Maya Gold & Silver: Operations Started at Zgounder Silver Mine

BLAINVILLE, QUEBEC -- (Marketwired) -- 07/22/14 -- Maya Gold & Silver Inc. ("Maya" or the "Corporation") (TSX VENTURE:MYA) The Board of Directors and Management of the Corporation are very pleased to announce the milling operations have started at Maya's flagship Zgounder Silver Mine in Morocco.

Ore grading an average of 245 g/t Ag is now being processed. The ore being run through the mill is being sourced from the 35,000 tonnes of mineralized rocks that were transferred to storage areas adjoining the plant from the existing 66,000 tonnes of "ancient stockpiles". The size of this stockpile can sustain over six months of production at the initial rate of approximately 200 tpd. Silver recovery is expected to be in the range of 92%. The Company is not basing its production decision on a feasibility study of mineral reserves demonstrating economic and technical viability.

"The mill start-up at Zgounder is a significant key milestone in the successful development of Maya as an operating resource company, and we recognize and thank our President, Noureddine Mokaddem, and the local and Moroccan Government offices who have just provided the Company with a very precious tool in a difficult period of the mining industry: a stable and upwardly potential cash flow stream", stated Guy Goulet, Chief Executive Officer.

Cautionary statements

The decision to re-start the production at Zgounder and the Company's plans for a mining operation as disclosed herein (the "Production Decision and Plans") were based on economic models prepared by the Company in conjunction with management's knowledge of the property and the existing preliminary estimates of the measured, indicated and inferred mineral resources on the property. The Production Decision and Plans were not based on a feasibility study of mineral reserves demonstrating economic and technical viability. Accordingly, there is increased uncertainty and economic and technical risks of failure associated with the Production Decision and Plans, in particular the risk that mineral grades will be lower than expected, the risk that construction or ongoing mining operations are more difficult or more expensive than expected, the risk that the Company will not be able to transport or sell the mineralized rock it produces to local custom toll mills on the terms it expects, or at all; production and economic variables may vary considerably, due to the absence of a detailed economic and technical analysis according to and in accordance with NI 43-101. Inferred mineral resource estimates are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves.

Milestones Achieved at Zgounder Mine Project (2013-2014)


--  The complete rehabilitation of mine site and mill; 
--  Completion of an Environmental Impact Study; 
--  Creation of Zgounder Millennium Silver Mining (85% Maya / 15% ONHYM); 
--  Filing of initial NI 43-101 compliant silver resources estimate for
    Zgounder silver mine (February 2014); 
--  Obtaining of cyanide importing and operating permits (March 2014). 
--  Filing of N I43-101 Preliminary Economic Assessment on SEDAR (March
    2014); 
--  Filing of NI 43-101 Pre-Feasibility Study on SEDAR (May 2014); 
--  Reception of cyanide (June 2014); 
--  Operations team strengthened at mine site. Key-management employees all
    being in place. 

Commissioning Phase

The commissioning phase for the processing facility is expected to continue for approximately four months, and ore throughput will increase to 250 tpd. Mill feed during the commissioning period will initially be sourced from the existing "ancient stockpile". Underground development and operations will commence and are expected to generate further stockpiles of ore for processing following the commissioning period.

A new tailings pond with a capacity of 1,000,000 tonnes was built and 25,000 m2 of geo-membrane have been stretched out and certified as compliant by local authorities. The local authorities visited the mine site on Friday, July 18th and favourably commented on the geo-membrane covering the new tailings dam which is designed to hold the first years of mine production.

Underground Development

Additional underground production equipment is expected to arrive on site during the second week of August 2014 which will immediately accelerate ore extraction from several already developed stopes.

Highlights of recent Pre-Economic Assessment Study


--  A mining life of 10 years with the current resources; 
--  First year silver production of 647,000 ounces, followed by a regular
    production of 1,027,000 ounces per year; 
--  Very high mill feed grade estimated at 360 g/t Ag; 
--  Total operating cost of US$113.5 per tonne (averaged over the expected
    mine's life); 
--  Additional capex requirements of only US$3.8 million, including the
    concentrator expansion; 
--  Internal rate of return of 174 per cent; 
--  Net present value of US$65.9 million (discounted at 6.5 per cent) at
    silver price of US$22 per ounce; 
--  The Zgounder PEA was prepared as a strictly underground mine related
    solely to the initial mineral resources reported on February 19, 2014,
    as noted above. 

Cautionary Statements

The PEA is preliminary in nature and includes the use of inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Thus, there is no certainty that the results stated in the PEA will be realized. Actual results may vary, perhaps materially. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

Goldminds Geoservices who authored the PEA, recognized in addition to the Measured, Indicated and Inferred Resources that there are areas within recognized structures and depth extensions which will require additional drilling. These recognized structure and depth extensions can offer additional Mineral Potential between 1.5 to 2.0 million tonnes grading 300 to 400 g/t Ag.

The potential quantity and grade is conceptual in nature, there has been insufficient exploration to define a mineral resource, and it is uncertain if further exploration will result in discovery of a mineral resource.

Qualified Persons

The technical content of this news release has been reviewed by Francois Goulet from Goulex Inc.: independent Qualified Persons under NI 43-101 standards.

ABOUT MAYA

Maya Gold & Silver Inc. is a Canadian listed mining corporation focused on the exploration and development of gold and silver deposits in Morocco. Maya is initiating mining and milling operations at its Zgounder Mine.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Forward-looking statements

This news release contains statements about our future business and planned activities. These are "forward-looking" because we have used what we know and expect today to make a statement about the future. Forward-looking statements including but are not limited to comments regarding the timing and content of upcoming work and analyses. Forward-looking statements usually include words such as may, intend, plan, expect, anticipate, believe, or other similar words. We believe the expectations reflected in these forward-looking statements are reasonable. However, actual events and results could be substantially different because of the risks and uncertainties associated with our business or events that happen after the date of this news release. You should not place undue reliance on forward-looking statements. As a general policy, we do not update forward-looking statements except as required by securities laws and regulations.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
Due of the rise of Hadoop, many enterprises are now deploying their first small clusters of 10 to 20 servers. At this small scale, the complexity of operating the cluster looks and feels like general data center servers. It is not until the clusters scale, as they inevitably do, when the pain caused by the exponential complexity becomes apparent. We've seen this problem occur time and time again. In his session at Big Data Expo, Greg Bruno, Vice President of Engineering and co-founder of StackI...
Once the decision has been made to move part or all of a workload to the cloud, a methodology for selecting that workload needs to be established. How do you move to the cloud? What does the discovery, assessment and planning look like? What workloads make sense? Which cloud model makes sense for each workload? What are the considerations for how to select the right cloud model? And how does that fit in with the overall IT transformation?
The recent trends like cloud computing, social, mobile and Internet of Things are forcing enterprises to modernize in order to compete in the competitive globalized markets. However, enterprises are approaching newer technologies with a more silo-ed way, gaining only sub optimal benefits. The Modern Enterprise model is presented as a newer way to think of enterprise IT, which takes a more holistic approach to embracing modern technologies.
For better or worse, DevOps has gone mainstream. All doubt was removed when IBM and HP threw up their respective DevOps microsites. Where are we on the hype cycle? It's hard to say for sure but there's a feeling we're heading for the "Peak of Inflated Expectations." What does this mean for the enterprise? Should they avoid DevOps? Definitely not. Should they be cautious though? Absolutely. The truth is that DevOps and the enterprise are at best strange bedfellows. The movement has its roots in t...
The true value of the Internet of Things (IoT) lies not just in the data, but through the services that protect the data, perform the analysis and present findings in a usable way. With many IoT elements rooted in traditional IT components, Big Data and IoT isn’t just a play for enterprise. In fact, the IoT presents SMBs with the prospect of launching entirely new activities and exploring innovative areas. CompTIA research identifies several areas where IoT is expected to have the greatest impac...
There is little doubt that Big Data solutions will have an increasing role in the Enterprise IT mainstream over time. 8th International Big Data Expo, co-located with 17th International Cloud Expo - to be held November 3-5, 2015, at the Santa Clara Convention Center in Santa Clara, CA - has announced its Call for Papers is open. As advanced data storage, access and analytics technologies aimed at handling high-volume and/or fast moving data all move center stage, aided by the cloud computing bo...
Every day we read jaw-dropping stats on the explosion of data. We allocate significant resources to harness and better understand it. We build businesses around it. But we’ve only just begun. For big payoffs in Big Data, CIOs are turning to cognitive computing. Cognitive computing’s ability to securely extract insights, understand natural language, and get smarter each time it’s used is the next, logical step for Big Data.
Enterprises are fast realizing the importance of integrating SaaS/Cloud applications, API and on-premises data and processes, to unleash hidden value. This webinar explores how managers can use a Microservice-centric approach to aggressively tackle the unexpected new integration challenges posed by proliferation of cloud, mobile, social and big data projects. Industry analyst and SOA expert Jason Bloomberg will strip away the hype from microservices, and clearly identify their advantages and d...
There's no doubt that the Internet of Things is driving the next wave of innovation. Google has spent billions over the past few months vacuuming up companies that specialize in smart appliances and machine learning. Already, Philips light bulbs, Audi automobiles, and Samsung washers and dryers can communicate with and be controlled from mobile devices. To take advantage of the opportunities the Internet of Things brings to your business, you'll want to start preparing now.
The 4th International Internet of @ThingsExpo, co-located with the 17th International Cloud Expo - to be held November 3-5, 2015, at the Santa Clara Convention Center in Santa Clara, CA - announces that its Call for Papers is open. The Internet of Things (IoT) is the biggest idea since the creation of the Worldwide Web more than 20 years ago.
In a world of ever-accelerating business cycles and fast-changing client expectations, the cloud increasingly serves as a growth engine and a path to new business models. Dynamic clouds enable businesses to continuously reinvent themselves, adapting their business processes, their service and software delivery and their operations to achieve speed-to-market and quick response to customer feedback. As the cloud evolves, the industry has multiple competing cloud technologies, offering on-premises ...
The 5th International DevOps Summit, co-located with 17th International Cloud Expo – being held November 3-5, 2015, at the Santa Clara Convention Center in Santa Clara, CA – announces that its Call for Papers is open. Born out of proven success in agile development, cloud computing, and process automation, DevOps is a macro trend you cannot afford to miss. From showcase success stories from early adopters and web-scale businesses, DevOps is expanding to organizations of all sizes, including the...
As the world moves from DevOps to NoOps, application deployment to the cloud ought to become a lot simpler. However, applications have been architected with a much tighter coupling than it needs to be which makes deployment in different environments and migration between them harder. The microservices architecture, which is the basis of many new age distributed systems such as OpenStack, Netflix and so on is at the heart of CloudFoundry – a complete developer-oriented Platform as a Service (PaaS...
In high-production environments where release cycles are measured in hours or minutes — not days or weeks — there's little room for mistakes and no room for confusion. Everyone has to understand what's happening, in real time, and have the means to do whatever is necessary to keep applications up and running optimally. DevOps is a high-stakes world, but done well, it delivers the agility and performance to significantly impact business competitiveness.
The OpenStack cloud operating system includes Trove, a database abstraction layer. Rather than applications connecting directly to a specific type of database, they connect to Trove, which in turn connects to one or more specific databases. One target database is Postgres Plus Cloud Database, which includes its own RESTful API. Trove was originally developed around MySQL, whose interfaces are significantly less complicated than those of the Postgres cloud database. In his session at 16th Cloud...