BERWICK, Pa., Dec. 28, 2012 /PRNewswire/ -- Unit 2 at the PPL Susquehanna nuclear power plant resumed generating electricity for the power grid Friday (12/28). The unit had been shut down since Dec. 16.
An electrical connection problem caused an automatic shutdown during a routine, scheduled turbine valve test. An unrelated issue with the positioning of a valve on one of the unit's main water pumps during start-up activities extended the out-of-service time.
"We have conducted a detailed review to understand the causes of these events and learn from them," said Timothy S. Rausch, PPL Susquehanna senior vice president and chief nuclear officer. "We have completed repairs, updated procedures and trained plant workers."
Unit 1 at PPL Susquehanna continues operating safely at full power.
The Susquehanna plant, located in Luzerne County about seven miles north of Berwick, is owned jointly by PPL Susquehanna LLC and Allegheny Electric Cooperative Inc. and is operated by PPL Susquehanna LLC.
PPL Susquehanna LLC is one of PPL Corporation's generating affiliates. Headquartered in Allentown, Pa., PPL Corporation (NYSE: PPL) owns or controls through its subsidiaries about 19,000 megawatts of generating capacity in the United States, sells energy in key U.S. markets, and delivers electricity and natural gas to about 10 million customers in the United States and the United Kingdom. More information is available at www.pplweb.com.
SOURCE PPL Susquehanna
Published December 28, 2012 Reads 154
Copyright © 2012 SYS-CON Media, Inc. — All Rights Reserved.
Syndicated stories and blog feeds, all rights reserved by the author.
More Stories By PR Newswire
Copyright © 2007 PR Newswire. All rights reserved. Republication or redistribution of PRNewswire content is expressly prohibited without the prior written consent of PRNewswire. PRNewswire shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.