Dominion Diamond Corporation reports Diavik and Ekati Diamond Mine Fourth Calendar Quarter Production

TORONTO, January 16, 2014 /PRNewswire/ --

Dominion Diamond Corporation (TSX: DDC) (NYSE: DDC) (the "Company") reports Diavik and Ekati Diamond Mine fourth calendar quarter production results.

Diavik Diamond Mine

The fourth calendar quarter of 2013 saw a continuing strong performance from the Diavik Diamond Mine. During the fourth calendar quarter of 2013, the Diavik Diamond Mine produced (on a 100% basis) 2.1 million carats from 0.54 million tonnes of ore processed compared to 1.9 million carats from 0.47 million tonnes of ore processed in the comparable quarter of the prior year.

Processing volumes in the fourth quarter were 16% higher than the prior year's comparable quarter. This was a result of improvements in the mining rates as the underground ramp up progressed throughout the year to full production from all three pipes.

A new mine plan and budget for calendar 2014 is under final review by Rio Tinto plc and the Company. The plan for calendar 2014 foresees Diavik Diamond Mine production (on a 100% basis) of approximately 6.1 million carats from the mining and processing of approximately 1.9 million tonnes of ore. Mining activities will be exclusively underground with approximately 0.7 million tonnes expected to be sourced from A-154 North, approximately 0.8 million tonnes from A-154 South and approximately 0.4 million tonnes from A-418 kimberlite pipes. In addition to the 6.1 million carats produced from underground mining there will be production from reprocessed plant rejects (RPR) and production from the improved recovery of small diamonds. This additional production is not included in the Company's ore reserves, and is therefore incremental. Based on historical recovery rates, the tonnage of this material which is planned to be processed during calendar 2014 would have produced 0.6 million carats from RPR and 0.2 million carats from the improved recovery process.

Ekati Diamond Mine

With the Company's senior management now firmly established in Yellowknife, the Ekati Diamond Mine is performing well. During the fourth calendar quarter of 2013, the Ekati Diamond Mine produced (on a 100% basis) 0.4 million carats from the processing of 0.9 million tonnes of ore from the reserves. Activities through the calendar quarter continued to focus on ore production from the Fox open pit, and Koala and Koala North underground. The Company also recovered 0.1 million carats from the processing of 0.1 million tonnes of coarse ore rejects and diamond bearing kimberlite excavated from satellite bodies in the Misery open pit (referred to as Misery South & Southwest).

A new mine plan and budget for fiscal 2015 is under final review by the Company. In fiscal 2015, the Ekati Diamond Mine expects to process (on a 100% basis) approximately 2.7 million tonnes from the mineral reserve and produce approximately 1.0 million carats. The Company expects to process approximately 1.7 million tonnes from the Fox pipe (including stockpiles) and approximately 1.0 million tonnes split between Koala phase 5 and phase 6 & 7. Additional plant feed to keep the processing plant at capacity for the period will be sourced from additional levels in the Koala North underground (inferred mineral resources), the Misery South and Southwest diamond bearing satellite bodies as well as the stockpile of coarse ore rejects. The Koala North underground, Misery South and Southwest satellite bodies as well as the coarse ore rejects are not included in the Company's reserves and resource statement and are therefore considered incremental to production.

Winter Road, Drilling Programme and Permitting

The Winter Road is expected to open in approximately two weeks and the relevant equipment will be mobilized via that road. The Company is working on a pre-feasibility study for the Jay Cardinal project which it aims to complete in calendar 2014.

The diamond and sonic core drilling programme which will be carried out at the Jay and Cardinal pipes and along alignments for the dikes planned for the proposed development is expected to commence in early-mid February 2014.

Permitting of both the Lynx kimberlite pipe and the Jay-Cardinal kimberlite pipes is proceeding as expected. Dates have been set in early February 2014 for public hearings on Lynx which has advanced directly to the permitting phase. At the same time, public scoping sessions are being held for Jay-Cardinal in order that the upcoming environmental assessment adequately focusses on issues of public interest. In parallel, and in support of the processes laid out by regulators, the Company continues discussions with its community partners in order to design the projects in a manner which minimizes any potential environmental impacts and at the same time maximizes local economic benefit.

Updated Life of Mine Plans

The Company expects to release an updated life-of-mine plan for both the Diavik Diamond Mine and the Ekati Diamond Mine including current estimates for anticipated annual production by pipe and associated operating and capital costs shortly.

Diavik Diamond Mine

For the 2013 calendar year, the Diavik Diamond Mine performed ahead of target, producing (on a 100% basis) 7.2 million carats from 2.1 million tonnes of ore processed compared to production of 7.2 million carats from 2.1 million tonnes of ore processed in the calendar 2012.

DIAVIK DIAMOND MINE PRODUCTION 40% BASIS

    For the three months ended December 31,  For the three months ended December 31,
                    2013                                     2012                    Ore
                 Processed
                   (000s      Carats        Grade    Ore Processed    Carats       Grade
       Pipe       tonnes)     (000s)    (carats/tonne)(000s tonnes)    (000s)(carats/tonne)
    A-154 South     51         220           4.28         67           313        4.66
    A-154 North     69         144           2.10         42            89        2.11
    A-418           94         418           4.46         77           344        4.49
    RPR              2          44              -          0.6          14           -
    Total          216         826       3.66 (a)        187           760        4.01(a)


(a)Grade has been adjusted to exclude RPR

    For the twelve months ended December 31,     For the twelve months ended December 31,
                     2013                                         2012

                     Ore
                  Processed
                    (000s      Carats        Grade    Ore Processed    Carats     Grade
        Pipe       tonnes)     (000s)   (carats/tonne) (000s tonnes)  (000s) (carats/tonne)
    A-154 South      228        976           4.29          166          750       4.52
    A-154 North      288        606           2.11          173          354       2.05
    A-418            326      1,160           3.56          482        1,732       3.59
    RPR                6        155              -            2           55          -
    Total            848      2,897       3.26 (a)          823        2,892       3.45 (a)


(a) Grade has been adjusted to exclude RPR

Cost of Sales and Cash Cost of Production

Based on the current mine plan for the Diavik Diamond Mine for calendar 2014, the Company currently expects its 40% share of the cost of sales for the Diavik Diamond Mine in fiscal 2015 to be approximately $280 million (including depreciation and amortization of approximately $100 million). The Company's 40% share of the cash cost of production at the Diavik Diamond Mine for calendar 2014 is expected to be approximately $155 million at an assumed average Canadian/US dollar exchange rate of $1.05.

Capital Expenditures

The Company currently expects Dominion Diamond Diavik Limited Partnership's 40% share of the planned capital expenditures for the Diavik Diamond Mine in fiscal 2015 to be approximately $20 million, assuming an average Canadian/US dollar exchange rate of $1.05.

Ekati Diamond Mine

During the period from April 10, 2013 to December 31, 2013, the Company (on a 100% basis) has mined a total of 4.2 million tonnes from the Ekati Diamond Mine from reserves with approximately 3.5 million tonnes from the Fox pipe, approximately 0.2 million tonnes sourced from Koala Phase 5, approximately 0.2 million tonnes from Koala Phase 6 & 7, and slightly under 0.3 million tonnes from Koala North. During this period, production (on 100% basis) was 1.1 million carats from the processing of 2.8 million tonnes of ore from the reserves. The Ekati Diamond Mine also produced 0.33 million carats from the processing of 0.30 million tonnes of coarse ore rejects and diamond bearing kimberlite excavated from Misery South & Southwest.

EKATI DIAMOND MINE PRODUCTION 80% BASIS

    For the three months ended December 31, 2013
                             Ore Processed Carats      Grade
    Pipe                     (000s tonnes) (000s)      (carats/tonne)
    Koala Phase 5                 46          19           0.42
    Koala Phase 6                 67          82           1.21
    Koala North                   63          48           0.75
    Fox                          576         157           0.27
    Misery South & Southwest      34          44           1.33
    Coarse Ore Rejects            29          18           0.60
    Total                        815         367           0.45


EKATI DIAMOND MINE PRODUCTION 80% BASIS

    For the period from April 10, 2013 (date of acquisition) to December
    31, 2013
                                Ore Processed    Carats    Grade
    Pipe                        (000s tonnes)    (000s)    (carats/tonne)
    Koala Phase 5                     145        57              0.39
    Koala Phase 6                     156       199              1.27
    Koala North                       187       140              0.75
    Fox                             1,710       514              0.30
    Misery South & Southwest          176       238              1.36
    Coarse Ore Rejects                 63        23              0.37
    Total                           2,437     1,172              0.48


Cost of Sales and Cash Cost of Production

Based on the current mine plan for the Ekati Diamond Mine for fiscal 2015, the Company currently expects cost of sales at the Ekati Diamond Mine (on a 100% basis) in fiscal 2015 to be approximately $520 million (including depreciation and amortization of approximately $125 million). The cash cost of production at the Ekati Diamond Mine for fiscal 2015 is expected to be approximately $360 million (on a 100% basis) at an assumed average Canadian/US dollar exchange rate of $1.05.

Capital Expenditures

The planned capital expenditures for the core zone at the Ekati Diamond Mine for fiscal 2015 (on a 100% basis) are expected to be approximately $195 million at an assumed average Canadian/US dollar exchange rate of $1.05. The planned capital expenditures include approximately $100 million for the continued development of the Misery Pipe, consisting largely of mining costs to achieve ore release, and approximately $55 million towards the development of the Pigeon Pipe.

Pricing

Based on the Company's sales during the fourth calendar quarter of 2013 and the current diamond recovery profile of the Diavik and Ekati processing plants, the Company has modeled the approximate rough diamond price per carat for each of the ore types below. The prices for the diamonds recovered from Misery South and Southwest extension as well as the coarse ore rejects that are not in reserves are expressed as ranges since there is limited sample data available.

                                                                      December
                                                                      2013
                                                                      Average
                                                                      Price
                                                                      per
                    December 2013                                     Carat
                    Average Price per Carat                           (in US
    Diavik Ore Type (in US dollars)         Ekati Ore Type            dollars)
    A-154 South              $140           Koala Phase 5               $350
    A-154 North              $180           Koala Phase 6               $405
    A-418                    $100           Koala North                 $420
    RPR                       $50           Fox                         $305
                                                                       $80 -
                                            Misery South & South West   100
                                                                       $65 -
                                            Coarse Ore Rejects          120


Non-IFRS Measure
This disclosure refers to cash cost of production, a non-IFRS performance measure, in order to provide investors with information about the measure used by management to monitor performance. This information is used to assess how well each of the Diavik Diamond Mine and Ekati Diamond Mine is performing compared to the mine plan and prior periods. Cash cost of production includes mine site operating costs such as mining, processing and administration, but is exclusive of amortization, capital, and exploration and development costs. Cash cost of production does not have any standardized meaning prescribed by IFRS and differs from measures determined in accordance with IRFS. This performance measure is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. This measure is not necessarily indicative of net profit or cash flow from operations as determined by IFRS.

Qualified person
The scientific and technical information contained in this press release has been prepared under the supervision of Mats Heimersson, P. ENG, an employee of the Company and a Qualified Person within the meaning of National Instrument 43-101.

About Dominion Diamond Corporation 
Dominion Diamond Corporation is a Canadian diamond mining company with ownership interests in two of the world's most valuable diamond mines. Both mines are located in the low political risk environment of the Northwest Territories of Canada. The Company is the fourth largest diamond producer by value globally and the largest diamond mining company by market capitalization, listed on the Toronto and New York Stock Exchanges.

The Company operates the Ekati Diamond Mine through its 80% ownership as well as a 58.8% ownership in the surrounding areas containing additional resources. It also sells diamonds from its 40% ownership in the Diavik Diamond Mine.

For more information, please visit http://www.ddcorp.ca

Forward-Looking Information
Certain information included herein, including information about mining activities, estimated production from the Company's mining properties, cost of sales and cash cost of production estimates and planned capital expenditures, constitutes forward-looking information or statements within the meaning of applicable securities laws. Forward-looking information is based on certain factors and assumptions including, among other things, the current mine plans for each of the Diavik Diamond Mine and the Ekati Diamond Mine; mining, production, construction and exploration activities at the Company's mineral properties; currency exchange rates; and world and US economic conditions. Forward-looking information is subject to certain factors, including risks and uncertainties, which could cause actual results to differ materially from what the Company currently expects. These factors include, among other things, the uncertain nature of mining activities, including risks associated with underground construction and mining operations, risks associated with joint venture operations, including risks associated with the inability to control the timing and scope of future capital expenditures, the risk that the operator of the Diavik Diamond Mine may make changes to the mine plan and other risks arising because of the nature of joint venture activities, risks associated with the remote location of and harsh climate at the Company's mineral property sites, risks resulting from the Eurozone financial crisis, risks associated with regulatory requirements, the risk of fluctuations in diamond prices and changes in US and world economic conditions, the risk of fluctuations in the Canadian/US dollar exchange rate and cash flow and liquidity risks. Actual results may vary from the forward-looking information. Readers are cautioned not to place undue importance on forward-looking information, which speaks only as of the date of this disclosure, and should not rely upon this information as of any other date. While the Company may elect to, it is under no obligation and does not undertake to, update or revise any forward-looking information, whether as a result of new information, further events or otherwise at any particular time, except as required by law. Additional information concerning factors that may cause actual results to materially differ from those in such forward-looking statements is contained in the Company's filings with Canadian and United States securities regulatory authorities and can be found athttp://www.sedar.comandhttp://www.sec.gov, respectively.

Mr. Richard Chetwode, Vice President, Corporate Development - +44 (0) 7720-970-762 or [email protected]
Ms. Kelley Stamm, Manager, Investor Relations - (416) 205-4380 or [email protected]
(DDC. DDC)


More Stories By PR Newswire

Copyright © 2007 PR Newswire. All rights reserved. Republication or redistribution of PRNewswire content is expressly prohibited without the prior written consent of PRNewswire. PRNewswire shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.

@CloudExpo Stories
The Internet of Things will greatly expand the opportunities for data collection and new business models driven off of that data. In her session at Internet of @ThingsExpo, Esmeralda Swartz, CMO of MetraTech, will discuss how for this to be effective you not only need to have infrastructure and operational models capable of utilizing this new phenomenon, but increasingly service providers will need to convince a skeptical public to participate. Get ready to show them the money! Speaker Bio: ...
Compute virtualization has been transformational, yet security policy implementation and enforcement has lagged behind in agility and automation. There are a number of key considerations when implementing policy in private and hybrid clouds. In his session at 15th Cloud Expo, Holland Barry, VP of Technology at Catbird, will discuss the impact of this new paradigm and what organizations can do today to safely move to software-defined network and compute architectures, including: How normal ope...
Samsung VP Jacopo Lenzi, who headed the company's recent SmartThings acquisition under the auspices of Samsung's Open Innovaction Center (OIC), answered a few questions we had about the deal. This interview was in conjunction with our interview with SmartThings CEO Alex Hawkinson. IoT Journal: SmartThings was developed in an open, standards-agnostic platform, and will now be part of Samsung's Open Innovation Center. Can you elaborate on your commitment to keep the platform open? Jacopo Lenzi: S...
How do APIs and IoT relate? The answer is not as simple as merely adding an API on top of a dumb device, but rather about understanding the architectural patterns for implementing an IoT fabric. There are typically two or three trends: Exposing the device to a management framework Exposing that management framework to a business centric logic • Exposing that business layer and data to end users. This last trend is the IoT stack, which involves a new shift in the separation of what stuff hap...
SYS-CON Events announced today that SOA Software, an API management leader, will exhibit at SYS-CON's 15th International Cloud Expo®, which will take place on November 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA. SOA Software is a leading provider of API Management and SOA Governance products that equip business to deliver APIs and SOA together to drive their company to meet its business strategy quickly and effectively. SOA Software’s technology helps businesses to accel...
SYS-CON Events announced today that Utimaco will exhibit at SYS-CON's 15th International Cloud Expo®, which will take place on November 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA. Utimaco is a leading manufacturer of hardware based security solutions that provide the root of trust to keep cryptographic keys safe, secure critical digital infrastructures and protect high value data assets. Only Utimaco delivers a general-purpose hardware security module (HSM) as a customiz...
Almost everyone sees the potential of Internet of Things but how can businesses truly unlock that potential. The key will be in the ability to discover business insight in the midst of an ocean of Big Data generated from billions of embedded devices via Systems of Discover. Businesses will also need to ensure that they can sustain that insight by leveraging the cloud for global reach, scale and elasticity.
SYS-CON Events announced today that ElasticBox is holding a Hackathon at DevOps Summit, November 6 from 12 pm -4 pm at the Santa Clara Convention Center in Santa Clara, CA. You can enter as an individual or team of up to 10 developers. A New Star Is Born Every Month! All completed ElasticBoxes will then be sent to a judging panel - 12 winners will be featured on the ElasticBox website in 2015. All entrants will receive five full enterprise licenses for one year + ElasticBox headphones + Elasti...
Once the decision has been made to move part or all of a workload to the cloud, a methodology for selecting that workload needs to be established. How do you move to the cloud? What does the discovery, assessment and planning look like? What workloads make sense? Which cloud model makes sense for each workload? What are the considerations for how to select the right cloud model? And how does that fit in with the overall IT tranformation? In his session at 15th Cloud Expo, John Hatem, head of V...
Cloud services are the newest tool in the arsenal of IT products in the market today. These cloud services integrate process and tools. In order to use these products effectively, organizations must have a good understanding of themselves and their business requirements. In his session at 15th Cloud Expo, Brian Lewis, Principal Architect at Verizon Cloud, will outline key areas of organizational focus, and how to formalize an actionable plan when migrating applications and internal services to...
SAP is delivering break-through innovation combined with fantastic user experience powered by the market-leading in-memory technology, SAP HANA. In his General Session at 15th Cloud Expo, Thorsten Leiduck, VP ISVs & Digital Commerce, SAP, will discuss how SAP and partners provide cloud and hybrid cloud solutions as well as real-time Big Data offerings that help companies of all sizes and industries run better. SAP launched an application challenge to award the most innovative SAP HANA and SAP ...
Ixia develops amazing products so its customers can connect the world. Ixia helps its customers provide an always-on user experience through fast, secure delivery of dynamic connected technologies and services. Through actionable insights that accelerate and secure application and service delivery, Ixia's customers benefit from faster time to market, optimized application performance and higher-quality deployments.
SYS-CON Events announced today that Calm.io has been named “Bronze Sponsor” of DevOps Summit Silicon Valley, which will take place on November 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA. Calm.io is a cloud orchestration platform for AWS, vCenter, OpenStack, or bare metal, that runs your CL tools puppet, Chef, shell, git, Jenkins, nagios, and will soon support New Relic and Docker. It can run hosted, or on premise and provides VM automation / expiry, self-service portals,...
In her General Session at 15th Cloud Expo, Anne Plese, Senior Consultant, Cloud Product Marketing, at Verizon Enterprise, will focus on finding the right mix of renting vs. buying Oracle capacity to scale to meet business demands, and offer validated Oracle database TCO models for Oracle development and testing environments. Anne Plese is a marketing and technology enthusiast/realist with over 19+ years in high tech. At Verizon Enterprise, she focuses on driving growth for the Verizon Cloud pla...
SYS-CON Events announced today that Aria Systems, the recurring revenue expert, has been named "Bronze Sponsor" of SYS-CON's 15th International Cloud Expo®, which will take place on November 4-6, 2014, at the Santa Clara Convention Center in Santa Clara, CA. Aria Systems helps leading businesses connect their customers with the products and services they love. Industry leaders like Pitney Bowes, Experian, AAA NCNU, VMware, HootSuite and many others choose Aria to power their recurring revenue bu...
The Internet of Things (IoT) is going to require a new way of thinking and of developing software for speed, security and innovation. This requires IT leaders to balance business as usual while anticipating for the next market and technology trends. Cloud provides the right IT asset portfolio to help today’s IT leaders manage the old and prepare for the new. Today the cloud conversation is evolving from private and public to hybrid. This session will provide use cases and insights to reinforce t...
As Platform as a Service (PaaS) matures as a category, developers should have the ability to use the programming language of their choice to build applications and have access to a wide array of services. Bluemix is IBM's open cloud development platform that enables users to easily build cloud-based, creative mobile and web applications without having to spend large amounts of time and resources on configuring infrastructure and multiple software licenses. In this track, you will learn about the...
Blue Box has closed a $10 million Series B financing. The round was led by a strategic investor and included participation from prior investors including Voyager Capital and Founders Collective, as well as the Blue Box executive team. This round follows a $4.3 million Series A closed in December of 2012 and led by Voyager Capital. In May of this year, the company announced general availability of its private cloud as a service offering, Blue Box Cloud. Since that release, the company has dem...
SYS-CON Events announced today that Verizon has been named "Gold Sponsor" of SYS-CON's 15th International Cloud Expo®, which will take place on November 4-6, 2014, at the Santa Clara Convention Center in Santa Clara, CA. Verizon Enterprise Solutions creates global connections that generate growth, drive business innovation and move society forward. With industry-specific solutions and a full range of global wholesale offerings provided over the company's secure mobility, cloud, strategic network...
SimpleECM is the only platform to offer a powerful combination of enterprise content management (ECM) services, capture solutions, and third-party business services providing simplified integrations and workflow development for solution providers. SimpleECM is opening the market to businesses of all sizes by reinventing the delivery of ECM services. Our APIs make the development of ECM services simple with the use of familiar technologies for a frictionless integration directly into web applicat...