Lupaka Gold to Begin Permitting and Commence Small-Scale Production at the Invicta Gold Project by Q1-2015

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 03/17/14 -- Lupaka Gold Corp ("Lupaka Gold" or the "Company") (TSX: LPK)(LMA: LPK)(FRANKFURT: LQP) is pleased to announce that it intends to initiate a small-scale mining operation at the Invicta Gold Project at a rate of 300 tonnes per day ("t/d") by Q1-2015.

The Company intends to commence production by using the existing 1.2 km of tunnels, utilizing contracted third-party mining, development and haulage, and sell the mineralized rock to a local mill for processing. This contract-mining strategy will significantly minimize required capital, surface disturbance, while reducing the impact on the local community. The Company forecasts that production can be commenced at a total cost of less than $2.0 million. Production is planned to initially target some of the highest grade gold and copper mineralization within the Atenea Vein, which contains the majority of the current Invicta gold resource.

Invicta Gold Project production plan highlights:


--  Mine permitting, engineering, development and infrastructure costs of
   less than $2.0 million, funded from the Company's treasury and/or
    alternative financing sources;
--  Preparing and submitting an operating permit under the small miner
    exemption in Peru, which is available for operations of up to 350 t/d;
--  Securing necessary permits within 7 months by modifying/utilizing the
    Company's existing Environmental Impact Assessment for Mine Operations,
    Archeological Certificate, Water License and Community Agreement;
--  Contractor pre-production mine development would commence after
    receiving required permits and be completed within three months;
--  Utilize the existing 1.2 km of tunnels, drifts, and cross cuts that
    access the Measured resource mineralization;
--  Construction of mine safety, alternate escapes, and ventilation upgrades
    as part of the pre-production development;
--  Utilizing a low-cost and scalable sub-level open stoping mining method;
--  Commencing initial production by March 2015;
--  Over the first 12 months, producing approximiately 100,000 tonnes of
    mineralized rock from the areas containing the Measured resource; and
--  Shipping and selling mineralized rock directly to local custom toll
    mills, thereby avoiding capital cost and permit delays associated with
    plant construction, tailings and water impacts.

Eric Edwards, Lupaka Gold's CEO, commented that "the historical development work already provides us with access to an area containing some of the highest grade rock within the current resource. The considerable investment made by Invicta's previous owners has provided most of the infrastructure required for this proposed small-scale mining operation."

The current Invicta resource estimate shows a Measured resource of 131,000 tonnes grading 6.65 grams per tonne ("g/t") gold equivalent for 28,000 contained ounces of gold available from the in-situ development. As well, the current Invicta resource shows an Indicated resource of 8,513,000 tonnes grading 3.43 g/t gold equivalent for 939,000 contained ounces of gold and an Inferred resource of 2,534,000 tonnes grading 2.90 g/t gold equivalent for 236,000 contained ounces of gold. See Table 1 below and the technical report dated April 16, 2012, titled "Technical Report on Resources, Invicta Gold Project, Huaura Province, Peru", and prepared by SRK Consulting (U.S.) Inc. ("SRK Technical Report"), which is available at www.sedar.com under Lupaka Gold Corp's profile.

A portion of the Measured resource mineralization will initially be targeted by the planned production. The Company also intends to pursue further drilling from underground, concurrent with production, with the objective of upgrading inferred resources and providing additional data to inform mining direction and control decisions.

Table 1: Invicta Project: Summarized extract from the SRK Technical Report, detailing the above-mentioned resource estimate


----------------------------------------------------------------------------
       Resource       Tonnes
Zone   Category      (000's)                   Metal Grade
                            ------------------------------------------------
                                AuEq
                               (g/t)Au (g/t)Ag (g/t)  Cu (%)  Pb (%)  Zn (%)
----------------------------------------------------------------------------
Total -Measured          131    6.65    4.29   31.71    0.73    0.39    0.38
 All   Indicated       8,513    3.43    2.09   15.65    0.42    0.24    0.28
 Zones M + I           8,644    3.48    2.13   15.90    0.43    0.24    0.29
       Inferred        2,534    2.90    1.61   12.02    0.46    0.27    0.18
----------------------------------------------------------------------------

-------------------------------------------------------------------
       Resource
Zone   Category                 Contained Metal (000's)
                   ------------------------------------------------
                    AuEq Oz   Au Oz   Ag Oz  Cu Lbs  Pb Lbs  Zn Lbs
-------------------------------------------------------------------
Total -Measured          28      18     133   2,119   1,110   1,105
 All   Indicated        939     573   4,285  79,048  45,171  53,482
 Zones M + I            967     591   4,418  81,167  46,281  54,587
       Inferred         236     131     979  25,879  14,891   9,854
-------------------------------------------------------------------

(i)Notes:


--  Mineral Resources are not Mineral Reserves and do not have demonstrated
    economic viability. There is no certainty that all or any part of the
    Mineral Resources estimate will be converted into a Mineral Reserves
    estimate;
--  Resources stated as contained within potentially economically mineable
    underground solids stated above a 1.3g/t Au Equivalent cut-off;
--  The resource is stated at a 1.30 g/t gold equivalent cut-off contained
    within potentially economically mineable mineralized solids. Metal
    prices assumed for the gold equivalent calculation are US$1,500/oz for
    gold, US$32.50/oz for silver, US$3.90/lb for copper, US$1.05/lb for lead
    and US$1.00/lb for zinc. The gold equivalent calculation assumes 100%
    metallurgical recovery, and does not account for any smelting,
    transportation or refining charges;
--  Mineral resource tonnage and contained metal have been rounded to
    reflect the accuracy of the estimate, and numbers may not add due to
    rounding; and
--  Mineral resource tonnage and grade are reported as diluted to reflect a
    potentially minable underground selective mining unit of 3.0m.

The Company will prepare and apply for a small mine operations permit in Peru that provides for mining operations of up to 350 tonne per day. The small mine permit approval process is administered through the local jurisdiction in the Department of Lima, and requires two public workshops for comment and local involvement. The permit application process requires similar studies as large-scale permits, i.e. environmental baseline, flora and fauna, archeological assessment, hydrology, hydrogeology, and others, but recognizes that the project has a much smaller surface and environmental disturbance and impact. Small mine permits can typically be prepared and approved within seven months.

The Company is in discussions and negotiations with a number of Peruvian mining contractors. A team to prepare the necessary small mine permits will be formed and contracted within the next month and should have the permit applications completed within 5 months. Community workshops will take place within the required timeframe.

Over the next several months and during the permit preparation/review process, the Company will complete mine engineering, contractor selections, staffing, training, road improvements, water system upgrades, and other activities leading toward operations. Critical to the contractor selection will be not only cost, but safety, environmental awareness, community and cultural sensitivity, permit compliance, references and experience, as well as other factors.

Mr. Edwards further commented that "Invicta remains a project with considerable unrecognized value, and with a successful implementation of an Invicta mining operation we believe that we will be able to interest an established miner in expanding to a larger-scale operation where Lupaka would hold a continuing carried interest."

Previous owners of the Invicta Gold property completed a number of technical studies including metallurgy, rock mechanics, structural geology on the mine area, hydrology, hydrogeology, power line from Andahuasi, and other engineering analysis.

The decision to commence production at the Invicta Gold property was based on economic models prepared by the Company in conjunction with management's knowledge of the property and the existing preliminary estimate of measured and inferred mineral resources on the property. The decision was not based on a preliminary economic assessment, a pre-feasibility study or a feasibility study of mineral reserves demonstrating economic and technical viability. Accordingly, there is increased uncertainty and economic and technical risks of failure associated with this production decision, in particular the risk that mineral grades will be lower than expected, the risk that construction or ongoing mining operations are more difficult or more expensive than expected, the risk that the Company will not be able to transport or sell the mineralized rock it produces to local custom toll mills on the terms it expects, or at all; production and economic variables may vary considerably, due to the absence of a detailed economic and technical analysis according to and in accordance with NI 43-101. Inferred mineral resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves.

To view Figure 1, "Invicta Project: Three dimensional view showing surface topography, underground projection of the main mineralized vein, and existing underground tunnels from surface to main vein," please visit the following link: http://media3.marketwire.com/docs/LPKfig1.pdf.

About Lupaka Gold

Lupaka Gold is a Peru-focused gold explorer and developer with geographic diversification and balance through its interest in asset-based resource projects spread across three regions of Peru.

As of December 31, 2013 Lupaka Gold had cash reserves of $3.85 million, sufficient to conduct planned exploration work and fund its operations during 2014.

Lupaka Gold currently has three projects occupying different stages of exploration and development.

The Company's 100% owned Invicta Gold Project (central Peru) has near-term underground gold and poly-metallic production potential. The Company plans to implement a small-scale mining operation and complete permitting, development and engineering with production to commence by Q1-2015.

Lupaka Gold's flagship exploration project is the Crucero Gold Project, its 5,500 hectare gold property located in southern Peru. Crucero has a growing indicated and inferred gold resource, and the Company is actively exploring the property to identify future drill targets.

In November 2013, the Company optioned the Josnitoro Gold Project from Hochschild Mining PLC. The project is located approximately 600 kilometres by road southeast of Lima in the Department of Apurimac, southern Peru. Historical work on the disseminated gold zones includes over 170 shallow drill holes and extensive surface trenching.

As a result of the Company's 2012 acquisition of Andean American Gold Corp., the Company also holds a strategic 17% stake in Southern Legacy Minerals Inc., owner of the AntaKori copper-gold deposit located in northern Peru.

Qualified Person

The technical information in this document has been reviewed and approved by Julio Castaneda, MAIG, the President of Lupaka Peru, a Peruvian subsidiary of the Company, and a Qualified Person as defined by National Instrument 43-101.

Forward-Looking Information and Regulatory Endnotes

This news release contains "forward-looking statements" and "forward-looking information" within the meaning of applicable securities regulations in Canada and the United States (collectively, "forward-looking information"). The forward-looking information contained in this news release is made as of the date of this news release. Except as required under applicable securities legislation, the Company does not intend, and does not assume any obligation, to update this forward-looking information. Forward-looking information in this news release includes all of the plans and expectations described above regarding initiating mining operations at the Invicta Gold Project (the "planned production"), including but is not limited to: the timing and cost of completing pre-production mine development; the method of funding mine development and infrastructure costs; the mineralizations to be targeted; the existence of high-grade mineralizations and the depth of any such mineralization from the existing tunnels on the project; the Company's plans for shipping and selling mineralized rock from the planned production; all statements regarding the permits necessary for the planned production and the timing and conditions of receiving those permits; mining methods to be used for the planned production and the costs thereof; the date by which the Company expects the planned production to commence; and all quantities and rates of production.

Forward-looking information also includes statements as to the sufficiency of current cash reserves to pay for planned exploration and fund future operations, as well as estimates of mineral resources. Often, but not always, forward-looking information can be identified by the use of words such as "plans", "expects, "is expected", "budget", "scheduled", "projects", "estimates", forecasts", "intends", "anticipates", or "believes", or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might", or "will" be taken, occur or be achieved. The forward-looking information contained in this news release is based on certain assumptions that the Company believes are reasonable, including, with respect to the planned production: that pre-production mine development can be completed in the time and for the cost projected; that the Company will be able to fund expenses of the planned production from its current cash reserves; that mineralizations on the project will be of the grades and in the locations expected; that the Company will be able to extract and transport mineralized rock efficiently and sell the mineralized rock at the prices and in the manner and quantities expected; that permits will be received on the terms and timeline expected and that other regulatory or permitting issues will not arise; that mining methods can be employed in the manner and at the costs expected and that such methods yield the results the Company expects them to; that supplies, equipment, personnel, permits and local community approvals required to develop and conduct the planned production will be available on reasonable term; that the Company will not experience any material accident, labour dispute, or failure of equipment.

The Company's assumptions with respect to mineral resource estimates include all of the key assumptions and parameters on which such estimates are based, as described in the technical report referred to in this news release. However, forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information. Such risks, uncertainties and other factors include, among others: all of the risks described in this news release; the risk that actual results of exploration activities will be different than anticipated; that cost of labour, equipment or materials will increase more than expected; that the future price of gold will decline; that the Canadian dollar will strengthen against the U.S. dollar; that mineral resources are not as estimated; unexpected variations in mineral resources, grade or recovery rates; risks related to shipping mineralized rock; the risk that local mills cannot or will not buy or process mineralized rock from the planned production for the prices expected or at all; risk of accidents, labour disputes and other risks generally associated with mineral exploration; unanticipated delays in obtaining or failure to obtain community, governmental or regulatory approvals or financing; and all of the risks generally associated with the development of mining facilities and the operation of a producing mine; as well as the risks described in the Company's annual information form, which is available on SEDAR at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking information, there may be other factors that cause actions, events or results to not be as anticipated, estimated or intended. There can be no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Readers are cautioned not to place undue reliance on forward-looking information due to the inherent uncertainty thereof.

This announcement contains certain forward looking statements, including such statements within the meaning of Section 27A of the US Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. In particular, such forward looking statements may relate to matters such as the business, strategy, investments, production, major projects and their contribution to expected production and other plans of Hochschild Mining plc and its current goals, assumptions and expectations relating to its future financial condition, performance and results.

Forward-looking statements include, without limitation, statements typically containing words such as "intends", "expects", "anticipates", "targets", "plans", "estimates" and words of similar import. By their nature, forward looking statements involve risks and uncertainties because they relate to events and depend on circumstances that will or may occur in the future. Actual results, performance or achievements of Hochschild Mining plc may be materially different from any future results, performance or achievements expressed or implied by such forward looking statements. Factors that could cause or contribute to differences between the actual results, performance or achievements of Hochschild Mining plc and current expectations include, but are not limited to, legislative, fiscal and regulatory developments, competitive conditions, technological developments, exchange rate fluctuations and general economic conditions. Past performance is no guide to future performance and persons needing advice should consult an independent financial adviser.

The forward looking statements reflect knowledge and information available at the date of preparation of this announcement. Except as required by the Listing Rules and applicable law, Hochschild Mining plc does not undertake any obligation to update or change any forward looking statements to reflect events occurring after the date of this announcement. Nothing in this announcement should be construed as a profit forecast.

Contacts:
Lupaka Gold Corp.
Investor Relations
+1 (604) 681-5900
www.lupakagold.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
"There is a natural synchronization between the business models, the IoT is there to support ,” explained Brendan O'Brien, Co-founder and Chief Architect of Aria Systems, in this SYS-CON.tv interview at the 15th International Cloud Expo®, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
The 4th International DevOps Summit, co-located with16th International Cloud Expo – being held June 9-11, 2015, at the Javits Center in New York City, NY – announces that its Call for Papers is now open. Born out of proven success in agile development, cloud computing, and process automation, DevOps is a macro trend you cannot afford to miss. From showcase success stories from early adopters and web-scale businesses, DevOps is expanding to organizations of all sizes, including the world's large...
Fundamentally, SDN is still mostly about network plumbing. While plumbing may be useful to tinker with, what you can do with your plumbing is far more intriguing. A rigid interpretation of SDN confines it to Layers 2 and 3, and that's reasonable. But SDN opens opportunities for novel constructions in Layers 4 to 7 that solve real operational problems in data centers. "Data center," in fact, might become anachronistic - data is everywhere, constantly on the move, seemingly always overflowing. Net...
An entirely new security model is needed for the Internet of Things, or is it? Can we save some old and tested controls for this new and different environment? In his session at @ThingsExpo, New York's at the Javits Center, Davi Ottenheimer, EMC Senior Director of Trust, reviewed hands-on lessons with IoT devices and reveal a new risk balance you might not expect. Davi Ottenheimer, EMC Senior Director of Trust, has more than nineteen years' experience managing global security operations and asse...
SYS-CON Media announced that Centrify, a provider of unified identity management across cloud, mobile and data center environments that delivers single sign-on (SSO) for users and a simplified identity infrastructure for IT, has launched an ad campaign on Cloud Computing Journal. The ads focus on security: how an organization can successfully control privilege for all of the organization’s identities to mitigate identity-related risk without slowing down the business, and how Centrify provides ...
The Internet of Things promises to transform businesses (and lives), but navigating the business and technical path to success can be difficult to understand. In his session at @ThingsExpo, Sean Lorenz, Technical Product Manager for Xively at LogMeIn, demonstrated how to approach creating broadly successful connected customer solutions using real world business transformation studies including New England BioLabs and more.
There's Big Data, then there's really Big Data from the Internet of Things. IoT is evolving to include many data possibilities like new types of event, log and network data. The volumes are enormous, generating tens of billions of logs per day, which raise data challenges. Early IoT deployments are relying heavily on both the cloud and managed service providers to navigate these challenges. In her session at Big Data Expo®, Hannah Smalltree, Director at Treasure Data, discussed how IoT, Big D...
The Internet of Things will greatly expand the opportunities for data collection and new business models driven off of that data. In her session at @ThingsExpo, Esmeralda Swartz, CMO of MetraTech, discussed how for this to be effective you not only need to have infrastructure and operational models capable of utilizing this new phenomenon, but increasingly service providers will need to convince a skeptical public to participate. Get ready to show them the money!
The 3rd International Internet of @ThingsExpo, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that its Call for Papers is now open. The Internet of Things (IoT) is the biggest idea since the creation of the Worldwide Web more than 20 years ago.
In her General Session at 15th Cloud Expo, Anne Plese, Senior Consultant, Cloud Product Marketing, at Verizon Enterprise, focused on finding the right mix of renting vs. buying Oracle capacity to scale to meet business demands, and offer validated Oracle database TCO models for Oracle development and testing environments. Anne Plese is a marketing and technology enthusiast/realist with over 19+ years in high tech. At Verizon Enterprise, she focuses on driving growth for the Verizon Cloud platfo...
The Internet of Things will put IT to its ultimate test by creating infinite new opportunities to digitize products and services, generate and analyze new data to improve customer satisfaction, and discover new ways to gain a competitive advantage across nearly every industry. In order to help corporate business units to capitalize on the rapidly evolving IoT opportunities, IT must stand up to a new set of challenges. In his session at @ThingsExpo, Jeff Kaplan, Managing Director of THINKstrateg...
SYS-CON Events announced today Isomorphic Software, the global leader in high-end, web-based business applications, will exhibit at SYS-CON's DevOps Summit 2015 New York, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Isomorphic Software is the global leader in high-end, web-based business applications. We develop, market, and support the SmartClient & Smart GWT HTML5/Ajax platform, combining the productivity and performance of traditional desktop software ...
The Internet of Things is tied together with a thin strand that is known as time. Coincidentally, at the core of nearly all data analytics is a timestamp. When working with time series data there are a few core principles that everyone should consider, especially across datasets where time is the common boundary. In his session at Internet of @ThingsExpo, Jim Scott, Director of Enterprise Strategy & Architecture at MapR Technologies, discussed single-value, geo-spatial, and log time series dat...
DevOps Summit 2015 New York, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that it is now accepting Keynote Proposals. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long development cycles that produce software that is obsolete...
SYS-CON Events announced today that Gridstore™, the leader in hyper-converged infrastructure purpose-built to optimize Microsoft workloads, will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Gridstore™ is the leader in hyper-converged infrastructure purpose-built for Microsoft workloads and designed to accelerate applications in virtualized environments. Gridstore’s hyper-converged infrastructure is the ...