on automatic recovery from failure. In other words, resilience trumps traditional quality measures. Continuous delivery models further squeeze traditional notions of quality. Remember the venerable project management Iron Triangle? Among time, scope, and cost, you can only fix two or quality will suffer. Only in today's DevOps world, continuous testing, integration, and deployment upend...
Data-intensive companies that strive to gain insights from data using Big Data analytics tools can gain tremendous competitive advantage by deploying data-centric storage. Organizations generate large volumes of data, the vast majority of which is unstructured. As the volume and velocity of this unstructured data increases, the costs, risks and usability challenges associated with managing the unstructured data (regardless of file type, size or device) increases simultaneously, including end-to-...
Sensor-enabled things are becoming more commonplace, precursors to a larger and more complex framework that most consider the ultimate promise of the IoT: things connecting, interacting, sharing, storing, and over time perhaps learning and predicting based on habits, behaviors, location, preferences, purchases and more. In his session at @ThingsExpo, Tom Wesselman, Director of Communications Ecosystem Architecture at Plantronics, will examine the still nascent IoT as it is coalescing, includin...
The excitement around the possibilities enabled by Big Data is being tempered by the daunting task of feeding the analytics engines with high quality data on a continuous basis. As the once distinct fields of data integration and data management increasingly converge, cloud-based data solutions providers have emerged that can buffer your organization from the complexities of this continuous data cleansing and management so that you’re free to focus on the end goal: actionable insight.
Between the compelling mockups and specs produced by your analysts and designers, and the resulting application built by your developers, there is a gulf where projects fail, costs spiral out of control, and applications fall short of requirements. In his session at DevOps Summit, Charles Kendrick, CTO and Chief Architect at Isomorphic Software, will present a new approach where business and development users collaborate – each using tools appropriate to their goals and expertise – to build mo...
Operational Hadoop and the Lambda Architecture for Streaming Data Apache Hadoop is emerging as a distributed platform for handling large and fast incoming streams of data. Predictive maintenance, supply chain optimization, and Internet-of-Things analysis are examples where Hadoop provides the scalable storage, processing, and analytics platform to gain meaningful insights from granular data that is typically only valuable from a large-scale, aggregate view. One architecture useful for capturing...
The Internet of Things (IoT) is causing data centers to become radically decentralized and atomized within a new paradigm known as “fog computing.” To support IoT applications, such as connected cars and smart grids, data centers' core functions will be decentralized out to the network's edges and endpoints (aka “fogs”). As this trend takes hold, Big Data analytics platforms will focus on high-volume log analysis (aka “logs”) and rely heavily on cognitive-computing algorithms (aka “cogs”) to mak...
When it comes to the Internet of Things, hooking up will get you only so far. If you want customers to commit, you need to go beyond simply connecting products. You need to use the devices themselves to transform how you engage with every customer and how you manage the entire product lifecycle. In his session at @ThingsExpo, Sean Lorenz, Technical Product Manager for Xively at LogMeIn, will show how “product relationship management” can help you leverage your connected devices and the data th...
In the consumer IoT, everything is new, and the IT world of bits and bytes holds sway. But industrial and commercial realms encompass operational technology (OT) that has been around for 25 or 50 years. This grittier, pre-IP, more hands-on world has much to gain from Industrial IoT (IIoT) applications and principles. But adding sensors and wireless connectivity won’t work in environments that demand unwavering reliability and performance. In his session at @ThingsExpo, Ron Sege, CEO of Echelon...
With several hundred implementations of IoT-enabled solutions in the past 12 months alone, this session will focus on experience over the art of the possible. Many can only imagine the most advanced telematics platform ever deployed, supporting millions of customers, producing tens of thousands events or GBs per trip, and hundreds of TBs per month. With the ability to support a billion sensor events per second, over 30PB of warm data for analytics, and hundreds of PBs for an data analytics arc...
One of the biggest impacts of the Internet of Things is and will continue to be on data; specifically data volume, management and usage. Companies are scrambling to adapt to this new and unpredictable data reality with legacy infrastructure that cannot handle the speed and volume of data. In his session at @ThingsExpo, Don DeLoach, CEO and president of Infobright, will discuss how companies need to rethink their data infrastructure to participate in the IoT, including: Data storage: Understand...