Asanko Gold Mine Phase 1 Project Update

Highlights:

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 06/18/14 -- Asanko Gold Inc. ("Asanko" or the "Company") (TSX:AKG)(NYSE MKT:AKG) is pleased to provide an update on activities at the fully funded and permitted Asanko Gold Mine (the "AGM" or the "Project") in Ghana. In early April, the Company engaged DRA as the Engineering, Procurement, Construction and Management ("EPCM") contractor for the design and construction of Phase 1 of the Project as well as Knight Piesold to design the Tailings Storage Facility and carry out detailed geotechnical engineering works for the site. Shortly thereafter, the Company initiated an early works program designed to advance the critical activities that will allow the Company to maintain its project schedule, targeting first gold in Q1 2016.

Detailed engineering and early works programs are proceeding on schedule, ground breaking at the plant site is expected to commence in August 2014, pending a positive investment decision on the Project by the Board in July.

Asanko Gold Mine Site Early Works

The site early works program, which began in April 2014 with a budget of approximately US$16 million, has been progressing on schedule and on budget. For photos of the early works progress at AGM, please click on the following link: http://www.asanko.com/s/photogallery.asp


--  Upgrading of the site access road is nearing completion with 8km out of
    11 km completed. 
    
--  Refurbishment of the mining village is 80% complete. 
    
--  The plant medical clinic construction is nearing completion and will be
    operational in early July. 
    
--  Mobile equipment orders have been placed and delivery of key equipment
    is scheduled for July. 
    
--  Refurbishment and upgrades to the site's airstrip have been completed
    and inspected by the regulatory authorities. 
    
--  Construction of the communication tower and office potable water systems
    have commenced. 

Detailed Engineering

Since commencing work in early April, DRA have advanced several key front-end engineering and design activities, including:


--  Plant layout is now complete, revised to incorporate a potential Phase 2
    expansion to the plant. 
    
--  An initial order is expected to be placed shortly for the detailed
    design of the 161kV electrical infrastructure. 
    
--  Various structural and civil designs are underway to allow bulk earth
    works to commence at the plant site in August 2014. 
    
--  Mechanical equipment list, process and instrumentation diagrams and
    process design criteria have been completed. 
    
--  Operating costs are in the process of being updated. 
    
--  Civil, mechanical, electrical and infrastructure designs have been
    completed to sufficient detail to allow the detailed capital cost to be
    estimated. 
    
--  The Control Base Estimate ("CBE") or detailed capital cost estimate for
    the Project is in the final stages of completion with all tenders
    closed. 

Knight Piesold have advanced geotechnical engineering with some additional geotechnical drilling completed over the past two months to support the detailed mine plan for the Nkran pit.

Resource Update & Mine Planning

Asanko's independent Qualified Person with respect to NI 43-101 has completed revisions to the Mineral Resource Estimate ("MRE") for the Nkran and Adubiaso pits, which are currently being used for detailed mine planning.

While the overall MRE has not changed materially since the previous estimate (announced in September 2012 and the basis for the Company's current disclosure), the revised estimate incorporates a more detailed geological model and utilises a combination of Indicator Kriging and Ordinary Kriging to bring a higher level of confidence and detail to the MRE which makes it more suitable for detailed mine planning.

DRA are currently working on the detailed mine plan, with a preliminary plan to be ready for the Board's investment decision in July and the final plan to be finalised during Q3 2014.

The revised MRE, detailed mine plan and CBE will all be combined into a Definitive Project Plan which is expected to be completed by Q4 2014 and filed as a NI 43-101 compliant technical report.

The contract tendering process has begun for the pre-strip component of the Nkran pit, which the Company expects to begin in Q4 2014. The pre-stripping of Nkran involves cutting back the existing pit from historical mining operations. Total pre-strip requirements are approximately 26 million tonnes of material to be moved to access the Nkran ore for the commencement of mining operations in Q3 2015. The cost of the pre-strip has been included in the Project's capital cost, as per the Company's current disclosure.

Permitting

Phase 1 of the Project is fully permitted for the commencement of construction. In early June, the Minerals Commission declared a moratorium over the expected mining and infrastructure areas. The declaration of a moratorium is an important precursor to construction activity and will establish the basis for crop compensation and land use deprivation processes to commence with the local communities. In addition, work is underway on a Resettlement Action Plan ("RAP") which will be reviewed and approved by the Ghanaian Environmental Protection Agency in Q4 2014.

The Company continues to advance the permitting required to mine both Dynamite Hill and the Phase 2 mining operations at Esaase. In early June, a Temporary Mining Permit was received for the Esaase deposit which would allow mining operations to commence at Esaase. Full environmental permitting at Esaase is ongoing.

Organisational Capability

On June 1st, the Company officially appointed Jonathan Ebo Collins as General Manager - Asanko Gold Mine. Charles Amoah, the current acting General Manager and a metallurgist, will continue with the Company as Manager - Processing. Recruitment is underway for other key operating positions as the Company continues to build its organisational capability in Ghana.

Jonathan is a Ghanaian national and a mining engineer with over 25 years of operational experience in the African mining sector. He has worked in Ghana, South Africa and Liberia, predominantly for major natural resources companies such as Xstrata Coal, Anglo American, Arcelor Mittal, Total, and Sasol. He began his career with Ashanti Goldfields, now AngloGold Ashanti, at the Obuasi mine before moving to South Africa to work in the coal industry. During his career, he has been Mine Manager and General Manager of several large coal operations with both open pit and underground mines and he has overseen projects from construction and commissioning through to operations. He has won multiple national safety awards in recognition of the outstanding safety performance of the mines under his management. Jonathan holds a Bachelor of Science and a Postgraduate Diploma in Mining Engineering and is a member of the South African Institute of Mining and Metallurgy (SAIMM).

For further information please visit www.asanko.com

About Asanko Gold Inc.

Asanko's vision is to become a mid-tier gold mining company that maximizes value for all its stakeholders. Asanko's flagship project is the fully financed, multi-million ounce Asanko Gold Mine Project located in Ghana, West Africa.

Asanko is managed by highly skilled and successful technical, operational and financial professionals. The Company is strongly committed to the highest standards for environmental management, social responsibility, and health and safety for its employees and neighbouring communities.

Forward-Looking and other Cautionary Information

This release includes certain statements that may be deemed "forward-looking statements". All statements in this release, other than statements of historical facts, that address estimated resource quantities, grades and contained metals, possible future mining, exploration and development activities, are forward-looking statements. Although the Company believes the forward-looking statements are based on reasonable assumptions, such statements should not be in any way construed as guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices for metals, the conclusions of detailed feasibility and technical analyses, lower than expected grades and quantities of resources, mining rates and recovery rates and the lack of availability of necessary capital, which may not be available to the Company on terms acceptable to it or at all. The Company is subject to the specific risks inherent in the mining business as well as general economic and business conditions. For more information on the Company, Investors should review the Company's annual Form 20-F filing with the United States Securities Commission and its home jurisdiction filings that are available at www.sedar.com.

Neither Toronto Stock Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for the adequacy or accuracy of this release.

Cautionary Note to US Investors Regarding Mineral Reporting Standards:

Asanko has prepared its disclosure in accordance with the requirements of securities laws in effect in Canada, which differ from the requirements of US securities laws. Terms relating to mineral resources in this press release are defined in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects under the guidelines set out in the Canadian Institute of Mining, Metallurgy, and Petroleum Standards on Mineral Resources and Mineral Reserves. The Securities and Exchange Commission (the "SEC") permits mining companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically and legally extract or produce. Asanko uses certain terms, such as, "measured mineral resources", "indicated mineral resources", "inferred mineral resources" and "probable mineral reserves", that the SEC does not recognize (these terms may be used in this press release and are included in the public filings of Asanko which have been filed with securities commissions or similar authorities in Canada).

Contacts:
Alex Buck, Manager - Investor Relations
Telephone: +44-7932-740-452
Email: [email protected]

Greg McCunn, Chief Financial Officer
Telephone: +1-778-729-0604
Email: [email protected]

Asanko Gold Inc.
General [email protected]

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
There are 182 billion emails sent every day, generating a lot of data about how recipients and ISPs respond. Many marketers take a more-is-better approach to stats, preferring to have the ability to slice and dice their email lists based numerous arbitrary stats. However, fundamentally what really matters is whether or not sending an email to a particular recipient will generate value. Data Scientists can design high-level insights such as engagement prediction models and content clusters that a...
Containers Expo Blog covers the world of containers, as this lightweight alternative to virtual machines enables developers to work with identical dev environments and stacks. Containers Expo Blog offers top articles, news stories, and blog posts from the world's well-known experts and guarantees better exposure for its authors than any other publication. Bookmark Containers Expo Blog ▸ Here Follow new article posts on Twitter at @ContainersExpo
It's time to face reality: "Americans are from Mars, Europeans are from Venus," and in today's increasingly connected world, understanding "inter-planetary" alignments and deviations is mission-critical for cloud. In her session at 15th Cloud Expo, Evelyn de Souza, Data Privacy and Compliance Strategy Leader at Cisco Systems, discussed cultural expectations of privacy based on new research across these elements
In today's application economy, enterprise organizations realize that it's their applications that are the heart and soul of their business. If their application users have a bad experience, their revenue and reputation are at stake. In his session at 15th Cloud Expo, Anand Akela, Senior Director of Product Marketing for Application Performance Management at CA Technologies, discussed how a user-centric Application Performance Management solution can help inspire your users with every applicati...
As enterprises engage with Big Data technologies to develop applications needed to meet operational demands, new computation fabrics are continually being introduced. To leverage these new innovations, organizations are sacrificing market opportunities to gain expertise in learning new systems. In his session at Big Data Expo, Supreet Oberoi, Vice President of Field Engineering at Concurrent, Inc., discussed how to leverage existing infrastructure and investments and future-proof them against e...
The consumption economy is here and so are cloud applications and solutions that offer more than subscription and flat fee models and at the same time are available on a pure consumption model, which not only reduces IT spend but also lowers infrastructure costs, and offers ease of use and availability. In their session at 15th Cloud Expo, Ermanno Bonifazi, CEO & Founder of Solgenia, and Ian Khan, Global Strategic Positioning & Brand Manager at Solgenia, discussed this shifting dynamic with an ...
Due of the rise of Hadoop, many enterprises are now deploying their first small clusters of 10 to 20 servers. At this small scale, the complexity of operating the cluster looks and feels like general data center servers. It is not until the clusters scale, as they inevitably do, when the pain caused by the exponential complexity becomes apparent. We've seen this problem occur time and time again. In his session at Big Data Expo, Greg Bruno, Vice President of Engineering and co-founder of StackI...
Once the decision has been made to move part or all of a workload to the cloud, a methodology for selecting that workload needs to be established. How do you move to the cloud? What does the discovery, assessment and planning look like? What workloads make sense? Which cloud model makes sense for each workload? What are the considerations for how to select the right cloud model? And how does that fit in with the overall IT transformation?
You use an agile process; your goal is to make your organization more agile. But what about your data infrastructure? The truth is, today's databases are anything but agile - they are effectively static repositories that are cumbersome to work with, difficult to change, and cannot keep pace with application demands. Performance suffers as a result, and it takes far longer than it should to deliver new features and capabilities needed to make your organization competitive. As your application an...
17th Cloud Expo, taking place Nov 3-5, 2015, at the Santa Clara Convention Center in Santa Clara, CA, will feature technical sessions from a rock star conference faculty and the leading industry players in the world. Cloud computing is now being embraced by a majority of enterprises of all sizes. Yesterday's debate about public vs. private has transformed into the reality of hybrid cloud: a recent survey shows that 74% of enterprises have a hybrid cloud strategy. Meanwhile, 94% of enterprises a...
The recent trends like cloud computing, social, mobile and Internet of Things are forcing enterprises to modernize in order to compete in the competitive globalized markets. However, enterprises are approaching newer technologies with a more silo-ed way, gaining only sub optimal benefits. The Modern Enterprise model is presented as a newer way to think of enterprise IT, which takes a more holistic approach to embracing modern technologies.
SYS-CON Events announced today that SUSE, a pioneer in open source software, will exhibit at SYS-CON's DevOps Summit 2015 New York, which will take place June 9-11, 2015, at the Javits Center in New York City, NY. SUSE provides reliable, interoperable Linux, cloud infrastructure and storage solutions that give enterprises greater control and flexibility. More than 20 years of engineering excellence, exceptional service and an unrivaled partner ecosystem power the products and support that help ...
Move from reactive to proactive cloud management in a heterogeneous cloud infrastructure. In his session at 16th Cloud Expo, Manoj Khabe, Innovative Solution-Focused Transformation Leader at Vicom Computer Services, Inc., will show how to replace a help desk-centric approach with an ITIL-based service model and service-centric CMDB that’s tightly integrated with an event and incident management platform. Learn how to expand the scope of operations management to service management. He will al...
The true value of the Internet of Things (IoT) lies not just in the data, but through the services that protect the data, perform the analysis and present findings in a usable way. With many IoT elements rooted in traditional IT components, Big Data and IoT isn’t just a play for enterprise. In fact, the IoT presents SMBs with the prospect of launching entirely new activities and exploring innovative areas. CompTIA research identifies several areas where IoT is expected to have the greatest impac...
There's no doubt that the Internet of Things is driving the next wave of innovation. Google has spent billions over the past few months vacuuming up companies that specialize in smart appliances and machine learning. Already, Philips light bulbs, Audi automobiles, and Samsung washers and dryers can communicate with and be controlled from mobile devices. To take advantage of the opportunities the Internet of Things brings to your business, you'll want to start preparing now.