Centerra Gold Completes Preliminary Economic Assessment of the Oksut Project

TORONTO, ONTARIO -- (Marketwired) -- 02/20/14 --

All figures are in United States dollars

Centerra Gold Inc. (TSX:CG) announces the completion of a preliminary economic assessment study (PEA) on its 100% owned Oksut project located in south-central Turkey, about 295 kilometres southeast of the capital city of Ankara. The Oksut project is currently comprised of the Keltepe deposit and the smaller Guneytepe deposit.

The resource estimate used as the basis for the PEA was made as of December 31, 2013 using a cut-off grade of 0.2 grams per tonne of gold and a gold price of $1,300 per ounce and was announced in a news release dated February 5, 2014. The resource estimate consists of: (i) indicated mineral resources from the Keltepe deposit, estimated at 29 million tonnes grading 1.2 grams per tonne of gold for 1.1 million contained ounces of gold; and (ii) inferred mineral resources located at the Guneytepe deposit, estimated at 4.7 million tonnes grading 0.9 grams per tonne of gold for 134,000 contained ounces of gold.

The PEA envisions a conventional open-pit and heap leach facility with an expected 34 million tonnes of ore to be stacked at a maximum rate of 11,000 tonnes per day.

Highlights of the PEA study (using a $1,300 per ounce gold price) include:


--  11 year mine life (2016 to 2027), 
--  Life of mine gold production of 893,000 ounces, average annual gold
    production of 125,000 ounces in years 4 through 6, 
--  Total construction capital and preproduction costs of $166 million, 
--  Total sustaining capital of $9 million, 
--  All-in costs(1) for the project of $849 per ounce, 
--  All-in costs including taxes(1) for the project of $914 per ounce, 
--  After tax net present value (NPV) of $117 million at an 8% discount rate
    with a 19% project internal rate of return, 
--  Payback on construction capital and pre-production costs is expected to
    be 4.5 years after production begins.

(1)  Non-GAAP measure. Centerra has adopted the World Gold Council's (WGC)  
     guidelines regarding "all-in-costs". These financial measures do not   
     have any standardized meaning prescribed by GAAP and are therefore     
     unlikely to be comparable to similar measures presented by other       
     issuers, even issuers applying the WGC's guidelines. See description of
     "Non-GAAP Measures" in the Company's Management Discussion & Analysis  
     dated February 19, 2014 and filed on SEDAR.                            

The PEA is preliminary in nature and includes the use of inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Thus, there is no certainty that the PEA will be realized. Actual results may vary, perhaps materially. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The PEA is subject to a number of assumptions, including, among others, that an environmental impact assessment will be completed within the required timelines, all required permits will be obtained in a timely manner, the Company will continue to have the support of local communities, a constant regulatory environment and no material increase occurs to the estimated costs. A full list of the relevant assumptions will be set out in the PEA.

Ian Atkinson, President and CEO of Centerra Gold stated, "We are very pleased with the positive results of the PEA study which confirmed our expectations based on the known resources. The Keltepe deposit is still open to the south in the direction of the Guneytepe deposit and we have additional exploration targets on our land package which we will continue to follow-up on through exploration and drilling. Now we will move forward with a feasibility study for the project with the target of achieving initial gold production sometime in late 2016."

The PEA study envisions a conventional open pit and heap leach facility with the mining of the two pits completed by a local mining contractor. The heap leach pad design is based on an expected 34 million tonnes of ore to be stacked at a maximum rate of 11,000 tonnes per day, with a nominal crush size of 80% less than 37.5 mm.

Over the life of mine, mining costs are estimated to average $2.77 per tonne mined, processing costs are estimated to average $4.00 per tonne processed and administrative costs will average about $9 million per operating year.

To account for mining dilution and losses during the mining process, the mineral resources have had a 95% factor applied to the gold grades in the production schedule and are constrained by an optimized pit shell defined using optimization software, a gold price of $1,300 per ounce, an overall metallurgical recovery of 77%, and estimated average mining, processing and administrative costs. Overall pit-slope angles range from 38 degrees to 42 degrees depending on the location in the pit and result in a low overall stripping ratio of 2.0 over the mine life.

Using a gold price of $1,300 per ounce and a discount rate of 8%, the Oksut open pit LOM outlined in the PEA has an estimated project NPV (after tax) of approximately $117 million and a project internal rate of return of 19% after accounting for all operating costs and capital expenditures related to the open pit operation as well as required tax and royalty payments. Additional exploration costs going forward have not been included in the financial analysis.

Sensitivities of the project NPV to the gold price, discount rate and other project variables are as follows:


 Sensitivities of Oksut Project Net Present Value to Gold Price and Discount
                                    Rate                                    
                            (millions of dollars)                           
                                                                            
                 ------------------------------------------                 
                                      Discount Rate                         
                             ------------------------------                 
                 Gold Price                                                 
                  ($/ounce)          5%        8%       10%                 
                 ------------------------------------------                 
                 $1,100        $   81.0  $   36.7  $   14.5                 
                 ------------------------------------------                 
                 $1,200        $  131.8  $   77.7  $   50.3                 
                 ------------------------------------------                 
                 $1,300        $  181.1  $  117.7  $   85.2                 
                 ------------------------------------------                 
                 $1,400        $  224.7  $  153.4  $  116.7                 
                 ------------------------------------------                 
                 $1,500        $  267.8  $  188.6  $  147.6                 
                 ------------------------------------------                 
                                                                            
   Sensitivities of Oksut Project Net Present Value to other Variables at   
                 $1,300 per ounce gold and 8% discount rate                 
                            (millions of dollars)                           
                                                                            
----------------------------------------------------------------------------
Variable                     Operating Costs   Capital Costs      Gold Grade
----------------------------------------------------------------------------
+15%                          $         75.4  $         99.9  $        181.3
----------------------------------------------------------------------------
Base Case                     $        117.7  $        117.7  $        117.7
----------------------------------------------------------------------------
-15%                          $        156.1  $        131.2  $         45.4
----------------------------------------------------------------------------

The inferred mineral resources located at the Guneytepe deposit have a great amount of uncertainty as to their existence and as to whether they can be mined legally or economically. It cannot be assumed that all or any part of inferred mineral resources will ever be upgraded to a higher category.

The PEA will be available on the Company's website in middle of March, 2014.

Qualified Person & QA/QC

The PEA report was undertaken by Centerra staff with the assistance of several external consultants. Resource estimates, life-of-mine plan and other scientific and technical information in this news release and on Centerra's website were prepared in accordance with the standards of the Canadian Institute of Mining, Metallurgy and Petroleum and National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") and were reviewed, verified and compiled by Centerra's geological and mining staff under the supervision of Dan Redmond, Ontario Professional Geoscientist, Centerra's Director, Technical Services - Mining, who is the qualified person for the purpose of NI 43-101. Sample preparation, analytical techniques, laboratories used and quality assurance-quality control protocols used during the exploration drilling programs on the Oksut project have been done consistent with industry standards and independent certified assay labs have been used. Available quality control data indicates that the gold assay data used for resource estimation are reliable.

Cautionary Note Regarding Forward-looking Information

Information contained in this news release and the documents referred to herein which are not statements of historical facts, may be "forward-looking information" for the purposes of Canadian securities laws. Such forward looking information involves risks, uncertainties and other factors that could cause actual results, performance, prospects and opportunities to differ materially from those expressed or implied by such forward looking information. The words "believe", "expect", "envision", "target", "intends", "estimate", "may", "will", and similar expressions identify forward-looking information. These forward-looking statements relate to, among other things, mineral resource estimates and Centerra's plans to conduct additional exploration and drilling work and to commence a feasibility study for its Oksut property in 2014.

Forward-looking information is necessarily based upon a number of estimates and assumptions that, while considered reasonable by Centerra, are inherently subject to significant political, business, economic and competitive uncertainties and contingencies. There may be factors that cause results, assumptions, performance, achievements, prospects or opportunities in future periods not to be as anticipated, estimated or intended. These factors include: (i) tight time lines for the completion of an environmental impact assessment and permitting, since the project has to receive all necessary permits prior to January 2016 and the possibility of forfeiting the operating license as a result of any delays in such timelines; (ii) delays in recent years in the issuance of permits, particularly for State Forestry Land which covers part of the Oksut project area and on which the two open pits and part of the waste dump are located; (iii) the absence of condemnation drilling of the heap-leach and waste-dump sites, which may result in those sites being poorly located or requiring additional capital costs; (iv) potential opposition to the project by local communities or civil groups related to concerns over water usage in competition with agriculture, water quality, environmental impact from cyanide use in gold leaching, visual impacts, acoustic impacts, ambient air impacts or failure of the company to agree to local demands; (v) potential material increases in project development or operation costs due to increases in key consumables, inflation, imposed demands for infrastructure development or regulatory changes; (vi) further column tests being required to determine the variability of the metallurgical parameters and response of the Oksut oxide ore; (vii) the planning, design and costing of the key project infrastructure such as power, water and access being at a high level conceptual stage in the PEA; (viii) closure costs to cap waste rock and heap leach dumps; (ix) mine design, mining schedules, metallurgical flow sheets and process designs will require additional detailed work and economic analysis; and (x) internal studies to ensure satisfactory operational conditions and decisions regarding future targeted production must be carried out. See also "Risks that can affect our business" in the Company's Annual Information Form for the year ended December 31, 2012, available on SEDAR at www.sedar.com.

There can be no assurances that forward-looking information and statements will prove to be accurate, as many factors and future events, both known and unknown could cause actual results, performance or achievements to vary or differ materially, from the results, performance or achievements that are or may be expressed or implied by such forward looking statements contained herein or incorporated by reference. Accordingly, all such factors should be considered carefully when making decisions with respect to Centerra, and prospective investors should not place undue reliance on forward-looking information. Forward looking information is as of February 19, 2014. Centerra assumes no obligation to update or revise forward-looking information to reflect changes in assumptions, changes in circumstances or any other events affecting such forward looking information, except as required by applicable law.

About Centerra

Centerra Gold Inc. is a gold mining company focused on operating, developing, exploring and acquiring gold properties primarily in Asia, the former Soviet Union and other emerging markets worldwide. Centerra is the largest Western-based gold producer in Central Asia. Centerra's shares trade on the Toronto Stock Exchange (TSX) under the symbol CG. The Company is based in Toronto, Ontario, Canada.

Additional information on Centerra is available on the Company's web site at www.centerragold.com and at SEDAR at www.sedar.com.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Samsung VP Jacopo Lenzi, who headed the company's recent SmartThings acquisition under the auspices of Samsung's Open Innovaction Center (OIC), answered a few questions we had about the deal. This interview was in conjunction with our interview with SmartThings CEO Alex Hawkinson. IoT Journal: SmartThings was developed in an open, standards-agnostic platform, and will now be part of Samsung's Ope...
Explosive growth in connected devices. Enormous amounts of data for collection and analysis. Critical use of data for split-second decision making and actionable information. All three are factors in making the Internet of Things a reality. Yet, any one factor would have an IT organization pondering its infrastructure strategy. How should your organization enhance its IT framework to enable an In...
The major cloud platforms defy a simple, side-by-side analysis. Each of the major IaaS public-cloud platforms offers their own unique strengths and functionality. Options for on-site private cloud are diverse as well, and must be designed and deployed while taking existing legacy architecture and infrastructure into account. Then the reality is that most enterprises are embarking on a hybrid cloud...
In her General Session at 15th Cloud Expo, Anne Plese, Senior Consultant, Cloud Product Marketing, at Verizon Enterprise, will focus on finding the right mix of renting vs. buying Oracle capacity to scale to meet business demands, and offer validated Oracle database TCO models for Oracle development and testing environments. Anne Plese is a marketing and technology enthusiast/realist with over 19...
StackIQ offers a comprehensive software suite that automates the deployment, provisioning, and management of Big Infrastructure. With StackIQ’s software, you can spin up fully configured big data clusters, quickly and consistently — from bare-metal up to the applications layer — and manage them efficiently. Our software’s modular architecture allows customers to integrate nearly any application wi...
As Platform as a Service (PaaS) matures as a category, developers should have the ability to use the programming language of their choice to build applications and have access to a wide array of services. Bluemix is IBM's open cloud development platform that enables users to easily build cloud-based, creative mobile and web applications without having to spend large amounts of time and resources o...
The Internet of Things will greatly expand the opportunities for data collection and new business models driven off of that data. In her session at Internet of @ThingsExpo, Esmeralda Swartz, CMO of MetraTech, will discuss how for this to be effective you not only need to have infrastructure and operational models capable of utilizing this new phenomenon, but increasingly service providers will nee...
When you set off to build an app that will change the world, designing your system architecture to be reliable and scalable is important but the stark reality is that, for your MVP, you probably had a “need for speed” (of development). You didn’t know what all the axes were to scale your application, where your stress points would be, and what weird and wonderful ways your customers would use it d...
Compute virtualization has been transformational, yet security policy implementation and enforcement has lagged behind in agility and automation. There are a number of key considerations when implementing policy in private and hybrid clouds. In his session at 15th Cloud Expo, Holland Barry, VP of Technology at Catbird, will discuss the impact of this new paradigm and what organizations can do to...
SYS-CON Events announced today that Red Hat, the world's leading provider of open source solutions, will exhibit at Internet of @ThingsExpo, which will take place on November 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA. Red Hat is the world's leading provider of open source software solutions, using a community-powered approach to reliable and high-performing cloud, Linux, ...