EDMONTON, ALBERTA -- (Marketwired) -- 04/25/14 -- Capital Power Corporation (Capital Power, or the Company) (TSX: CPX) today released its financial results for the quarter ended March 31, 2014.

Funds from operations were $90 million in the first quarter of 2014, down 13%, on a comparable basis, from $103 million in the first quarter of 2013. Net income attributable to shareholders in the first quarter of 2014 was $32 million, or $0.33 per share, compared with $34 million, or $0.44 per share, in the comparable period of 2013. Normalized earnings attributable to common shareholders in the first quarter of 2014, after adjusting for one-time items and fair value adjustments, were $25 million or $0.31 per share compared with $25 million or $0.36 per share in the first quarter of 2013.

"Financial results in the first quarter were modestly below our expectations primarily due to a 10-day unplanned outage at Genesee 1," said Brian Vaasjo, President and CEO of Capital Power. "Despite the unplanned outage at Genesee 1, the rest of the fleet performed well with an overall average plant availability of 94% in the first quarter. With Alberta power prices generally in-line with our forecast for the remaining nine months of 2014, we remain on track to achieve our funds from operations financial target for this year."

"We have finalized joint arrangement agreements with ENMAX Corporation to advance the development, construction, and operation of the Genesee 4 and 5 facility," said Mr. Vaasjo. "Discussions relating to commercial agreements are on-going with the expectation that these agreements will be finalized when the project receives its full notice to proceed. Genesee 4 and 5 is scheduled for completion later this decade when additional generation in the province is required to meet growing demand and replace generation from the retirement of coal-fired units."

"We are pleased to welcome our new joint venture partners, Westmoreland Coal Company (Westmoreland) and Altius Minerals Corporation, on the Genesee coal mine as part of Westmoreland's recent acquisition of Prairie Mines & Minerals Royalty Ltd.'s coal operations. Westmoreland has strong experience in mine-mouth operations and is recognized as the lowest-cost fuel supplier to some of the cleanest, most economical and highly utilized coal-fired utility owned power plants in North America."


----------------------------------------------------------------------------
Operational and Financial Highlights(1)                   Three months ended
(unaudited)                                                         March 31
----------------------------------------------------------------------------
(millions of dollars except per share and
 operational amounts)                                     2014          2013
----------------------------------------------------------------------------
Electricity generation (excluding acquired
 Sundance PPA) (GWh)                                     3,241         4,142
----------------------------------------------------------------------------
Generation plant availability (excluding acquired
 Sundance PPA) (%)                                         94%           94%
----------------------------------------------------------------------------
Revenues                                           $       308   $       365
----------------------------------------------------------------------------
Adjusted EBITDA (2)                                $       113   $       135
----------------------------------------------------------------------------
Net income                                         $        38   $        48
----------------------------------------------------------------------------
Net income attributable to shareholders of the
 Company                                           $        32   $        34
----------------------------------------------------------------------------
Normalized earnings attributable to common
 shareholders (2)                                  $        25   $        25
----------------------------------------------------------------------------
Basic earnings per share                           $      0.33   $      0.44
----------------------------------------------------------------------------
Diluted earnings per share                         $      0.33   $      0.44
----------------------------------------------------------------------------
Normalized earnings per share (2)                  $      0.31   $      0.36
----------------------------------------------------------------------------
Funds from operations (2)                          $        90   $       103
----------------------------------------------------------------------------
Purchase of property, plant and equipment and
 other assets                                      $        75   $       293
----------------------------------------------------------------------------
Dividends per common share, declared               $     0.315   $     0.315
----------------------------------------------------------------------------
(1) The operational and financial highlights in this press release should be
    read in conjunction with Management's Discussion and Analysis and the
    audited Consolidated Financial Statements for the three months ended
    March 31, 2014.
(2) Earnings before finance expense, income tax expense, depreciation and
    amortization, impairments, foreign exchange losses, and gains on
    disposals (adjusted EBITDA), normalized earnings attributable to common
    shareholders, normalized earnings per share, and funds from operations
    are non-GAAP financial measures and do not have standardized meanings
    under GAAP and are, therefore, unlikely to be comparable to similar
    measures used by other enterprises. See Non-GAAP Financial Measures.

Significant Event

Construction of K2 Wind Power Project commences

On March 24, 2014, construction of the K2 Wind Power Project (K2 Wind) commenced following the successful completion of an $850 million financing in the form of a construction loan that will convert to long-term project debt once K2 Wind starts commercial operations. K2 Wind is a 270 megawatt (MW) wind power project located in Goderich, Ontario that is under joint development by Samsung Renewable Energy, Inc., Pattern Energy Group LP and Capital Power with operations expected to commence in the second half of 2015. The total estimated project cost has been revised upward to $930 million from the previous upper end of range of $900 million primarily due to foreign exchange changes on U.S. contract deliverables. Capital Power's share is $310 million. As a higher portion of the project is expected to be financed with project debt than originally forecast, Capital Power expects higher equity returns on the project.

Subsequent Events

Genesee 4 and 5

On April 24, 2014, Capital Power and ENMAX Corporation (ENMAX) executed a purchase and sale agreement in support of a joint arrangement agreement to jointly develop, construct, and operate the Genesee 4 and 5 power project. The joint arrangement agreement will provide provisions for, among other things, an agreement for ENMAX to purchase approximately 225 MW from Capital Power for eight years. The joint arrangement agreement closing is expected to occur in May 2014.

Genesee coal mine

Capital Power is a party to various agreements with Prairie Mines & Minerals Royalty Ltd. (PMRL) in relation to the operations of the Genesee coal mine (Genesee Coal Mine Agreements). Pursuant to the Genesee Coal Mine Agreements, PMRL operates the Genesee Coal Mine. In connection with the acquisition by Westmoreland Coal Company (Westmoreland) of PMRL and the acquisition by Altius Minerals Corporation (Altius) of the royalty assets of PMRL, the Genesee Coal Mine Agreements and certain related agreements have, amongst other things, been amended to: (a) confirm the acquisitions by Westmoreland and Altius; and (b) provide for certain amendments to the Genesee Coal Mine Agreements.

Analyst Conference Call and Webcast

Capital Power will be hosting a conference call and live webcast with analysts on April 28, 2014 at 11:00 AM (ET) to discuss the first quarter results. The conference call dial-in numbers are:

(604) 681-8564 (Vancouver)

(403) 532-5601 (Calgary)

(416) 623-0333 (Toronto)

(514) 687-4017 (Montreal)

(855) 353-9183 (toll-free from Canada and USA)

Participant access code for the call: 21543#

A replay of the conference call will be available following the call at: (855) 201-2300 (toll-free) and entering conference reference number 1153040# followed by participant code 21543#. The replay will be available until midnight on July 28, 2014.

Interested parties may also access the live webcast on the Company's website at www.capitalpower.com with an archive of the webcast available following the conference call.

Non-GAAP Financial Measures

The Company uses (i) adjusted EBITDA, (ii) funds from operations, (iii) normalized earnings attributable to common shareholders, and (iv) normalized earnings per share as financial performance measures. These terms are not defined financial measures according to GAAP and do not have standardized meanings prescribed by GAAP, and are, therefore, unlikely to be comparable to similar measures used by other enterprises. These measures should not be considered alternatives to gross income, net income, net income attributable of shareholders of the Company, net cash flows from operating activities or other measures of financial performance calculated in accordance with GAAP. Rather, these measures are provided to complement GAAP measures in the analysis of the Company's results of operations from management's perspective. Reconciliations of adjusted EBITDA to gross income, operating income and net income, funds from operations to net cash flows from operating activities and normalized earnings attributable to common shareholders to net income attributable to shareholders of the Company are contained in the Company's Management's Discussion and Analysis dated April 24, 2014 for the three months ended March 31, 2014 which is available under the Company's profile on SEDAR at www.SEDAR.com.

Forward-looking Information

Forward-looking information or statements included in this press release are provided to inform the Company's shareholders and potential investors about management's assessment of Capital Power's future plans and operations. This information may not be appropriate for other purposes. The forward-looking information in this press release is generally identified by words such as will, anticipate, believe, plan, intend, target, and expect or similar words that suggest future outcomes.

Material forward-looking information in this press release includes information with respect to expectations regarding: (i) future cash flows, and (ii) completion of capital projects.

These statements are based on certain assumptions and analyses made by the Company in light of its experience and perception of historical trends, current conditions and expected future developments, and other factors it believes are appropriate. The material factors and assumptions used to develop these forward-looking statements relate to: (i) electricity and other energy prices, (ii) performance, (iii) business prospects and opportunities including expected growth and capital projects, (iv) status and impact of policy, legislation and regulation, and (v) effective tax rates.

Whether actual results, performance or achievements will conform to the Company's expectations and predictions is subject to a number of known and unknown risks and uncertainties which could cause actual results and experience to differ materially from the Company's expectations. Such material risks and uncertainties are: (i) changes in electricity prices in markets in which the Company operates, (ii) changes in energy commodity market prices and use of derivatives, (iii) regulatory and political environments including changes to environmental, financial reporting and tax legislation, (iv) power plant availability and performance including maintenance expenditures, (v) ability to fund current and future capital and working capital needs, (vi) acquisitions and developments including timing and costs of regulatory approvals and construction, (vii) changes in market prices and availability of fuel, and (viii) changes in general economic and competitive conditions. See Risks and Risk Management in the Company's December 31, 2013 annual Management's Discussion and Analysis for further discussion of these and other risks.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@CloudExpo Stories
Once the decision has been made to move part or all of a workload to the cloud, a methodology for selecting that workload needs to be established. How do you move to the cloud? What does the discovery, assessment and planning look like? What workloads make sense? Which cloud model makes sense for each workload? What are the considerations for how to select the right cloud model? And how does that fit in with the overall IT tranformation? In his session at 15th Cloud Expo, John Hatem, head of V...
Cloud services are the newest tool in the arsenal of IT products in the market today. These cloud services integrate process and tools. In order to use these products effectively, organizations must have a good understanding of themselves and their business requirements. In his session at 15th Cloud Expo, Brian Lewis, Principal Architect at Verizon Cloud, will outline key areas of organizational focus, and how to formalize an actionable plan when migrating applications and internal services to...
SAP is delivering break-through innovation combined with fantastic user experience powered by the market-leading in-memory technology, SAP HANA. In his General Session at 15th Cloud Expo, Thorsten Leiduck, VP ISVs & Digital Commerce, SAP, will discuss how SAP and partners provide cloud and hybrid cloud solutions as well as real-time Big Data offerings that help companies of all sizes and industries run better. SAP launched an application challenge to award the most innovative SAP HANA and SAP ...
SYS-CON Events announced today that ElasticBox is holding a Hackathon at DevOps Summit, November 6 from 12 pm -4 pm at the Santa Clara Convention Center in Santa Clara, CA. You can enter as an individual or team of up to 10 developers. A New Star Is Born Every Month! All completed ElasticBoxes will then be sent to a judging panel - 12 winners will be featured on the ElasticBox website in 2015. All entrants will receive five full enterprise licenses for one year + ElasticBox headphones + Elasti...
Ixia develops amazing products so its customers can connect the world. Ixia helps its customers provide an always-on user experience through fast, secure delivery of dynamic connected technologies and services. Through actionable insights that accelerate and secure application and service delivery, Ixia's customers benefit from faster time to market, optimized application performance and higher-quality deployments.
SYS-CON Events announced today that Calm.io has been named “Bronze Sponsor” of DevOps Summit Silicon Valley, which will take place on November 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA. Calm.io is a cloud orchestration platform for AWS, vCenter, OpenStack, or bare metal, that runs your CL tools puppet, Chef, shell, git, Jenkins, nagios, and will soon support New Relic and Docker. It can run hosted, or on premise and provides VM automation / expiry, self-service portals,...
In her General Session at 15th Cloud Expo, Anne Plese, Senior Consultant, Cloud Product Marketing, at Verizon Enterprise, will focus on finding the right mix of renting vs. buying Oracle capacity to scale to meet business demands, and offer validated Oracle database TCO models for Oracle development and testing environments. Anne Plese is a marketing and technology enthusiast/realist with over 19+ years in high tech. At Verizon Enterprise, she focuses on driving growth for the Verizon Cloud pla...
SYS-CON Events announced today that Aria Systems, the recurring revenue expert, has been named "Bronze Sponsor" of SYS-CON's 15th International Cloud Expo®, which will take place on November 4-6, 2014, at the Santa Clara Convention Center in Santa Clara, CA. Aria Systems helps leading businesses connect their customers with the products and services they love. Industry leaders like Pitney Bowes, Experian, AAA NCNU, VMware, HootSuite and many others choose Aria to power their recurring revenue bu...
The Internet of Things (IoT) is going to require a new way of thinking and of developing software for speed, security and innovation. This requires IT leaders to balance business as usual while anticipating for the next market and technology trends. Cloud provides the right IT asset portfolio to help today’s IT leaders manage the old and prepare for the new. Today the cloud conversation is evolving from private and public to hybrid. This session will provide use cases and insights to reinforce t...
As Platform as a Service (PaaS) matures as a category, developers should have the ability to use the programming language of their choice to build applications and have access to a wide array of services. Bluemix is IBM's open cloud development platform that enables users to easily build cloud-based, creative mobile and web applications without having to spend large amounts of time and resources on configuring infrastructure and multiple software licenses. In this track, you will learn about the...
Blue Box has closed a $10 million Series B financing. The round was led by a strategic investor and included participation from prior investors including Voyager Capital and Founders Collective, as well as the Blue Box executive team. This round follows a $4.3 million Series A closed in December of 2012 and led by Voyager Capital. In May of this year, the company announced general availability of its private cloud as a service offering, Blue Box Cloud. Since that release, the company has dem...
SYS-CON Events announced today that Verizon has been named "Gold Sponsor" of SYS-CON's 15th International Cloud Expo®, which will take place on November 4-6, 2014, at the Santa Clara Convention Center in Santa Clara, CA. Verizon Enterprise Solutions creates global connections that generate growth, drive business innovation and move society forward. With industry-specific solutions and a full range of global wholesale offerings provided over the company's secure mobility, cloud, strategic network...
SimpleECM is the only platform to offer a powerful combination of enterprise content management (ECM) services, capture solutions, and third-party business services providing simplified integrations and workflow development for solution providers. SimpleECM is opening the market to businesses of all sizes by reinventing the delivery of ECM services. Our APIs make the development of ECM services simple with the use of familiar technologies for a frictionless integration directly into web applicat...
The only place to be June 9-11 is Cloud Expo & @ThingsExpo 2015 East at the Javits Center in New York City. Join us there as delegates from all over the world come to listen to and engage with speakers & sponsors from the leading Cloud Computing, IoT & Big Data companies. Cloud Expo & @ThingsExpo are the leading events covering the booming market of Cloud Computing, IoT & Big Data for the enterprise. Speakers from all over the world will be hand-picked for their ability to explore the economic...
Cloudwick, the leading big data DevOps service and solution provider to the Fortune 1000, announced Big Loop, its multi-vendor operations platform. Cloudwick Big Loop creates greater collaboration between Fortune 1000 IT staff, developers and their database management systems as well as big data vendors. This allows customers to comprehensively manage and oversee their entire infrastructure, which leads to more successful production cluster operations, and scale-out. Cloudwick Big Loop supports ...
To manage complex web services with lots of calls to the cloud, many businesses have invested in Application Performance Management (APM) and Network Performance Management (NPM) tools. Together APM and NPM tools are essential aids in improving a business’s infrastructure required to support an effective web experience… but they are missing a critical component – Internet visibility. Internet connectivity has always played a role in customer access to web presence, but in the past few years use...
SAP is delivering break-through innovation combined with fantastic user experience powered by the market-leading in-memory technology, SAP HANA. In his General Session at 15th Cloud Expo, Thorsten Leiduck, VP ISVs & Digital Commerce, SAP, will discuss how SAP and partners provide cloud and hybrid cloud solutions as well as real-time Big Data offerings that help companies of all sizes and industries run better. SAP launched an application challenge to award the most innovative SAP HANA and SAP ...
Software AG helps organizations transform into Digital Enterprises, so they can differentiate from competitors and better engage customers, partners and employees. Using the Software AG Suite, companies can close the gap between business and IT to create digital systems of differentiation that drive front-line agility. We offer four on-ramps to the Digital Enterprise: alignment through collaborative process analysis; transformation through portfolio management; agility through process automation...
What are the benefits of using an enterprise-grade orchestration platform? In their session at 15th Cloud Expo, Jeff Tegethoff, CEO of Appcore, and Kedar Poduri, Senior Director of Product Management at Citrix Systems, will take a closer look at the architectural design factors needed to support diverse workloads and how to run these workloads efficiently as a service provider. They will also discuss how to deploy private cloud environments in 15 minutes or less.
Headquartered in Santa Monica, California, Bitium was founded by Kriz and Erik Gustavson. The 1,500 cloud-based application using Bitium’s analytics, app management, and single sign-on services include bug trackers, customer service dashboards, Google Apps, and social networks. The firm states website administrators can do multiple tasks online without revealing passwords. Bitium’s advisors include Microsoft’s former CMO and the former senior vice president of strategy, the founder and CEO of Li...