Asanko Gold Mine Phase 1 Project Update

Highlights:

VANCOUVER, BRITISH COLUMBIA -- (Marketwired) -- 06/18/14 -- Asanko Gold Inc. ("Asanko" or the "Company") (TSX: AKG)(NYSE MKT: AKG) is pleased to provide an update on activities at the fully funded and permitted Asanko Gold Mine (the "AGM" or the "Project") in Ghana. In early April, the Company engaged DRA as the Engineering, Procurement, Construction and Management ("EPCM") contractor for the design and construction of Phase 1 of the Project as well as Knight Piesold to design the Tailings Storage Facility and carry out detailed geotechnical engineering works for the site. Shortly thereafter, the Company initiated an early works program designed to advance the critical activities that will allow the Company to maintain its project schedule, targeting first gold in Q1 2016.

Detailed engineering and early works programs are proceeding on schedule, ground breaking at the plant site is expected to commence in August 2014, pending a positive investment decision on the Project by the Board in July.

Asanko Gold Mine Site Early Works

The site early works program, which began in April 2014 with a budget of approximately US$16 million, has been progressing on schedule and on budget. For photos of the early works progress at AGM, please click on the following link: http://www.asanko.com/s/photogallery.asp


--  Upgrading of the site access road is nearing completion with 8km out of
    11 km completed.

--  Refurbishment of the mining village is 80% complete.

--  The plant medical clinic construction is nearing completion and will be
    operational in early July.

--  Mobile equipment orders have been placed and delivery of key equipment
    is scheduled for July.

--  Refurbishment and upgrades to the site's airstrip have been completed
    and inspected by the regulatory authorities.

--  Construction of the communication tower and office potable water systems
    have commenced.

Detailed Engineering

Since commencing work in early April, DRA have advanced several key front-end engineering and design activities, including:


--  Plant layout is now complete, revised to incorporate a potential Phase 2
    expansion to the plant.

--  An initial order is expected to be placed shortly for the detailed
    design of the 161kV electrical infrastructure.

--  Various structural and civil designs are underway to allow bulk earth
    works to commence at the plant site in August 2014.

--  Mechanical equipment list, process and instrumentation diagrams and
    process design criteria have been completed.

--  Operating costs are in the process of being updated.

--  Civil, mechanical, electrical and infrastructure designs have been
    completed to sufficient detail to allow the detailed capital cost to be
    estimated.

--  The Control Base Estimate ("CBE") or detailed capital cost estimate for
    the Project is in the final stages of completion with all tenders
    closed.

Knight Piesold have advanced geotechnical engineering with some additional geotechnical drilling completed over the past two months to support the detailed mine plan for the Nkran pit.

Resource Update & Mine Planning

Asanko's independent Qualified Person with respect to NI 43-101 has completed revisions to the Mineral Resource Estimate ("MRE") for the Nkran and Adubiaso pits, which are currently being used for detailed mine planning.

While the overall MRE has not changed materially since the previous estimate (announced in September 2012 and the basis for the Company's current disclosure), the revised estimate incorporates a more detailed geological model and utilises a combination of Indicator Kriging and Ordinary Kriging to bring a higher level of confidence and detail to the MRE which makes it more suitable for detailed mine planning.

DRA are currently working on the detailed mine plan, with a preliminary plan to be ready for the Board's investment decision in July and the final plan to be finalised during Q3 2014.

The revised MRE, detailed mine plan and CBE will all be combined into a Definitive Project Plan which is expected to be completed by Q4 2014 and filed as a NI 43-101 compliant technical report.

The contract tendering process has begun for the pre-strip component of the Nkran pit, which the Company expects to begin in Q4 2014. The pre-stripping of Nkran involves cutting back the existing pit from historical mining operations. Total pre-strip requirements are approximately 26 million tonnes of material to be moved to access the Nkran ore for the commencement of mining operations in Q3 2015. The cost of the pre-strip has been included in the Project's capital cost, as per the Company's current disclosure.

Permitting

Phase 1 of the Project is fully permitted for the commencement of construction. In early June, the Minerals Commission declared a moratorium over the expected mining and infrastructure areas. The declaration of a moratorium is an important precursor to construction activity and will establish the basis for crop compensation and land use deprivation processes to commence with the local communities. In addition, work is underway on a Resettlement Action Plan ("RAP") which will be reviewed and approved by the Ghanaian Environmental Protection Agency in Q4 2014.

The Company continues to advance the permitting required to mine both Dynamite Hill and the Phase 2 mining operations at Esaase. In early June, a Temporary Mining Permit was received for the Esaase deposit which would allow mining operations to commence at Esaase. Full environmental permitting at Esaase is ongoing.

Organisational Capability

On June 1st, the Company officially appointed Jonathan Ebo Collins as General Manager - Asanko Gold Mine. Charles Amoah, the current acting General Manager and a metallurgist, will continue with the Company as Manager - Processing. Recruitment is underway for other key operating positions as the Company continues to build its organisational capability in Ghana.

Jonathan is a Ghanaian national and a mining engineer with over 25 years of operational experience in the African mining sector. He has worked in Ghana, South Africa and Liberia, predominantly for major natural resources companies such as Xstrata Coal, Anglo American, Arcelor Mittal, Total, and Sasol. He began his career with Ashanti Goldfields, now AngloGold Ashanti, at the Obuasi mine before moving to South Africa to work in the coal industry. During his career, he has been Mine Manager and General Manager of several large coal operations with both open pit and underground mines and he has overseen projects from construction and commissioning through to operations. He has won multiple national safety awards in recognition of the outstanding safety performance of the mines under his management. Jonathan holds a Bachelor of Science and a Postgraduate Diploma in Mining Engineering and is a member of the South African Institute of Mining and Metallurgy (SAIMM).

For further information please visit www.asanko.com

About Asanko Gold Inc.

Asanko's vision is to become a mid-tier gold mining company that maximizes value for all its stakeholders. Asanko's flagship project is the fully financed, multi-million ounce Asanko Gold Mine Project located in Ghana, West Africa.

Asanko is managed by highly skilled and successful technical, operational and financial professionals. The Company is strongly committed to the highest standards for environmental management, social responsibility, and health and safety for its employees and neighbouring communities.

Forward-Looking and other Cautionary Information

This release includes certain statements that may be deemed "forward-looking statements". All statements in this release, other than statements of historical facts, that address estimated resource quantities, grades and contained metals, possible future mining, exploration and development activities, are forward-looking statements. Although the Company believes the forward-looking statements are based on reasonable assumptions, such statements should not be in any way construed as guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices for metals, the conclusions of detailed feasibility and technical analyses, lower than expected grades and quantities of resources, mining rates and recovery rates and the lack of availability of necessary capital, which may not be available to the Company on terms acceptable to it or at all. The Company is subject to the specific risks inherent in the mining business as well as general economic and business conditions. For more information on the Company, Investors should review the Company's annual Form 20-F filing with the United States Securities Commission and its home jurisdiction filings that are available at www.sedar.com.

Neither Toronto Stock Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for the adequacy or accuracy of this release.

Cautionary Note to US Investors Regarding Mineral Reporting Standards:

Asanko has prepared its disclosure in accordance with the requirements of securities laws in effect in Canada, which differ from the requirements of US securities laws. Terms relating to mineral resources in this press release are defined in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects under the guidelines set out in the Canadian Institute of Mining, Metallurgy, and Petroleum Standards on Mineral Resources and Mineral Reserves. The Securities and Exchange Commission (the "SEC") permits mining companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically and legally extract or produce. Asanko uses certain terms, such as, "measured mineral resources", "indicated mineral resources", "inferred mineral resources" and "probable mineral reserves", that the SEC does not recognize (these terms may be used in this press release and are included in the public filings of Asanko which have been filed with securities commissions or similar authorities in Canada).

Contacts:
Alex Buck, Manager - Investor Relations
Telephone: +44-7932-740-452
Email: [email protected]

Greg McCunn, Chief Financial Officer
Telephone: +1-778-729-0604
Email: [email protected]

Asanko Gold Inc.
General [email protected]

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Connected devices and the Internet of Things are getting significant momentum in 2014. In his session at Internet of @ThingsExpo, Jim Hunter, Chief Scientist & Technology Evangelist at Greenwave Systems, examined three key elements that together will drive mass adoption of the IoT before the end of 2015. The first element is the recent advent of robust open source protocols (like AllJoyn and WebRTC) that facilitate M2M communication. The second is broad availability of flexible, cost-effective ...
Collecting data in the field and configuring multitudes of unique devices is a time-consuming, labor-intensive process that can stretch IT resources. Horan & Bird [H&B], Australia’s fifth-largest Solar Panel Installer, wanted to automate sensor data collection and monitoring from its solar panels and integrate the data with its business and marketing systems. After data was collected and structured, two major areas needed to be addressed: improving developer workflows and extending access to a b...
When an enterprise builds a hybrid IaaS cloud connecting its data center to one or more public clouds, security is often a major topic along with the other challenges involved. Security is closely intertwined with the networking choices made for the hybrid cloud. Traditional networking approaches for building a hybrid cloud try to kludge together the enterprise infrastructure with the public cloud. Consequently this approach requires risky, deep "surgery" including changes to firewalls, subnets...
Move from reactive to proactive cloud management in a heterogeneous cloud infrastructure. In his session at 16th Cloud Expo, Manoj Khabe, Innovative Solution-Focused Transformation Leader at Vicom Computer Services, Inc., will show how to replace a help desk-centric approach with an ITIL-based service model and service-centric CMDB that’s tightly integrated with an event and incident management platform. Learn how to expand the scope of operations management to service management. He will al...
SYS-CON Events announced today that BMC will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. BMC delivers software solutions that help IT transform digital enterprises for the ultimate competitive business advantage. BMC has worked with thousands of leading companies to create and deliver powerful IT management services. From mainframe to cloud to mobile, BMC pairs high-speed digital innovation with robust...
The true value of the Internet of Things (IoT) lies not just in the data, but through the services that protect the data, perform the analysis and present findings in a usable way. With many IoT elements rooted in traditional IT components, Big Data and IoT isn’t just a play for enterprise. In fact, the IoT presents SMBs with the prospect of launching entirely new activities and exploring innovative areas. CompTIA research identifies several areas where IoT is expected to have the greatest impac...
2015 predictions circa 1970: houses anticipate our needs and adapt, city infrastructure is citizen and situation aware, office buildings identify and preprocess you. Today smart buildings have no such collective conscience, no shared set of fundamental services to identify, predict and synchronize around us. LiveSpace and M2Mi are changing that. LiveSpace Smart Environment devices deliver over the M2Mi IoT Platform real time presence, awareness and intent analytics as a service to local connecte...
High-performing enterprise Software Quality Assurance (SQA) teams validate systems that are ready for use - getting most actively involved as components integrate and form complete systems. These teams catch and report on defects, making sure the customer gets the best software possible. SQA teams have leveraged automation and virtualization to execute more thorough testing in less time - bringing Dev and Ops together, ensuring production readiness. Does the emergence of DevOps mean the end of E...
Amazon and Google have built software-defined data centers (SDDCs) that deliver massively scalable services with great efficiency. Yet, building SDDCs has proven to be a near impossibility for companies without hyper-scale resources. In his session at 15th Cloud Expo, David Cauthron, CTO and Founder of NIMBOXX, highlighted how a mid-sized manufacturer of global industrial equipment bridged the gap from virtualization to software-defined services, streamlining operations and costs while connect...
Container technology is sending shock waves through the world of cloud computing. Heralded as the 'next big thing,' containers provide software owners a consistent way to package their software and dependencies while infrastructure operators benefit from a standard way to deploy and run them. Containers present new challenges for tracking usage due to their dynamic nature. They can also be deployed to bare metal, virtual machines and various cloud platforms. How do software owners track the usag...
The Industrial Internet revolution is now underway, enabled by connected machines and billions of devices that communicate and collaborate. The massive amounts of Big Data requiring real-time analysis is flooding legacy IT systems and giving way to cloud environments that can handle the unpredictable workloads. Yet many barriers remain until we can fully realize the opportunities and benefits from the convergence of machines and devices with Big Data and the cloud, including interoperability, ...
paradigm shifts in networking, to cloud and licensure, and all the Internet of Things in between. In 2014 automation was the name of the game. In his session at DevOps Summit, Matthew Joyce, a Sales Engineer at Big Switch, will discuss why in 2015 it’s complexity reduction. Matthew Joyce, a sales engineer at Big Switch, is helping push networking into the 21st century. He is also a hacker at NYC Resistor. Previously he worked at NASA Ames Research Center with the Nebula Project (where OpenSta...
The term culture has had a polarizing effect among DevOps supporters. Some propose that culture change is critical for success with DevOps, but are remiss to define culture. Some talk about a DevOps culture but then reference activities that could lead to culture change and there are those that talk about culture change as a set of behaviors that need to be adopted by those in IT. There is no question that businesses successful in adopting a DevOps mindset have seen departmental culture change, ...
Discussions about cloud computing are evolving into discussions about enterprise IT in general. As enterprises increasingly migrate toward their own unique clouds, new issues such as the use of containers and microservices emerge to keep things interesting. In this Power Panel at 16th Cloud Expo, moderated by Conference Chair Roger Strukhoff, panelists will address the state of cloud computing today, and what enterprise IT professionals need to know about how the latest topics and trends affec...
Explosive growth in connected devices. Enormous amounts of data for collection and analysis. Critical use of data for split-second decision making and actionable information. All three are factors in making the Internet of Things a reality. Yet, any one factor would have an IT organization pondering its infrastructure strategy. How should your organization enhance its IT framework to enable an Internet of Things implementation? In this session, James Kirkland, Red Hat's Chief Architect for the ...