Orvana Reports Revised Resource and Reserve Estimates for the Upper Mineralized Zone ("UMZ") Copper-Gold-Silver Mine, Bolivia

TORONTO, ONTARIO -- (Marketwire) -- 12/13/12 -- Orvana Minerals Corp. (TSX:ORV), through its wholly-owned subsidiary, Empresa Minera Paititi ("EMIPA"), provides updated National Instrument ("NI") 43-101-compliant resource and reserve estimates for its Don Mario UMZ copper-gold-silver mine operations in Bolivia. During 2012, EMIPA made significant changes to the mining and processing aspects of the operation thus warranting an update.

The updated NI 43-101-compliant resource and reserve estimates are effective October 1, 2012 and are shown in the tables below. The reserve estimate contains approximately 177,000 ounces of gold, 5.6 million ounces of silver, and 120 million pounds of copper, which is a decrease of about 5%, 2%, and 11%, respectively, after considerations for production through September 30, 2012 as well as the exclusion of certain oxide mineralization whose metals cannot be extracted economically (see press release of January 18, 2012); testing of these ores will continue in order to seek a viable extraction method. The most significant change in the mine plan is the processing of Transition ore by a Flotation-Only process instead of the Leach-Precipitation-Flotation ("LPF") process.


                     -----------------------------------------------
                                MEASURED                   INDICATED
                     -----------------------------------------------
                     tonnes, Gold, Copper, Silver, tonnes,    Gold, 
ORE TYPE               '000s   g/t       %     g/t   '000s      g/t 
--------------------------------------------------------------------
Oxides (in situ)         149  1.90    1.74      77     219     1.94 
--------------------------------------------------------------------
Oxides (stockpile)                                     757     1.78 
--------------------------------------------------------------------
Transition (in situ)     701  1.30    1.23      44     938     1.22 
--------------------------------------------------------------------
Transition                                                          
 (stockpile)                                             3     1.40 
--------------------------------------------------------------------
Sulphides                874  1.16    1.15      30   1,344     1.03 
--------------------------------------------------------------------
                       1,724  1.28    1.23      39   3,261     1.32 
                     -----------------------------------------------
                                         TOTAL M&I   4,985     1.31 
                                   ---------------------------------
                                                                    
                     -----------------------------------------------
                                    PROVEN                  PROBABLE
                     -----------------------------------------------
                     tonnes, Gold, Copper, Silver, tonnes,    Gold, 
ORE TYPE               '000s   g/t       %     g/t   '000s      g/t 
--------------------------------------------------------------------
Oxides (in situ)         131  1.85    1.78      83     196     1.86 
--------------------------------------------------------------------
Oxides (stockpile)                                     401     1.74 
--------------------------------------------------------------------
Transition (in situ)     643  1.32    1.22      43     908     1.23 
--------------------------------------------------------------------
Transition                                                          
 (stockpile)                                             3     1.40 
--------------------------------------------------------------------
Sulphides                820  1.13    1.16      30   1,231     1.05 
--------------------------------------------------------------------
                       1,594  1.26    1.23      40   2,739     1.27 
                     -----------------------------------------------
                                          TOTAL 2P   4,333     1.27 
                                   ---------------------------------

                    ------------------------------------------------
                    INDICATED                    INFERRED           
                    ------------------------------------------------
                      Copper, Silver, tonnes,  Gold, Copper, Silver,
ORE TYPE                    %     g/t   '000s    g/t       %     g/t
--------------------------------------------------------------------
Oxides (in situ)         1.88      63      38   1.93    1.80      52
--------------------------------------------------------------------
Oxides (stockpile)       1.79      44                               
--------------------------------------------------------------------
Transition (in situ)     1.18      41      97   0.96    1.10      43
--------------------------------------------------------------------
Transition                                                          
 (stockpile)             1.53      72                               
--------------------------------------------------------------------
Sulphides                1.07      31      28   1.02    0.73      17
--------------------------------------------------------------------
                         1.32      39     162   1.20    1.20      40
                    ------------------------------------------------
                         1.29      39                               
                    -----------------                               
                                                                    
                    ------------------------------------------------
                     PROBABLE            PROVEN + PROBABLE          
                    ------------------------------------------------
                      Copper, Silver, tonnes,  Gold, Copper, Silver,
ORE TYPE                    %     g/t   '000s    g/t       %     g/t
--------------------------------------------------------------------
Oxides (in situ)         1.90      67     327   1.85    1.85      73
--------------------------------------------------------------------
Oxides (stockpile)       1.81      49     401   1.74    1.81      49
--------------------------------------------------------------------
Transition (in situ)     1.17      41   1,551   1.27    1.19      42
--------------------------------------------------------------------
Transition                                                          
 (stockpile)             1.53      72       3   1.40    1.53      72
--------------------------------------------------------------------
Sulphides                1.10      31   2,051   1.08    1.12      31
--------------------------------------------------------------------
                         1.28      40   4,333   1.27    1.26      40
                    ------------------------------------------------
                         1.26      40                               
                    -----------------                               

Note: As of October 1, 2012, the effective date of the Technical Report to be filed.

The mine plan now consists of 720,000 tonnes per year of Flotation-Only processing of Transition and Sulphide ores and 100,800 tonnes per year of LPF processing of oxide ores through 2017; the LPF processing of 224,300 tonnes of certain stockpiled oxide ores will continue in 2018. Model parameters are as follows:


Mine Plan: Flotation-Only            - 2,700 tonnes/day     (263 days/yr)   
           LPF                       - 1,667 tonnes/day     (60 days/yr)    
           224,300-tonne oxide stockpile sent to LPF in 2018                
                                                                            
Gold       Flotation-Only                                                   
 recovery: (Transition)              - 50%                                  
           Flotation-Only (Sulphide) - 60%                                  
           LPF                       - 56%                                  
Copper     Flotation-Only                                                   
 recovery: (Transition)              - 60%                                  
           Flotation-Only (Sulphide) - 80%                                  
           LPF                       - 60%                                  
Silver     Flotation-Only                                                   
 recovery: (Transition)              - 50%                                  
           Flotation-Only (Sulphide) - 60%                                  
           LPF                       - 40%                                  

Key financial input parameters are (all values in US dollars):


Sustaining capital:             $26,900,000                                 
Mine operating cost:            $4.78 per tonne (ore + waste)               
Strip ratio (waste:ore):         0.55:1                                     
Processing cost:                                                            
  LPF:                          $80.23 per tonne ore (Oxide)                
  Flotation -only:              $13.09 per tonne ore (Transition, Sulphide) 
G&A:                            $6.76 per tonne ore (LPF)                   
                                $5.68 per tonne ore (Flotation-Only)        
Copper sales:                   $0.85 per pound (LPF)                       
                                $1.28 per pound (Flotation-Only)            
Gold sales:                     $127.64 per ounce (LPF)                     
                                $168.80 per ounce (Flotation-Only)          
Silver sales:                   $3.40 per ounce (LPF)                       
                                $5.20 per ounce (Flotation-Only)            
Copper price (LOM):             $3.00/pound                                 
Gold price (LOM):               $1,400.00/ounce                             
Silver price (LOM):             $25.00/ounce                                

Certain oxide resources are not included in the mine plan, whether in situ or in stockpile, since treatment by Flotation-Only or LPF processes is not practical and/or not economically viable because of the input price deck or other parameters, but will be processed opportunistically during the life of mine. Likewise, some Transition and Sulphide resources not included in the mine plan will also be mined and processed opportunistically if extraction of the metals is economically viable.

Products made from the LPF process include a copper cement and a talc-rich precious-metal concentrate, and from the Flotation-Only process a copper concentrate with levels of lead from 8% to as high as 20% as well as a lead concentrate. All products are under contract.

"This mine plan outlines a path forward that optimizes the UMZ operation," said Bill Williams, President and Chief Executive Officer of Orvana Minerals Corp. "We will continue to pursue opportunities to improve recoveries as well as seek alternatives to extend production beyond 2018, including exploration in proximal concessions," he added.

During October, production was about 973,000 pounds of copper, 1,440 ounces of gold, and 76,000 ounces of silver. Total cash costs, on a co-product basis including all royalties and based on sales, were approximately $1.80 per pound copper, $910 per ounce gold and $16 per ounce silver. During November, production was about 1,060,000 pounds of copper, 1,290 ounces of gold, and 62,000 ounces of silver at total cash costs of less than $2.00 per pound, less than $980 per ounce, and less than $22.00 per ounce, respectively. Whereas the Flotation-Only process was operable during October and November, the LPF process is currently active and processing will switch over to Flotation-Only next week and continue in January.

The information regarding the NI 43-101-compliant technical report was prepared under the supervision of Francisco Alcalde Garmendia of Kminante Consultores in Santiago, Chile, who is a qualified person for the purposes of NI 43-101 and is independent of EMIPA. The compilation of production information was prepared by Bill Williams, President and Chief Executive Officer of Orvana Minerals Corp, who is a qualified person for the purposes of NI 43-101.

The Technical Report will be filed on www.sedar.com and the Orvana website within 45 days of this release.

About Orvana

Orvana Minerals Corp. is a multi-mine gold and copper producer. Orvana's primary asset is the El Valle-Boinas/Carles gold-copper Mine in northern Spain. Orvana also owns and operates the Don Mario Upper Mineralized Zone Mine in Bolivia, which is a copper-gold-silver deposit. In addition, Orvana is advancing its Copperwood copper project in Michigan, USA. Additional information is available at Orvana's website (www.orvana.com).

Forward Looking Disclaimer

Certain statements in this press release constitute forward-looking statements or forward-looking information within the meaning of applicable securities laws ("forward-looking statements"). Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions, potentials, future events or performance (often, but not always, using words or phrases such as "believes", "expects", "plans", "estimates" or "intends" or stating that certain actions, events or results "may", "could", "would", "might", "will" or "are projected to" be taken or achieved) are not statements of historical fact, but are forward-looking statements.

Forward-looking statements relate to, among other things, all aspects of the development of the Upper Mineralized Zone ("UMZ") deposit at the Don Mario Mine in Bolivia, the El Valle-Boinas/Carles Mine in Spain and the Copperwood project in Michigan and their potential operations and production; the outcome and timing of decisions with respect to whether and how to proceed with such development and production; the timing and outcome of any such development and production; estimates of future capital expenditures; mineral resource estimates; estimates of permitting time lines; statements and information regarding future feasibility studies and their results; production forecasts; future transactions; future metal prices; the ability to achieve additional growth and geographic diversification; future production costs; future financial performance, including the ability to increase cash flow and profits; future financing requirements; and mine development plans.

Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by Orvana as of the date of such statements, are inherently subject to significant business, economic and competitive uncertainties and contingencies. The estimates and assumptions of Orvana contained or incorporated by reference in this news release, which may prove to be incorrect, include, but are not limited to, the various assumptions set forth herein and in the Company's most recently filed Annual Information Form, or as otherwise expressly incorporated herein by reference as well as: there being no significant disruptions affecting operations, whether due to labour disruptions, supply disruptions, power disruptions, damage to equipment or otherwise; permitting, development, operations, expansion and acquisitions at the UMZ deposit, El Valle-Boinas/Carles Mine and the Copperwood project being consistent with the Company's current expectations; political developments in any jurisdiction in which the Company operates being consistent with its current expectations; certain price assumptions for gold, copper and silver; prices for key supplies being approximately consistent with current levels; production and cost of sales forecasts meeting expectations; the accuracy of the Company's current mineral reserve and mineral resource estimates; and labour and materials costs increasing on a basis consistent with Orvana's current expectations.

A variety of inherent risks, uncertainties and factors, many of which are beyond the Company's control, affect the operations, performance and results of the Company and its business, and could cause actual events or results to differ materially from estimated or anticipated events or results expressed or implied by forward looking statements. Some of these risks, uncertainties and factors include fluctuations in the price of gold, silver and copper; the need to recalculate estimates of resources based on actual production experience; the failure to achieve production estimates; variations in the grade of ore mined; variations in the cost of operations; the availability of qualified personnel; the Company's ability to obtain and maintain all necessary regulatory approvals and licenses; the Company's ability to use cyanide in its mining operations; risks generally associated with mineral exploration and development, including the Company's ability to develop the UMZ deposit, the Copperwood project or the El Valle-Boinas/Carles Mine; the Company's ability to acquire and develop mineral properties and to successfully integrate such acquisitions; the Company's ability to obtain financing when required on terms that are acceptable to the Company; challenges to the Company's interests in its property and mineral rights; current, pending and proposed legislative or regulatory developments or changes in political, social or economic conditions in the countries in which the Company operates; general economic conditions worldwide; and the risks identified in Orvana's Management's Discussion and Analysis for the period ended June 30, 2012 under the heading "Risks and Uncertainties". This list is not exhaustive of the factors that may affect any of the Company's forward-looking statements and reference should also be made to the Company's Annual Information Form for a description of additional risk factors.

Forward-looking statements are based on management's current plans, estimates, projections, beliefs and opinions and, except as required by law, the Company does not undertake any obligation to update forward-looking statements should assumptions related to these plans, estimates, projections, beliefs and opinions change. Readers are cautioned not to put undue reliance on forward-looking statements.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
The Internet of Things is tied together with a thin strand that is known as time. Coincidentally, at the core of nearly all data analytics is a timestamp. When working with time series data there are a few core principles that everyone should consider, especially across datasets where time is the common boundary. In his session at Internet of @ThingsExpo, Jim Scott, Director of Enterprise Strategy & Architecture at MapR Technologies, discussed single-value, geo-spatial, and log time series dat...
There's Big Data, then there's really Big Data from the Internet of Things. IoT is evolving to include many data possibilities like new types of event, log and network data. The volumes are enormous, generating tens of billions of logs per day, which raise data challenges. Early IoT deployments are relying heavily on both the cloud and managed service providers to navigate these challenges. In her session at Big Data Expo®, Hannah Smalltree, Director at Treasure Data, discussed how IoT, Big D...
The Internet of Things promises to transform businesses (and lives), but navigating the business and technical path to success can be difficult to understand. In his session at @ThingsExpo, Sean Lorenz, Technical Product Manager for Xively at LogMeIn, demonstrated how to approach creating broadly successful connected customer solutions using real world business transformation studies including New England BioLabs and more.
The security devil is always in the details of the attack: the ones you've endured, the ones you prepare yourself to fend off, and the ones that, you fear, will catch you completely unaware and defenseless. The Internet of Things (IoT) is nothing if not an endless proliferation of details. It's the vision of a world in which continuous Internet connectivity and addressability is embedded into a growing range of human artifacts, into the natural world, and even into our smartphones, appliances, a...
The Internet of Things will put IT to its ultimate test by creating infinite new opportunities to digitize products and services, generate and analyze new data to improve customer satisfaction, and discover new ways to gain a competitive advantage across nearly every industry. In order to help corporate business units to capitalize on the rapidly evolving IoT opportunities, IT must stand up to a new set of challenges. In his session at @ThingsExpo, Jeff Kaplan, Managing Director of THINKstrateg...
Fundamentally, SDN is still mostly about network plumbing. While plumbing may be useful to tinker with, what you can do with your plumbing is far more intriguing. A rigid interpretation of SDN confines it to Layers 2 and 3, and that's reasonable. But SDN opens opportunities for novel constructions in Layers 4 to 7 that solve real operational problems in data centers. "Data center," in fact, might become anachronistic - data is everywhere, constantly on the move, seemingly always overflowing. Net...
DevOps Summit 2015 New York, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that it is now accepting Keynote Proposals. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long development cycles that produce software that is obsolete...
WebRTC defines no default signaling protocol, causing fragmentation between WebRTC silos. SIP and XMPP provide possibilities, but come with considerable complexity and are not designed for use in a web environment. In his session at @ThingsExpo, Matthew Hodgson, technical co-founder of the Matrix.org, discussed how Matrix is a new non-profit Open Source Project that defines both a new HTTP-based standard for VoIP & IM signaling and provides reference implementations.
"There is a natural synchronization between the business models, the IoT is there to support ,” explained Brendan O'Brien, Co-founder and Chief Architect of Aria Systems, in this SYS-CON.tv interview at the 15th International Cloud Expo®, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
SYS-CON Events announced today Isomorphic Software, the global leader in high-end, web-based business applications, will exhibit at SYS-CON's DevOps Summit 2015 New York, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Isomorphic Software is the global leader in high-end, web-based business applications. We develop, market, and support the SmartClient & Smart GWT HTML5/Ajax platform, combining the productivity and performance of traditional desktop software ...
The definition of IoT is not new, in fact it’s been around for over a decade. What has changed is the public's awareness that the technology we use on a daily basis has caught up on the vision of an always on, always connected world. If you look into the details of what comprises the IoT, you’ll see that it includes everything from cloud computing, Big Data analytics, “Things,” Web communication, applications, network, storage, etc. It is essentially including everything connected online from ha...
The 3rd International Internet of @ThingsExpo, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that its Call for Papers is now open. The Internet of Things (IoT) is the biggest idea since the creation of the Worldwide Web more than 20 years ago.
Connected devices and the Internet of Things are getting significant momentum in 2014. In his session at Internet of @ThingsExpo, Jim Hunter, Chief Scientist & Technology Evangelist at Greenwave Systems, examined three key elements that together will drive mass adoption of the IoT before the end of 2015. The first element is the recent advent of robust open source protocols (like AllJoyn and WebRTC) that facilitate M2M communication. The second is broad availability of flexible, cost-effective ...
How do APIs and IoT relate? The answer is not as simple as merely adding an API on top of a dumb device, but rather about understanding the architectural patterns for implementing an IoT fabric. There are typically two or three trends: Exposing the device to a management framework Exposing that management framework to a business centric logic Exposing that business layer and data to end users. This last trend is the IoT stack, which involves a new shift in the separation of what stuff happe...
Scott Jenson leads a project called The Physical Web within the Chrome team at Google. Project members are working to take the scalability and openness of the web and use it to talk to the exponentially exploding range of smart devices. Nearly every company today working on the IoT comes up with the same basic solution: use my server and you'll be fine. But if we really believe there will be trillions of these devices, that just can't scale. We need a system that is open a scalable and by using ...