Black Iron Updates Bankable Feasibility Study Showing 48% IRR, 2 Year Payback and US$3.3 Billion NPV for Shymanivske Project

Feasibility study outlines an operation producing 9.9 million tonnes per year of high-grade 68% iron ore concentrate, projecting a 48% IRR, 2 year payback and a US$3.3 billion NPV at an 8% discount rate

TORONTO, ONTARIO -- (Marketwired) -- 01/23/14 -- Black Iron Inc. ("Black Iron" or the "Company") (TSX:BKI) (FRANKFURT:BIN) has updated its current Bankable Feasibility Study ("BFS"), incorporating pilot plant test work, completed on its Shymanivske Iron Ore Project located in Krivoy Rog, Ukraine (the "Project"). The updated BFS outlines an operation producing 9.9 million tonnes per year of high-grade 68% iron ore concentrate, projecting a 48% internal rate of return ("IRR"), two year payback and a US$3.3 billion net present value ("NPV") at an 8% discount rate.

The primary reason for updating the previous report filed in December 2012 is to include results from pilot plant test work conducted throughout 2013, which resulted in an optimized process design and layout, along with revised infrastructure usage rates confirmed through several recently signed protocols of intent. The most significant changes implemented are: changing from dry cobbing to more efficient wet cobbing at a finer particle size resulting in an increase from 10% to 40% rejection of waste rock prior to grinding; elimination of the second grinding stage resulting in a 14% reduction in total operational running active power; reducing the plant footprint through a more optimal layout; and an 8% increase in iron ore concentrate production from 9.2 to 9.9 million tonnes per year with essentially no change in capital cost.

Financial metrics contained in the BFS report are shown on a pre and after tax basis and in both cases are inclusive of royalties. Ukraine has a corporate tax rate of 16% effective January 1, 2014 and a mining royalty rate of $0.09 per tonne of ore mined (less than 1%) payable to the State.

The Table below summarizes the key elements of the BFS:

High-Grade 68% Concentrate (all currency is US$)


----------------------------------------------------------------------------
Measured and Indicated Resources (at 31.6% Total Fe)(i)  646 Mt             
----------------------------------------------------------------------------
Proven and Probable Reserves (at 31.1% Total Fe)(i)      449 Mt             
----------------------------------------------------------------------------
Annual Production Rate (average life of mine, post ramp- 9.9 Mt             
up year)                                                                    
----------------------------------------------------------------------------
Estimated Mine Life (based on Proven and Probable        14 years           
Reserves only)                                                              
----------------------------------------------------------------------------
Final Product Iron Grade (Fine Iron Ore Concentrate)     68% Fe             
----------------------------------------------------------------------------
Projected Plant Start-up and Commissioning               Q4 2016            
----------------------------------------------------------------------------
Projected Commencement of Revenue Generation             Q1 2017            
----------------------------------------------------------------------------
Long Term CFR Benchmark Iron Ore Concentrate Price       $95 /t             
Estimate (62% Fe)                                                           
----------------------------------------------------------------------------
Total Estimated Capital Costs (excluding sustaining      $1,097 million     
capital)                                                                    
----------------------------------------------------------------------------
Life of Mine FOB OPEX (Beneficiation, Mine,              $44.54 /t          
Transportation & Loading)                                $29.64 /t          
Mine Gate OPEX (Beneficiation & Mine)                                       
----------------------------------------------------------------------------
Average Annual Cash Flow (pre-tax)                       $630 million       
Average Annual Cash Flow (after-tax)                     $536 million       
----------------------------------------------------------------------------
NPV at 8% discount (pre-tax)                             $3.3 billion       
NPV at 8% discount (after-tax)                           $2.6 billion       
----------------------------------------------------------------------------
IRR (pre-tax)                                            48.0%              
IRR (after-tax)                                          39.1%              
----------------------------------------------------------------------------
Projected Years to Payback (at 8% Discount Rate, pre-    2.0 years          
tax)                                                     2.5 years          
Projected Years to Payback (at 8% Discount Rate, after-                     
tax)                                                                        
----------------------------------------------------------------------------
                                                                            
(i) See "About Black Iron" section at end of this press release             

Matt Simpson, Black Iron's President and CEO, commented, "The operation outlined by this BFS for the Shymanivske Project continues to clearly illustrate the potential for a high-value, low net cost iron ore development project. The optimized process design and layout developed for this new study, based on significant pilot scale test work, results in increased annual iron ore concentrate production of approximately 8%, while holding initial capital costs virtually unchanged. As a result of these improvements, the Project's access to significant existing infrastructure (railway, power lines and port), and the availability of competitively-priced skilled labour, the BFS continues to show extremely attractive and robust economics."

Financial Sensitivities at Various Discount Rates


----------------------------------------------------------------------------
                           (pre-tax)                    (after-tax)         
----------------------------------------------------------------------------
IRR (pre-tax)                48.0%                         39.1%            
----------------------------------------------------------------------------
                               NPV     Payback               NPV     Payback
Discount Rate       US$ (Millions)     (Years)    US$ (Millions)     (Years)
----------------------------------------------------------------------------
0%                $          7,165         1.8  $          5,877         2.1
----------------------------------------------------------------------------
6%                $          3,997         1.9  $          3,177         2.4
----------------------------------------------------------------------------
8%                $          3,304         2.0  $          2,609         2.5
----------------------------------------------------------------------------
10%               $          2,756         2.1  $          2,148         2.6
----------------------------------------------------------------------------

The Project has favourable economic potential across a range of discount rates. The operations outlined in this BFS are projected to generate over U.S. $1,216 million in average annual revenue over the life of mine.

The life of mine strip ratio is estimated at 1.64:1, which is essentially unchanged from the December 2012 reported value of 1.63:1. On the basis of the metallurgical test and beneficiation plant design work completed for this BFS, it is estimated that the 449 million tonnes of reserves will result in a project life of 14 years based on the average 9.9 million tonnes per year iron ore concentrate production rate. The Company believes that additional exploration and definition drilling work have the potential to expand the existing resource and upgrade the 188 Mt of Inferred mineral resources to the Measured and Indicated classification, potentially adding up to five years to the Project life. With successful exploration in the North end of Shymanivske and the addition of resources from the nearly adjacent Zelenivske Project, Black Iron expects to be able to support an even higher annual production rate through a potential second phase expansion, which would be expected to further increase the Project NPV.

George Mover, Black Iron's Chief Operating Officer, added, "We are pleased with the level of detailed engineering proficiency and precision that went into this BFS. Through this process, we confirmed and implemented several improvements to the work completed in the previous BFS study. As a result, we are now considering an initial operation with 8% higher annual production, relatively unchanged initial capital requirements, and only a modest 1.3% increase in operating costs relative to our previous study. The updated operating costs are inclusive of firm letters of intent signed with several infrastructure and utility service providers and were benchmarked against our development partner's actual operating experience. The Project's capital intensity is improving, positioning it even lower into the first quartile of worldwide development projects that should bode well to source project financing; particularly when coupled with our relatively low operating cost, and proximity to end-user markets of Turkey, Middle East and Europe."

Details and Assumptions

The total capital expenditure to develop the mine, concentrator and infrastructure tie-ins is estimated at U.S. $1,097 million to produce 9.9 million tonnes per year of high-grade 68% iron ore concentrate. The capital cost estimate excludes the sustaining capital cost of U.S. $483 million spread over the life of mine. Assessment of the preferred port facility, backed up by a formal protocol (letter) of intent, confirms that sufficient capacity exists for the planned production.


----------------------------------------------------------------------------
Summary of Estimated Initial Capital Costs                 (US$ in Millions)
----------------------------------------------------------------------------
Mine                                                                     162
----------------------------------------------------------------------------
Beneficiation Plant                                                      475
----------------------------------------------------------------------------
Tailings and Waste                                                        21
----------------------------------------------------------------------------
Project Infrastructure                                                   113
----------------------------------------------------------------------------
Project In-directs (mainly EPCM)                                         102
----------------------------------------------------------------------------
Owner's Costs (includes land acquisition)                                 81
----------------------------------------------------------------------------
Contingencies (15%)                                                      143
----------------------------------------------------------------------------
TOTAL                                                                  1,097
----------------------------------------------------------------------------

The 15% contingency estimate includes a 5% design allowance. The total average Freight On Board operating costs over 14 years are estimated at U.S. $44.54 per tonne of high grade 68% iron ore concentrate broken out as follows:


----------------------------------------------------------------------------
Summary of Estimated Operating Costs                US$/tonne of Concentrate
                                                                            
                                                        (Average Mine Life )
----------------------------------------------------------------------------
Mine                                              $                    15.46
----------------------------------------------------------------------------
Beneficiation Plant                               $                    12.50
----------------------------------------------------------------------------
Tailings & Waste                                  $                     0.08
----------------------------------------------------------------------------
Environmental                                     $                     0.26
----------------------------------------------------------------------------
Infrastructure (primarily rail & port)            $                    15.65
----------------------------------------------------------------------------
General & Administration                          $                     0.59
----------------------------------------------------------------------------
      TOTAL                                       $                    44.54
----------------------------------------------------------------------------

Consistent with practice in the industry, this BFS has been prepared with an engineering accuracy of +/-15%.

Currency Sensitivity

For the purpose of the BFS an exchange rate of 8.2 UAH per US$ has been used for the CAPEX (up to January 2016) and 9.5 UAH per US$ for the OPEX and Sustaining Capital (2017 and beyond) based on review of several economic forecasts. Variations in the exchange rates from year 2016 onward impact the financial analysis as follows:

Impact of Ukraine Hryvna Exposure - BFS Currency Sensitivity (US$)


----------------------------------------------------------------------------
Exchange Rate as of year 2016 onward                (UAH/US$)               
                                    ----------------------------------------
                                         8:1     9:1   9.5:1    10:1    11:1
----------------------------------------------------------------------------
NPV @ 8% discount                                                           
 pre-tax (billion)                    $  3.2  $  3.3  $  3.3  $  3.3  $  3.4
 after-tax (billion)                  $  2.5  $  2.6  $  2.6  $  2.6  $  2.7
----------------------------------------------------------------------------
Total Estimated Capital Cost                                                
 (million)                            $ 1097  $ 1097  $ 1097  $ 1097  $ 1097
----------------------------------------------------------------------------
Estimated Operating Cost (per tonne)  $47.71  $45.48  $44.54  $43.70  $42.24
----------------------------------------------------------------------------
Average Annual Cash Flow                                                    
 pre-tax (million)                    $  575  $  586  $  590  $  594  $  601
 after-tax (million)                  $  494  $  502  $  506  $  509  $  515
----------------------------------------------------------------------------

Updated Bankable Feasibility Study Report

The updated BFS has been prepared in accordance with the guidelines of National Instrument 43-101 by the independent firms of Lycopodium Minerals Canada Ltd.; Soutex Mineral & Metallurgical Consultants; Watts, Griffis and McOuat Limited; and P&E Mining Consultants Inc. The final BFS technical report, which will also include the current mineral resource and reserve estimate, will be filed on SEDAR within 45 days of the publication of this news release.

Analyst and Shareholder Conference Call

Black Iron will host a conference call today, January 23, 2014, at 8:30 a.m., EST (1:30 p.m., GMT and 3:30 p.m., EET) to discuss the updated BFS results. To participate in the call please dial the following:

International: +1 647 788 4901

Toll Free (North America): 1 877 201 0168

To register and listen to the webcast of the call, please go to Black Iron's website at www.blackiron.com.

Qualified Persons

The contents of this press release have been prepared under the supervision of and reviewed and approved by Qualified Persons, as follows:


--  Balaji Thangavel, P.Eng., Mauro Batista, P.Eng. and Enayat Shahrokni,
    P.Eng., Lycopodium Minerals Canada Ltd., QP for the Plant
    Infrastructure, CAPEX, and OPEX; 
    
--  Daniel Roy, P.Eng, Soutex Inc., QP for Metallurgical testing and Process
    design; 
    
--  Michael Kociumbas, P.Geo. and Rick Risto, P.Geo., Watts, Griffis and
    McOuat Limited, QPs for mineral resources estimate and QA/QC and data
    verification; 
    
--  Eugene Puritch, P.Eng., P&E Mining Consultants Inc., QP for the mine
    engineering aspects and the mineral reserves estimate. 

These persons are Qualified Persons as defined by NI 43-101, are independent of Black Iron, and have reviewed the content of this press release.

About Black Iron

Black Iron is an iron ore exploration and development company, advancing its 100 percent-owned Shymanivske project located in Kryviy Rih, Ukraine. This project contains an NI 43-101 compliant resource, with 645.8 Mt Measured and Indicated mineral resources, consisting of 355.1 Mt Measured mineral resources grading 32.0% Total iron and 19.5% Magnetic iron, and Indicated mineral resources of 290.7 Mt grading 31.1% Total iron and 17.9% Magnetic iron, using a cut-off grade of 10% Magnetic iron. Additionally, the project contains 188.3 Mt of Inferred mineral resources grading 30.1% Total iron and 18.4% Magnetic iron. The project is surrounded by five other operating mines, including ArcelorMittal's iron ore complex. The Company believes that existing infrastructure, including access to power, rail and port facilities, will allow for a quick development timeline to production. Further, the Company holds an exploration permit for the adjacent Zelenivske project, which it intends to further explore to determine its potential. Please visit the Company's website at www.blackiron.com or write us at [email protected] for more information.

Forward-Looking Information

This press release contains forward-looking information which may include, but is not limited to, statements about the results of the BFS and the development potential of the Company and its project; the timing and amount of future exploration and development of the project; and the future financial or operating performance of the Company and its projects. Often, but not always, forward-looking information can be identified by the use of words such as "plans," "expects," "is expected," "budget," "scheduled," "estimates," "forecasts," "intends," "anticipates" or "believes" or variations (including negative variations) of such words and phrases, or by the use of words or phrases that state that certain actions, events or results "may," "could," "would," "might" or "will" be taken, occur or be achieved.

Forward-looking information is based on certain assumptions and analyses made by the Company and based on known facts at the time. Forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company and/or its subsidiaries to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information contained in this press release, including, without limitation, those described in the Company's public disclosure documents which may be found under the Company's profile on SEDAR. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in such forward-looking information, there may be other factors that may cause actions, events or results to differ from those anticipated, estimated or intended. Should one or more of these risks or uncertainties materialize, or should assumptions underlying such forward-looking information prove incorrect, actual results, performance or achievements may vary materially from those expressed or implied by the forward-looking information contained in this press release. The forward-looking information contained herein is made as of the date of this press release and the Company disclaims any obligation to update or review such information or statements, whether as a result of new information, future events or results or otherwise, except as required by law.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
SYS-CON Events announced today that MetraTech, now part of Ericsson, has been named “Silver Sponsor” of SYS-CON's 16th International Cloud Expo®, which will take place on June 9–11, 2015, at the Javits Center in New York, NY. Ericsson is the driving force behind the Networked Society- a world leader in communications infrastructure, software and services. Some 40% of the world’s mobile traffic runs through networks Ericsson has supplied, serving more than 2.5 billion subscribers.
How does one bridge the gap between traditional enterprise storage infrastructures and the private, hybrid, and public cloud? In his session at 15th Cloud Expo, Dan Pollack, Chief Architect of Storage Operations at AOL Inc., examed the workload differences and required changes to reuse existing knowledge and components when building and using a cloud infrastructure. He also looked into the operational considerations, tool requirements, and behavioral changes required for private cloud storage s...
Software is eating the world. Companies that were not previously in the technology space now find themselves competing with Google and Amazon on speed of innovation. As the innovation cycle accelerates, companies must embrace rapid and constant change to both applications and their infrastructure, and find a way to deliver speed and agility of development without sacrificing reliability or efficiency of operations. In her Day 2 Keynote DevOps Summit, Victoria Livschitz, CEO of Qubell, discussed...
The speed of product development has increased massively in the past 10 years. At the same time our formal secure development and SDL methodologies have fallen behind. This forces product developers to choose between rapid release times and security. In his session at DevOps Summit, Michael Murray, Director of Cyber Security Consulting and Assessment at GE Healthcare, examined the problems and presented some solutions for moving security into the DevOps lifecycle to ensure that we get fast AND ...
The 5th International DevOps Summit, co-located with 17th International Cloud Expo – being held November 3-5, 2015, at the Santa Clara Convention Center in Santa Clara, CA – announces that its Call for Papers is open. Born out of proven success in agile development, cloud computing, and process automation, DevOps is a macro trend you cannot afford to miss. From showcase success stories from early adopters and web-scale businesses, DevOps is expanding to organizations of all sizes, including the...
Cloud Expo, Inc. has announced today that Andi Mann returns to DevOps Summit 2015 as Conference Chair. The 4th International DevOps Summit will take place on June 9-11, 2015, at the Javits Center in New York City. "DevOps is set to be one of the most profound disruptions to hit IT in decades," said Andi Mann. "It is a natural extension of cloud computing, and I have seen both firsthand and in independent research the fantastic results DevOps delivers. So I am excited to help the great team at ...
SYS-CON Events announced today that BMC will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. BMC delivers software solutions that help IT transform digital enterprises for the ultimate competitive business advantage. BMC has worked with thousands of leading companies to create and deliver powerful IT management services. From mainframe to cloud to mobile, BMC pairs high-speed digital innovation with robust...
Discussions about cloud computing are evolving into discussions about enterprise IT in general. As enterprises increasingly migrate toward their own unique clouds, new issues such as the use of containers and microservices emerge to keep things interesting. In this Power Panel at 16th Cloud Expo, moderated by Conference Chair Roger Strukhoff, panelists will address the state of cloud computing today, and what enterprise IT professionals need to know about how the latest topics and trends affec...
Move from reactive to proactive cloud management in a heterogeneous cloud infrastructure. In his session at 16th Cloud Expo, Manoj Khabe, Innovative Solution-Focused Transformation Leader at Vicom Computer Services, Inc., will show how to replace a help desk-centric approach with an ITIL-based service model and service-centric CMDB that’s tightly integrated with an event and incident management platform. Learn how to expand the scope of operations management to service management. He will al...
Working with Big Data is challenging, especially when decision makers depend on market insights and intelligence from your data but don't have quick access to it or find it unusable. In their session at 6th Big Data Expo, Ian Khan, Global Strategic Positioning & Brand Manager at Solgenia; Zel Bianco, President, CEO and Co-Founder of Interactive Edge of Solgenia; and Ermanno Bonifazi, CEO & Founder at Solgenia, discussed how a revolutionary cloud-based BI along with mobile analytics is already c...
The world is at a tipping point where the technology, the device and global adoption are converging to such a point that we will see an explosion of a world where smartphone devices not only allow us to talk to each other, but allow for communication between everything – serving as a central hub from which we control our world – MediaTek is at the heart of both driving this and allowing the markets to drive this reality forward themselves. The next wave of consumer gadgets is here – smart, con...
Hardware will never be more valuable than on the day it hits your loading dock. Each day new servers are not deployed to production the business is losing money. While Moore's Law is typically cited to explain the exponential density growth of chips, a critical consequence of this is rapid depreciation of servers. The hardware for clustered systems (e.g., Hadoop, OpenStack) tends to be significant capital expenses. In his session at Big Data Expo, Mason Katz, CTO and co-founder of StackIQ, disc...
Enterprises are fast realizing the importance of integrating SaaS/Cloud applications, API and on-premises data and processes, to unleash hidden value. This webinar explores how managers can use a Microservice-centric approach to aggressively tackle the unexpected new integration challenges posed by proliferation of cloud, mobile, social and big data projects. Industry analyst and SOA expert Jason Bloomberg will strip away the hype from microservices, and clearly identify their advantages and d...
Software Development Solution category in The 2015 American Business Awards, and will ultimately be a Gold, Silver, or Bronze Stevie® Award winner in the program. More than 3,300 nominations from organizations of all sizes and in virtually every industry were submitted this year for consideration. "We are honored to be recognized as a leader in the software development industry by the Stevie Awards judges," said Steve Brodie, CEO of Electric Cloud. "We introduced ElectricFlow and our Deploy app...
Containers Expo Blog covers the world of containers, as this lightweight alternative to virtual machines enables developers to work with identical dev environments and stacks. Containers Expo Blog offers top articles, news stories, and blog posts from the world's well-known experts and guarantees better exposure for its authors than any other publication. Bookmark Containers Expo Blog ▸ Here Follow new article posts on Twitter at @ContainersExpo