Paramount Resources Ltd. First Quarter 2014 Results; Musreau Deep Cut Facility Construction Complete; Final Commissioning Underway - First Sales Gas In June

CALGARY, ALBERTA -- (Marketwired) -- 05/07/14 -- Paramount Resources Ltd. (TSX: POU)

FIRST QUARTER OVERVIEW

Oil and Gas Operations


--  Construction of Paramount's wholly-owned 200 MMcf/d Musreau Deep Cut
    Facility is complete and the final stages of commissioning are underway.
    The expected total cost of the facility remains in-line with the
    original budget at approximately $190 million.
--  First quarter sales volumes averaged 21,028 Boe/d. Sales volumes will
    begin to ramp-up after the Musreau Deep Cut Facility starts up in June.
--  Paramount's sales volumes are expected to reach approximately 50,000
    Boe/d in 2014 and increase to approximately 70,000 Boe/d in 2015. NGLs
    volumes are projected to increase from 15 percent of total sales volumes
    in the first quarter to approximately 40 percent by the end of the year.
--  The Company's first quarter netback increased 72 percent to $55.7
    million in 2014 from $32.4 million in 2013, driven mainly by higher
    realized natural gas prices. Paramount's first quarter 2014 gas
    production remained unhedged, enabling the Company to capture strong
    winter pricing, including significant increases in daily spot prices.
--  First quarter drilling activities in the Kaybob area were focused on two
    10-well Montney pads and one 5-well Montney pad on the northern portion
    of the Company's lands, where liquids yields are anticipated to be the
    highest. Drilling operations are expected to be finished on all 25 wells
    by the end of July, with completion and tie-in operations to follow.
--  In March 2014, Paramount closed the sale of coal bed methane properties
    producing approximately 6 MMcf/d in the Chain-Delia area of Alberta for
    $11.7 million in common shares of a TSX-Venture Exchange listed Company.

Strategic Investments


--  In April 2014, Paramount entered into an agreement with MGM Energy Corp.
    ("MGM Energy") to acquire all of the shares of MGM Energy that it does
    not already own (the "Arrangement"). All shareholders of MGM Energy
    other than Paramount would receive one Common Share of Paramount for
    every 300 shares of MGM Energy. The Arrangement is subject to MGM Energy
    shareholder and court approvals. It is anticipated that Paramount would
    issue approximately 1.1 million Common Shares to MGM Energy shareholders
    under the arrangement.
--  Shale gas exploration drilling operations at Dunedin in northeast
    British Columbia have been suspended due to spring break-up and are
    scheduled to resume in the winter of 2014 / 2015.


FINANCIAL AND OPERATING HIGHLIGHTS (1)
($ millions, except as noted)
Three months ended March 31                   2014     2013 (2)   % Change

FINANCIAL
Petroleum and natural gas sales               86.2        61.3          41
Funds flow from operations                    33.5        16.6         102
 Per share - diluted ($/share)                0.34        0.18
Net income (loss)                             (8.9)        0.4          NM
 Per share - diluted ($/share)               (0.09)          -
Exploration and development
 expenditures                                173.2       145.2          19
Investments in other entities - market
 value (3)                                   718.5       719.6           -
Total assets                               2,614.6     2,076.5          26
Net debt                                   1,273.7       857.9          48
Common shares outstanding (thousands)       97,532      90,130           8

OPERATING
Sales volumes
 Natural gas (MMcf/d)                        104.7       113.6          (8)
 NGLs (Bbl/d)                                3,079       2,662          16
 Oil (Bbl/d)                                   500         998         (50)
 Total (Boe/d)                              21,028      22,591          (7)
Average realized price
 Natural gas ($/Mcf)                          6.04        3.47          74
 NGLs ($/Bbl)                                86.97       73.78          18
 Oil ($/Bbl)                                 96.56       84.37          14
 Total ($/Boe)                               45.56       30.16          51

Operating expense ($/Boe)                     9.75       10.18          (4)
Netback ($/Boe)                              29.40       15.28          92

Net Wells (excluding oil sands
 evaluation)                                    12           9          33
Net oil sands evaluation wells                   -           6        (100)
---------------------------------------------------------------------------
---------------------------------------------------------------------------
(1) Readers are referred to the advisories concerning non-GAAP measures and
    Oil and Gas Measures and Definitions in the Advisories section of this
    document.
(2) Amounts include the results of discontinued operations. Refer to
    Management's Discussion and Analysis for the three months ended March
    31, 2014.
(3) Based on the period-end closing prices of publicly-traded enterprises
    and the book value of the remaining investments.
NM - Not meaningful

OUTLOOK

Paramount's 2014 capital budget for exploration and development ("E&D") and Strategic Investments remains at $650 million, excluding land acquisitions and capitalized interest. E&D spending will continue to focus on the Company's Deep Basin developments, including drilling and completing wells in the Kaybob area and at Karr-Gold Creek, and the completion of new deep cut facilities and related infrastructure. Shale gas exploration activities in the Liard Basin are substantially complete for this winter season.

Paramount will begin to ramp-up production as the Musreau Deep Cut Facility starts up, additional components of the Company's Kaybob area infrastructure are completed and third-party de-ethanization capacity becomes available. Sales volumes are expected to reach approximately 50,000 Boe/d in 2014 and increase to approximately 70,000 Boe/d in 2015, depending upon the availability of downstream third-party de-ethanization capacity.

Despite achieving sales volumes of approximately 25,000 Boe/d in April 2014, second quarter sales volumes are expected to average between 17,500 Boe/d and 20,000 Boe/d. The Company's production will be impacted later in the quarter by a scheduled third-party plant outage in the Grande Prairie COU, as well as outages in the Kaybob COU resulting from the integration of the non-operated Smoky deep cut facility expansion and final commissioning activities for the Musreau Deep Cut Facility. Production will ramp-up significantly in the third quarter following the start-up of the Musreau Deep Cut Facility.

ADDITIONAL INFORMATION

ABOUT PARAMOUNT

Paramount is an independent, publicly traded, Canadian corporation that explores for and develops conventional petroleum and natural gas prospects, pursues longer-term non-conventional exploration and pre-development projects and holds investments in other entities. The Company's principal properties are primarily located in Alberta and British Columbia. Paramount's Class A Common Shares are listed on the Toronto Stock Exchange under the symbol "POU".

Paramount's first quarter 2014 report, including Management's Discussion and Analysis and the Company's unaudited Interim Condensed Consolidated Financial Statements can be obtained at: http://media3.marketwire.com/docs/944113_pr.pdf

This information will also be made available through Paramount's website at www.paramountres.com and SEDAR at www.sedar.com.

ADVISORIES

FORWARD-LOOKING INFORMATION

Certain statements in this document constitute forward-looking information under applicable securities legislation. Forward-looking information typically contains statements with words such as "anticipate", "believe", "estimate", "will", "expect", "plan", "schedule", "intend", "propose", or similar words suggesting future outcomes or an outlook. Forward looking information in this document includes, but is not limited to:


--  projected production and sales volumes and growth and the timing
    thereof;
--  forecast capital expenditures;
--  exploration, development, and associated operational plans and
    strategies and the anticipated timing of such activities;
--  projected timelines for constructing, commissioning and/or starting-up
    new and expanded deep cut natural gas processing and associated
    facilities;
--  the projected availability of third party processing, transportation,
    fractionation, de-ethanization and other facilities; and
--  business strategies and objectives.

Such forward-looking information is based on a number of assumptions which may prove to be incorrect. Assumptions have been made with respect to the following matters, in addition to any other assumptions identified in this document:


--  future oil, bitumen, natural gas, NGLs and other commodity prices;
--  royalty rates, taxes and capital, operating, general & administrative
    and other costs;
--  foreign currency exchange rates and interest rates;
--  general economic and business conditions;
--  the ability of Paramount to obtain the required capital to finance its
    exploration, development and other operations;
--  the ability of Paramount to obtain equipment, services, supplies and
    personnel in a timely manner and at an acceptable cost to carry out its
    activities;
--  the ability of Paramount to secure adequate product processing,
    transportation, fractionation, de-ethanization and storage capacity on
    acceptable terms;
--  the ability of Paramount to market its oil, bitumen, natural gas and
    NGLs successfully to current and new customers;
--  the ability of Paramount and its industry partners to obtain drilling
    success (including in respect of anticipated production volumes,
    reserves additions and NGLs yields) and operational improvements,
    efficiencies and results consistent with expectations;
--  the timely receipt of required governmental and regulatory approvals;
    and
--  anticipated timelines and budgets being met in respect of drilling
    programs and other operations (including well completions and tie-ins
    and the construction, commissioning and start-up of new and expanded
    facilities).

Although Paramount believes that the expectations reflected in such forward looking information is reasonable, undue reliance should not be placed on it as Paramount can give no assurance that such expectations will prove to be correct. Forward-looking information is based on expectations, estimates and projections that involve a number of risks and uncertainties which could cause actual results to differ materially from those anticipated by Paramount and described in the forward looking information. The material risks and uncertainties include, but are not limited to:


--  fluctuations in oil, bitumen, natural gas, NGLs and other commodity
    prices;
--  changes in foreign currency exchange rates and interest rates;
--  the uncertainty of estimates and projections relating to future revenue,
    future production, NGLs yields, royalty rates, taxes and costs and
    expenses;
--  the ability to secure adequate product processing, transportation,
    fractionation, de-ethanization and storage capacity on acceptable terms;
--  operational risks in exploring for, developing and producing crude oil,
    bitumen, natural gas and NGLs;
--  the ability to obtain equipment, services, supplies and personnel in a
    timely manner and at an acceptable cost;
--  potential disruptions or unexpected technical or other difficulties in
    designing, developing, expanding or operating new, expanded or existing
    facilities (including third party facilities);
--  industry wide processing, pipeline, de-ethanization, and fractionation
    infrastructure outages, disruptions and constraints;
--  risks and uncertainties involving the geology of oil and gas deposits;
--  the uncertainty of reserves and resources estimates;
--  general business, economic and market conditions;
--  the ability to generate sufficient cash flow from operations and obtain
    financing at an acceptable cost to fund planned exploration, development
    and operational activities and meet current and future obligations
    (including costs of anticipated new and expanded facilities and other
    projects and product processing, transportation, de-ethanization,
    fractionation and similar commitments);
--  changes in, or in the interpretation of, laws, regulations or policies
    (including environmental laws);
--  the ability to obtain required governmental or regulatory approvals in a
    timely manner, and to enter into and maintain leases and licenses;
--  the effects of weather;
--  the timing and cost of future abandonment and reclamation obligations
    and potential liabilities for environmental damage and contamination;
--  uncertainties regarding aboriginal claims and in maintaining
    relationships with local populations and other stakeholders;
--  the outcome of existing and potential lawsuits, regulatory actions,
    audits and assessments; and
--  other risks and uncertainties described elsewhere in this document and
    in Paramount's other filings with Canadian securities authorities.

The foregoing list of risks is not exhaustive. For more information relating to risks, see the section titled "RISK FACTORS" in Paramount's current annual information form. The forward-looking information contained in this document is made as of the date hereof and, except as required by applicable securities law, Paramount undertakes no obligation to update publicly or revise any forward-looking statements or information, whether as a result of new information, future events or otherwise.

NON-GAAP MEASURES

In this document "Funds flow from operations", "Netback", "Net Debt", "Exploration and development expenditures" and "Investments in other entities - market value", collectively the "Non-GAAP measures", are used and do not have any standardized meanings as prescribed by International Financial Reporting Standards.

Funds flow from operations refers to cash from operating activities before net changes in operating non-cash working capital, geological and geophysical expenses and asset retirement obligation settlements. Funds flow from operations is commonly used in the oil and gas industry to assist management and investors in measuring the Company's ability to fund capital programs and meet financial obligations. Netback equals petroleum and natural gas sales less royalties, operating costs, production taxes and transportation costs. Netback is commonly used by management and investors to compare the results of the Company's oil and gas operations between periods. Net Debt is a measure of the Company's overall debt position after adjusting for certain working capital amounts and is used by management to assess the Company's overall leverage position. Refer to the liquidity and capital resources section of the Company's Management's Discussion and Analysis for the period for the calculation of Net Debt. Exploration and development expenditures refer to capital expenditures and geological and geophysical costs incurred by the Company's COUs (excluding land and acquisitions). The exploration and development expenditure measure provides management and investors with information regarding the Company's Principal Property spending on drilling and infrastructure projects, separate from land acquisition activity. Investments in other entities - market value reflects the Company's investments in enterprises whose securities trade on a public stock exchange at their period end closing price (e.g. Trilogy Energy Corp., MEG Energy Corp., MGM Energy Corp., Strategic Oil & Gas Ltd. and others), and investments in all other entities at book value. Paramount provides this information because the market values of equity-accounted investments, which are significant assets of the Company, are often materially different than their carrying values.

Non-GAAP measures should not be considered in isolation or construed as alternatives to their most directly comparable measure calculated in accordance with GAAP, or other measures of financial performance calculated in accordance with GAAP. The Non-GAAP measures are unlikely to be comparable to similar measures presented by other issuers.

OIL AND GAS MEASURES AND DEFINITIONS

This document contains disclosures expressed as "Boe" and "Boe/d". All oil and natural gas equivalency volumes have been derived using the ratio of six thousand cubic feet of natural gas to one barrel of oil. Equivalency measures may be misleading, particularly if used in isolation. A conversion ratio of six thousand cubic feet of natural gas to one barrel of oil is based on an energy equivalency conversion method primarily applicable at the burner tip and does not represent a value equivalency at the well head. The term "liquids" is used to represent oil and natural gas liquids.

During the first quarter of 2014, the value ratio between crude oil and natural gas was approximately 16:1. This value ratio is significantly different from the energy equivalency ratio of 6:1. Using a 6:1 ratio would be misleading as an indication of value.

Contacts:
Paramount Resources Ltd.
J.H.T. (Jim) Riddell
President and Chief Operating Officer
(403) 290-3600
(403) 262-7994 (FAX)

Paramount Resources Ltd.
B.K. (Bernie) Lee
Chief Financial Officer
(403) 290-3600
(403) 262-7994 (FAX)
www.paramountres.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
The term culture has had a polarizing effect among DevOps supporters. Some propose that culture change is critical for success with DevOps, but are remiss to define culture. Some talk about a DevOps culture but then reference activities that could lead to culture change and there are those that talk about culture change as a set of behaviors that need to be adopted by those in IT. There is no question that businesses successful in adopting a DevOps mindset have seen departmental culture change, ...
The Internet of Things promises to transform businesses (and lives), but navigating the business and technical path to success can be difficult to understand. In his session at @ThingsExpo, Sean Lorenz, Technical Product Manager for Xively at LogMeIn, demonstrated how to approach creating broadly successful connected customer solutions using real world business transformation studies including New England BioLabs and more.
The security devil is always in the details of the attack: the ones you've endured, the ones you prepare yourself to fend off, and the ones that, you fear, will catch you completely unaware and defenseless. The Internet of Things (IoT) is nothing if not an endless proliferation of details. It's the vision of a world in which continuous Internet connectivity and addressability is embedded into a growing range of human artifacts, into the natural world, and even into our smartphones, appliances, a...
SYS-CON Media announced that Centrify, a provider of unified identity management across cloud, mobile and data center environments that delivers single sign-on (SSO) for users and a simplified identity infrastructure for IT, has launched an ad campaign on Cloud Computing Journal. The ads focus on security: how an organization can successfully control privilege for all of the organization’s identities to mitigate identity-related risk without slowing down the business, and how Centrify provides ...
"Matrix is an ambitious open standard and implementation that's set up to break down the fragmentation problems that exist in IP messaging and VoIP communication," explained John Woolf, Technical Evangelist at Matrix, in this SYS-CON.tv interview at @ThingsExpo, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
SYS-CON Events announced today Isomorphic Software, the global leader in high-end, web-based business applications, will exhibit at SYS-CON's DevOps Summit 2015 New York, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Isomorphic Software is the global leader in high-end, web-based business applications. We develop, market, and support the SmartClient & Smart GWT HTML5/Ajax platform, combining the productivity and performance of traditional desktop software ...
DevOps Summit 2015 New York, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that it is now accepting Keynote Proposals. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long development cycles that produce software that is obsolete...
The 3rd International @ThingsExpo, co-located with the 16th International Cloud Expo – to be held June 9-11, 2015, at the Javits Center in New York City, NY – is now accepting Hackathon proposals. Hackathon sponsorship benefits include general brand exposure and increasing engagement with the developer ecosystem. At Cloud Expo 2014 Silicon Valley, IBM held the Bluemix Developer Playground on November 5 and ElasticBox held the DevOps Hackathon on November 6. Both events took place on the expo fl...
We are reaching the end of the beginning with WebRTC, and real systems using this technology have begun to appear. One challenge that faces every WebRTC deployment (in some form or another) is identity management. For example, if you have an existing service – possibly built on a variety of different PaaS/SaaS offerings – and you want to add real-time communications you are faced with a challenge relating to user management, authentication, authorization, and validation. Service providers will w...
There's Big Data, then there's really Big Data from the Internet of Things. IoT is evolving to include many data possibilities like new types of event, log and network data. The volumes are enormous, generating tens of billions of logs per day, which raise data challenges. Early IoT deployments are relying heavily on both the cloud and managed service providers to navigate these challenges. In her session at Big Data Expo®, Hannah Smalltree, Director at Treasure Data, discussed how IoT, Big D...
The Internet of Things is tied together with a thin strand that is known as time. Coincidentally, at the core of nearly all data analytics is a timestamp. When working with time series data there are a few core principles that everyone should consider, especially across datasets where time is the common boundary. In his session at Internet of @ThingsExpo, Jim Scott, Director of Enterprise Strategy & Architecture at MapR Technologies, discussed single-value, geo-spatial, and log time series dat...
The Internet of Things will put IT to its ultimate test by creating infinite new opportunities to digitize products and services, generate and analyze new data to improve customer satisfaction, and discover new ways to gain a competitive advantage across nearly every industry. In order to help corporate business units to capitalize on the rapidly evolving IoT opportunities, IT must stand up to a new set of challenges. In his session at @ThingsExpo, Jeff Kaplan, Managing Director of THINKstrateg...
Fundamentally, SDN is still mostly about network plumbing. While plumbing may be useful to tinker with, what you can do with your plumbing is far more intriguing. A rigid interpretation of SDN confines it to Layers 2 and 3, and that's reasonable. But SDN opens opportunities for novel constructions in Layers 4 to 7 that solve real operational problems in data centers. "Data center," in fact, might become anachronistic - data is everywhere, constantly on the move, seemingly always overflowing. Net...
DevOps Summit 2015 New York, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that it is now accepting Keynote Proposals. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long development cycles that produce software that is obsolete...
WebRTC defines no default signaling protocol, causing fragmentation between WebRTC silos. SIP and XMPP provide possibilities, but come with considerable complexity and are not designed for use in a web environment. In his session at @ThingsExpo, Matthew Hodgson, technical co-founder of the Matrix.org, discussed how Matrix is a new non-profit Open Source Project that defines both a new HTTP-based standard for VoIP & IM signaling and provides reference implementations.