Bear Creek Files Notice of Intent to Arbitrate with Peruvian Government in Connection with the Santa Ana Project; Six Month Consultation Period Begins

VANCOUVER, Feb. 7, 2014 /PRNewswire/ - Bear Creek Mining (TSX Venture: BCM) ("Bear Creek" or the "Company") announces that it delivered to the Peruvian Minister of Economy and Finance, on February 6, 2014, a Notice of Intent to Submit a Claim to Arbitration ("Notice of Intent"), under the Free Trade Agreement between Canada and Peru ("Canada-Peru FTA").  The dispute arises out of the enactment by the Peruvian government on June 25, 2011, of Supreme Decree 032 rescinding the Company's rights to operate the Santa Ana Project and which resulted in a complete stoppage of activities at Santa Ana and significant damages to the Company.  Peru's actions constitute violations of the Canada-Peru FTA, Peruvian and international law.

The Notice of Intent is necessary in order to preserve the Company's rights to initiate arbitration should a resolution with the Peruvian government not be reached.  The filing of the Notice of Intent also initiates a six-month consultation period between the parties during which time they are to continue to attempt to amicably settle the dispute.  If no amicable settlement is reached in that six-month period, the Company may then initiate international arbitration proceedings against Peru in accordance with the Canada-Peru FTA.

Based upon outside counsel's opinion of the strength of the Company's legal position, and ongoing discussions with the Peruvian government and local communities, the Company remains optimistic that a settlement of the dispute in relation to the Santa Ana Project will be reached to avoid international arbitration.  The Ministry of Energy and Mines recently issued a public statement that Peru wants to reach an amicable  solution through dialogue with the Company.  The Company's desire is for both parties to reach a mutually acceptable favorable solution, as evidenced by the numerous proposals submitted by Bear Creek to the Peruvian government to date, with a view to allowing the Company to resume its development of the Santa Ana Project for the benefit of our shareholders, the local communities and the Peruvian nation as a whole.  If such a solution is not achieved within the next six months, the Company expects it will have no alternative but to pursue its claims before an international tribunal and seek full compensation for damages the Company has suffered as a result of Peru's acts.

The Santa Ana Project is located in the Puno Region of Peru and contains Proven and Probable Mineral Reserves totaling 63.2 million ounces of silver. Bear Creek acquired the mining concessions in full compliance with Peruvian law, as is confirmed by Supreme Decree 083, enacted by the President of Peru and the Council of Ministers on November 29, 2007.  Bear Creek initiated exploration work in early 2008, and undertook a comprehensive Environmental and Social Impact Assessment ("ESIA") shortly thereafter.  The ESIA, which the Peruvian government suspended on June 1, 2011, remains on standby.  The Company has stated its willingness to complete the ESIA process, including demonstration of social license, and carry out the other steps required to reach commercial production as quickly as possible.  The Santa Ana Project, which is widely supported by the local communities surrounding the proposed mine site, will create 2,500 direct and indirect jobs in the southern Puno Region, and bring important infrastructure improvements to the area.  The Santa Ana Project is also expected to provide US$330 million in federal taxes, much of which benefit local communities. 

Corani Update

The Company's Corani silver-lead-zinc project (the "Corani Project") enjoys continued strong community support, and remains on track for advancement following the approval of its ESIA in September 2013.  Numerous public statements by the President of Peru and Cabinet Ministers have expressed strong support for the advancement of the Corani Project and the government has worked in concert with the Company in order to fund local infrastructure projects.  However, the successful resolution of the Santa Ana dispute is a critical component to the Company's ability to raise financing for, and ultimately the potential success of, the Corani Project.

Recent media in Peru have reported false accusations by an individual distant from our communities wherein Bear Creek Mining officials supposedly paid locally elected officials based on an alleged document showing an agreement between the company and politicians in the Corani District.   The alleged document is falsified from our duly registered, official agreement as disclosed in April, 2013 (see news release dated April 14, 2013).  Police in Peru are investigating these claims and Bear Creek has both encouraged and is cooperating fully in this process.  We continue to work with our partner communities under the legal agreement executed in April 2013 and for which the Company is extremely proud of its transparent foundation structure that delivers long-term benefits to our communities. This is the only agreement to make social payments to our local communities or its members that exists and, in the interest of transparency; we have posted the agreement in both Spanish and English to the Bear Creek website. http://www.bearcreekmining.com/s/corani_project.asp?ReportID=622470

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cautionary Note regarding Forward-Looking Statements:
This document contains "forward-looking information" within the meaning of Canadian securities legislation and "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995.  This information and these statements, referred to herein as "forward-looking statements" are made as of the date of this news release or as of the date of the effective date of information described in this news release, as applicable.  Forward-looking statements relate to future events or future performance and reflect current estimates, predictions, expectations or beliefs regarding future events and include, without limitation, statements with respect to (i) the Company's plans to continue discussions with the Peruvian government and local communities for a settlement of the dispute in relation to the Santa Ana Project, (ii) the Company's plans to pursue any claims with regard to its projects in Peru, including, without limitation, any claims before an international tribunal, (iii) the Company's intentions to complete any environmental and social impact assessment, and (iv) the planned development of the Corani and Santa Ana projects, including the timing thereof.  Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as "expects", "anticipates", "plans", "projects", "estimates", "envisages", "assumes", "intends", "strategy", "goals", "objectives" or variations thereof or stating that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be forward-looking statements.

By their very nature, forward-looking statements involve inherent risks and uncertainties, both general and specific, and risks exist that estimates, forecasts, projections and other forward-looking statements will not be achieved or that assumptions do not reflect future experience. We caution readers not to place undue reliance on these forward-looking statements as a number of important factors could cause the actual outcomes to differ materially from the beliefs, plans, objectives, expectations, anticipations, estimates assumptions and intentions expressed in such forward-looking statements. These risk factors may be generally stated as the risk that the assumptions and estimates expressed above do not occur, but specifically include, without limitation, risks relating to variations in the mineral content within the material identified as mineral reserves and mineral resources from that predicted; variations in rates of recovery and extraction; developments in world metals and minerals markets; risks relating to fluctuations in the Canadian dollar relative to other currencies; increases in the estimated capital and operating costs or unanticipated costs; difficulties attracting the necessary work force; increases in financing costs or adverse changes to global market conditions and the terms of available financing, if any; tax rates or royalties being greater than assumed; changes in development or mining plans due to changes in logistical, technical or other factors, changes in project parameters as plans continue to be refined; risks relating timing and to receipt of regulatory approvals; adverse changes to government approval processes; the effects of competition in the markets in which the Company operates; operational and infrastructure risks; and the additional risks described in the Company's Annual Information Form, annual financial statements and management's discussion and analysis for the year ended December 31, 2012 and in the feasibility study entitled "Corani Project, Form 43-101F1 Technical Report, Feasibility Study" filed by the Company on December 22, 2011 filed on the SEDAR website in Canada (available at www.sedar.com). The foregoing list of factors that may affect future results is not exhaustive.

When relying on our forward-looking statements, investors and others should carefully consider the foregoing factors and other uncertainties and potential events.  The Company does not undertake to update any forward-looking statement, whether written or oral, that may be made from time to time by the Company or on behalf of the Company, except as required by law.

All scientific and technical information contained in this news release has been reviewed and approved by Andrew Swarthout, P.Geo., the President and Chief Executive Officer of the Company, who serves as the "qualified person" within the meaning of National Instrument 43-101 ("NI 43-101"). The block model estimate, mine design and schedules for the Santa Ana Feasibility Study were prepared by Independent Mining Consultants of Tucson Arizona, with John Marek, P.E. acting as the independent qualified person under NI 43-101.  Additionally, the methods used in determining and reporting the mineral reserves and resources in the Feasibility Study are consistent with the CIM Best Practices Guidelines.

Following is a table setting forth mineral reserve estimates from the Santa Ana Feasibility Study announced on October 7, 2010:

Bear Creek Mining, Santa Ana Project Silver Zone
Mineral Reserves

October 7, 2010 Mineral Reserves, Cutoff Grade, Variable 27 to 24 g/t Silver by Year
Category Ktonnes Silver
g/t
Lead
%
Zinc
%
Contained
Silver
Million
Ozs
Proven 8,951 57.6 0.37 0.66 16.6
Prob 28,126 51.5 0.33 0.55 46.6
Prov+Prob 37,077 53.0 0.34 0.58 63.2

Please refer to the Company's news release dated October 7, 2010 for further details of the Santa Ana Feasibility Study, as well as the feasibility study itself filed on SEDAR (www.sedar.com) on October 21, 2010.

SOURCE Bear Creek Mining Corporation

More Stories By PR Newswire

Copyright © 2007 PR Newswire. All rights reserved. Republication or redistribution of PRNewswire content is expressly prohibited without the prior written consent of PRNewswire. PRNewswire shall not be liable for any errors or delays in the content, or for any actions taken in reliance thereon.

Latest Stories
SYS-CON Events announced today that Windstream, a leading provider of advanced network and cloud communications, has been named “Silver Sponsor” of SYS-CON's 16th International Cloud Expo®, which will take place on June 9–11, 2015, at the Javits Center in New York, NY. Windstream (Nasdaq: WIN), a FORTUNE 500 and S&P 500 company, is a leading provider of advanced network communications, including cloud computing and managed services, to businesses nationwide. The company also offers broadband, p...
The 4th International DevOps Summit, co-located with16th International Cloud Expo – being held June 9-11, 2015, at the Javits Center in New York City, NY – announces that its Call for Papers is now open. Born out of proven success in agile development, cloud computing, and process automation, DevOps is a macro trend you cannot afford to miss. From showcase success stories from early adopters and web-scale businesses, DevOps is expanding to organizations of all sizes, including the world's large...
"There is a natural synchronization between the business models, the IoT is there to support ,” explained Brendan O'Brien, Co-founder and Chief Architect of Aria Systems, in this SYS-CON.tv interview at the 15th International Cloud Expo®, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
Verizon Enterprise Solutions is simplifying the cloud-purchasing experience for its clients, with the launch of Verizon Cloud Marketplace, a key foundational component of the company's robust ecosystem of enterprise-class technologies. The online storefront will initially feature pre-built cloud-based services from AppDynamics, Hitachi Data Systems, Juniper Networks, PfSense and Tervela. Available globally to enterprises using Verizon Cloud, Verizon Cloud Marketplace provides a one-stop shop fo...
Leysin American School is an exclusive, private boarding school located in Leysin, Switzerland. Leysin selected an OpenStack-powered, private cloud as a service to manage multiple applications and provide development environments for students across the institution. Seeking to meet rigid data sovereignty and data integrity requirements while offering flexible, on-demand cloud resources to users, Leysin identified OpenStack as the clear choice to round out the school's cloud strategy. Additional...
The major cloud platforms defy a simple, side-by-side analysis. Each of the major IaaS public-cloud platforms offers their own unique strengths and functionality. Options for on-site private cloud are diverse as well, and must be designed and deployed while taking existing legacy architecture and infrastructure into account. Then the reality is that most enterprises are embarking on a hybrid cloud strategy and programs. In this Power Panel at 15th Cloud Expo (http://www.CloudComputingExpo.com...
We are all here because we are sold on the transformative promise of The Cloud. But what good is all of this ephemeral, on-demand infrastructure if your usage doesn't actually improve the agility and speed of your business? How must Operations adapt in order to avoid stifling your Cloud initiative? In his session at DevOps Summit, Damon Edwards, co-founder and managing partner of the DTO Solutions, will highlight the successful organizational, process, and tooling patterns of high-performing c...
The definition of IoT is not new, in fact it’s been around for over a decade. What has changed is the public's awareness that the technology we use on a daily basis has caught up on the vision of an always on, always connected world. If you look into the details of what comprises the IoT, you’ll see that it includes everything from cloud computing, Big Data analytics, “Things,” Web communication, applications, network, storage, etc. It is essentially including everything connected online from ha...
Software-driven innovation is becoming a primary approach to how businesses create and deliver new value to customers. A survey of 400 business and IT executives by the IBM Institute for Business Value showed businesses that are more effective at software delivery are also more profitable than their peers nearly 70 percent of the time (1). DevOps provides a way for businesses to remain competitive, applying lean and agile principles to software development to speed the delivery of software that ...
Docker offers a new, lightweight approach to application portability. Applications are shipped using a common container format and managed with a high-level API. Their processes run within isolated namespaces that abstract the operating environment independently of the distribution, versions, network setup, and other details of this environment. This "containerization" has often been nicknamed "the new virtualization." But containers are more than lightweight virtual machines. Beyond their small...
The move in recent years to cloud computing services and architectures has added significant pace to the application development and deployment environment. When enterprise IT can spin up large computing instances in just minutes, developers can also design and deploy in small time frames that were unimaginable a few years ago. The consequent move toward lean, agile, and fast development leads to the need for the development and operations sides to work very closely together. Thus, DevOps become...
Cloud Expo 2014 TV commercials will feature @ThingsExpo, which was launched in June, 2014 at New York City's Javits Center as the largest 'Internet of Things' event in the world.

ARMONK, N.Y., Nov. 20, 2014 /PRNewswire/ --  IBM (NYSE: IBM) today announced that it is bringing a greater level of control, security and flexibility to cloud-based application development and delivery with a single-tenant version of Bluemix, IBM's

An entirely new security model is needed for the Internet of Things, or is it? Can we save some old and tested controls for this new and different environment? In his session at @ThingsExpo, New York's at the Javits Center, Davi Ottenheimer, EMC Senior Director of Trust, reviewed hands-on lessons with IoT devices and reveal a new risk balance you might not expect. Davi Ottenheimer, EMC Senior Director of Trust, has more than nineteen years' experience managing global security operations and asse...
Explosive growth in connected devices. Enormous amounts of data for collection and analysis. Critical use of data for split-second decision making and actionable information. All three are factors in making the Internet of Things a reality. Yet, any one factor would have an IT organization pondering its infrastructure strategy. How should your organization enhance its IT framework to enable an Internet of Things implementation? In his session at Internet of @ThingsExpo, James Kirkland, Chief Ar...