CALGARY, ALBERTA -- (Marketwired) -- 07/24/14 -- Husky Energy (TSX: HSE) advanced a strong balance of near, mid and long-term projects in the second quarter while generating higher quality returns to sustain growth.

"Our continued investment in longer-wavelength projects such as heavy oil thermals, resource plays and oil sands provide steady production and more predictable cash flow to support our growth projects in the Asia Pacific and the Atlantic Regions," said CEO Asim Ghosh.

"Our new thermal developments are delivering well above their nameplate designs and production was further boosted this quarter by strong performance from our resource plays and the start up of the Liwan Gas Project."

Net earnings were $628 million, up approximately four percent from $605 million in the second quarter of 2013. Cash flow from operations was $1.50 billion, up from $1.45 billion a year ago.

Upstream production averaged 334,000 barrels of oil equivalent per day (boe/day) up eight percent compared to 310,000 boe/day in the second quarter of 2013.

Throughputs at the Downstream refineries and Lloydminster Upgrader were 304,000 barrels per day (bbls/day), compared to 317,000 bbls/day in the second quarter of 2013.

Highlights Include:


--  Net earnings were $628 million, or $0.63 per share (diluted), compared
    to $605 million, or $0.59 per share (diluted) a year ago.
--  Cash flow from operations was $1.50 billion, or $1.52 per share
    (diluted), up from $1.45 billion, or $1.47 per share (diluted) in the
    second quarter of 2013.
--  Total Upstream production averaged 334,000 boe/day, compared to 310,000
    boe/day a year ago.
--  Sales gas from the Liwan Gas Project is flowing into the mainland China
    market, with the deepwater wells, shallow water platform and onshore gas
    terminal performing as expected.
--  All major regulatory approvals are in place at the Sunrise Energy
    Project, including the Maximum Operating Pressure permit.
--  Well pads and gathering pipelines are being commissioned at Sunrise,
    with startup on track for later this year.
--  Received regulatory approval of the contract award for an FPSO (Floating
    Production, Storage and Offloading) vessel to develop the BD field in
    the Madura Strait offshore Indonesia.
--  Construction advanced at the 10,000 bbls/day Rush Lake heavy oil thermal
    project, with first oil planned in the second half of 2015.
--  Drilling has resumed at the North Amethyst Hibernia formation well in
    the Atlantic Region, with first oil production expected later this year.
--  A seismic acquisition program has commenced in the Bay du Nord discovery
    area in the Flemish Pass, with drilling anticipated to begin in the
    third quarter.

FINANCIAL AND OPERATIONAL HIGHLIGHTS


                                       Three Months Ended   Six Months Ended
                                     June 30  Mar 31 June 30 June 30 June 30
                                        2014    2014    2013    2014    2013
1) Daily Production, before
 royalties
  Total Equivalent Production
   (mboe/day)                            334     326     310     330     316
  Crude Oil and NGLs (mbbls/day)         233     242     226     237     229
  Natural Gas (mmcf/day)                 604     506     505     555     521
2) Operating Netback ($/boe) (1)(2)    48.70   44.81   38.32   46.78   35.24
3) Refinery and Upgrader Throughput
 (mbbls/day)                             304     289     317     296     322
4) Cash Flow from Operations(2) (Cdn
 $ millions)                           1,504   1,536   1,449   3,040   2,732
  Per Common Share - Basic ($/share)    1.53    1.56    1.47    3.09    2.78
  Per Common Share - Diluted
   ($/share)                            1.52    1.56    1.47    3.08    2.78
5) Net Earnings (Cdn $ millions)         628     662     605   1,290   1,140
  Per Common Share - Basic ($/share)    0.63    0.67    0.61    1.30    1.15
  Per Common Share - Diluted
   ($/share)                            0.63    0.66    0.59    1.30    1.13
6) Adjusted Net Earnings(2) (Cdn $
 millions)                               682     716     610   1,398   1,157
  Per Common Share - Basic ($/share)    0.69    0.73    0.62    1.42    1.18
  Per Common Share - Diluted
   ($/share)                            0.69    0.73    0.62    1.42    1.18
7) Capital Investment, including
 acquisitions (Cdn $ millions)         1,056   1,269     932   2,325   2,084
8) Dividend Per Common Share
 ($/share)                              0.30    0.30    0.30    0.60    0.60

(1) Operating netback includes results from Upstream Exploration and
    Production and excludes Upstream Infrastructure and Marketing.
(2) Operating netback, cash flow from operations and adjusted net earnings
    are non-GAAP measures. Refer to the Q2 MD&A, Section 11, which is
    incorporated herein by reference.

Second quarter production was 334,000 boe/day, compared to 310,000 boe/day in the second quarter of 2013. This reflected growing production from heavy oil thermal developments, oil and liquids-rich gas resource plays and the ramp up of the Liwan Gas Project.

Downstream throughputs of 304,000 bbls/day take into account extended startups at the Lima Refinery and the Upgrader following planned turnarounds.

WTI prices averaged US$102.99 per barrel in the second quarter compared to US$94.22 a year ago. Average realized pricing for the Company's crude oil, natural gas liquids and bitumen was $90.33 per barrel, compared to $77.98 in the second quarter of 2013.

U.S. refining Chicago market crack spreads averaged US$19.40 per barrel in the second quarter, compared to US$30.78 in the same period in 2013, while the realized U.S. refining margin averaged US$14.40 per barrel compared to US$20.24 a year ago.

KEY AREA SUMMARY

THE FOUNDATION BUSINESS


--  Heavy Oil

Growing production volumes and longer-life thermal projects are helping lengthen the stride of the heavy oil business with improved earnings per barrel of production.

Consistent performance from thermal developments delivered approximately 44,000 bbls/day during the second quarter, compared to 41,000 bbls/day in the first quarter and 37,500 bbls/day a year ago.

The Sandall thermal project continues to deliver strong results, with average production of 5,300 bbls/day in the second quarter, well above its design capacity of 3,500 bbls/day.

Husky continued to advance construction on a series of high-netback, modular thermal projects.


--  The 10,000 bbls/day Rush Lake thermal development is being advanced
    towards first production in the second half of 2015.
--  The 10,000 bbls/day Edam East thermal project is on pace for first oil
    in the first half of 2016.
--  The 3,500 bbls/day Edam West thermal project is set to come on
    production in the second half of 2016.
--  The 10,000 bbls/day Vawn thermal project is anticipated to begin
    production in the second half of 2016.

Four horizontal heavy oil wells were drilled in the second quarter, with 27 wells drilled to date in 2014. Two Cold Heavy Oil Production with Sand (CHOPS) wells were drilled, with 75 wells drilled so far in 2014.


--  Western Canada

The transformation of the Company's Western Canada business continued in the second quarter, with production from an extensive liquids-rich gas and oil resource portfolio averaging 32,500 boe/day compared to 24,700 boe/day in the second quarter of 2013.

Gas Resource Plays

With a large land base of more than 120,000 net acres and multi-zone potential, the Ansell liquids-rich gas play is a key development in the Company's Western Canada resource portfolio. Eleven horizontal wells were drilled and five completed at Ansell in the second quarter, contributing to production of about 17,000 boe/day compared to 13,500 boe/day in the second quarter of 2013. Planning is under way for an additional four-well pad later this year.

Results from a four-well pad and a two-well pad at Kaybob in the Duvernay continued to be monitored as the play is worked for greater productivity and efficiency.

At the Wilrich liquids-rich gas play at Kakwa, three horizontal gas wells were drilled and three wells were completed during the second quarter. At the Strachan Cardium play, two horizontal gas wells were completed with further development drilling scheduled later in 2014.

Oil Resource Plays

Three horizontal wells were drilled and three completed in the second quarter, with activity primarily focused on the Viking and Cardium oil resource plays.

A four-well pad at Wapiti Cardium is delivering good results, and the Company has expanded its land position on the play to add more drilling locations.


--  Downstream

The focused integration of Husky's Downstream business enables it to capture Brent-like pricing for its Western Canada crude production. The Company is undertaking several initiatives to further build flexibility of feedstocks, product range and market access.

Work was advanced on a terminal expansion project at Hardisty, Alberta in the second quarter to add value through extended pipeline connectivity, blending capability and storage capacity. Construction on two 300,000-barrel storage tanks and new pipe interconnections is scheduled to be completed in 2015.

Plans are underway to extend the Company's South Saskatchewan Gathering System to accommodate increased heavy oil thermal production from Rush Lake, Edam West, Edam East and Vawn.

Equipment upgrades are progressing at the Lima Refinery to allow for the processing of up to 40,000 bbls/day of heavy crude feedstock starting in 2017, which will support the Company's growing heavy oil thermal business. FEED is approximately 95 percent complete.

A new recycle gas compressor at the partner-operated refinery in Toledo, Ohio is scheduled to come online later in 2014.

GROWTH PILLARS


--  Asia Pacific Region

Husky is building on its strong track record in the Asia Pacific Region.

Sales gas from the Liwan Gas Project continues to be sold into the mainland China market, and the Company recently began regular shipments of natural gas liquids and condensates.

Construction vessels have commenced work to complete the installation of a second deepwater production pipeline from the main Liwan 3-1 field to the shallow water central platform. The field is scheduled to be shut-in for six to eight weeks starting in the fourth quarter to facilitate the installation.

Liwan production will continue to ramp up as several third-party power plants complete their commissioning and startup process.

In Indonesia, construction is progressing on the shallow water platform infrastructure for the BD field and the contract award for the FPSO (Floating Production, Storage and Offloading) vessel has received final regulatory approval. The tendering process for the MDA and MBH joint development is in progress, and a gas sales agreement is being negotiated.


--  Oil Sands

A rich portfolio of oil sands leases in northern Alberta is providing the foundation for predictable, long-wavelength production and cash flow.

The Sunrise Energy Project is progressing towards startup later this year. All major regulatory approvals, including the Maximum Operating Pressure permit, are now in place for Phase 1. The well pads, diluent, diluted bitumen and gathering pipelines are moving through the commissioning phase, and major electrical systems for Plant 1A have been completed and energized.

Phase 1 production is expected to ramp up over 18-24 months to 60,000 bbls/day (30,000 bbls/day net to Husky). Plant 1A is scheduled to be brought online first, followed by Plant 1B approximately six months afterwards.


--  Atlantic Region

Husky is developing a wide range of projects in the White Rose field offshore Eastern Canada to maintain production over the near and mid-term, while exploration and appraisal activities are opening up a new chapter of long-term growth.

In the Jeanne d'Arc Basin offshore Newfoundland and Labrador, drilling has resumed on a Hibernia-formation well that will target a deeper zone beneath the North Amethyst field, with first production planned later in 2014.

Production equipment for the South White Rose extension in the White Rose field is scheduled for installation in the third quarter, with first oil expected around the end of the year.

A public review process is underway for the West White Rose extension project and work continues on a graving dock to support construction of a fixed wellhead platform. Subject to final approvals, first oil is scheduled for the 2017 timeframe.

The Company and its partner have initiated a 3-D seismic program in the Bay du Nord discovery area of the Flemish Pass Basin, which will be followed in the third quarter by an 18-month deepwater drilling program. Husky holds a 35 percent working interest in the Bay du Nord, Mizzen and Harpoon discoveries in the Flemish Pass.

CORPORATE DEVELOPMENTS

The Company is conducting a search for a Chief Financial Officer following the resignation of Alister Cowan. During this period, Treasurer Darren Andruko will serve as Acting CFO.

The Board of Directors has declared a quarterly dividend of $0.30 (Canadian) per share on its common shares for the three-month period ended June 30, 2014. The dividend will be payable on October 1, 2014 to shareholders of record at the close of business on August 28, 2014.

A regular quarterly dividend on the 4.45 percent Cumulative Redeemable Preferred Shares, Series 1 (the "Series 1 Preferred Shares") will be paid for the period July 1, 2014 to September 30, 2014. The dividend of $0.27813 per Series 1 Preferred Share will be payable on September 30, 2014 to holders of record at the close of business on August 28, 2014.

For those shareholders of the common shares who have not already done so and would like to accept to receive dividends in the form of common shares, they should inform Husky's transfer agent, Computershare, via written notice in prescribed form on or before August 20, 2014. A link to an electronic copy of the Stock Dividend Confirmation Notice is available at www.investorcentre.com/husky

CONFERENCE CALL

A conference call will take place on Thursday, July 24 at 9 a.m. Mountain Time (11 a.m. Eastern Time) to discuss Husky's second quarter results. To listen live, please call one of the following numbers:


Canada and U.S. Toll Free:            1-800-319-4610
Outside Canada and U.S.:              1-604-638-5340

CEO Asim Ghosh, COO Rob Peabody, Treasurer and Acting CFO Darren Andruko and Downstream Senior VP Bob Baird will participate in the call. To listen to a recording of the call, available at 11 a.m. Mountain Time on July 24, please call one of the following numbers:


Canada and U.S. Toll Free:            1-800-319-6413
Outside Canada and U.S.:              1-604-638-9010

Passcode:                             2658 followed by the # sign
Duration:                             Available until August 25, 2014

The archived webcast conference call will be available for approximately 90 days.

Husky Energy is one of Canada's largest integrated energy companies. It is headquartered in Calgary, Alberta, Canada and is publicly traded on the Toronto Stock Exchange under the symbol HSE and HSE.PR.A. More information is available at www.huskyenergy.com

FORWARD-LOOKING STATEMENTS

Certain statements in this news release are forward-looking statements and information (collectively "forward-looking statements"), within the meaning of the applicable Canadian securities legislation, Section 21E of the United States Securities Exchange Act of 1934, as amended, and Section 27A of the United States Securities Act of 1933, as amended. The forward-looking statements contained in this document are forward-looking and not historical facts.

Some of the forward-looking statements may be identified by statements that express, or involve discussions as to, expectations, beliefs, plans, objectives, assumptions or future events or performance (often, but not always, through the use of words or phrases such as "will likely result", "are expected to", "will continue", "is anticipated", "is targeting", "estimated", "intend", "plan", "projection", "could", "aim", "vision", "goals", "objective", "target", "schedules" and "outlook"). In particular, forward-looking statements in this news release include, but are not limited to, references to:


--  with respect to the Company's Asia Pacific Region: expected timing and
    duration of installation of a second deepwater production pipeline from
    the main Liwan 3-1 field to the shallow water central platform, and
    associated shut-in of production from the field; and continued ramping-
    up of production from the Company's Liwan Gas Project;

--  with respect to the Company's Atlantic Region: scheduled timing of
    installation of oil production equipment and anticipated timing of first
    production at the Company's South White Rose Extension project;
    scheduled timing of first oil at the West White Rose extension project;
    planned drilling targets and timing of first production from the North
    Amethyst Hibernia formation well; and scheduled timing and duration for
    a drilling program at the Bay du Nord discovery;

--  with respect to the Company's Oil Sands properties: scheduled timing of
    start up at the Company's Sunrise Energy Project; and expected timing
    and volume of ramping-up of production from Phase 1 of the Company's
    Sunrise Energy Project;

--  with respect to the Company's Heavy Oil properties: expected timing of
    first production at the Company's Rush Lake, Edam East, Edam West and
    Vawn heavy oil thermal development projects;

--  with respect to the Company's Western Canadian oil and gas resource
    plays: drilling plans for the Company's Ansell liquids-rich gas play;
    and drilling and development plans at the Company's Strachan Cardium
    play;

--  with respect to the Company's Infrastructure and Marketing operating
    segment: scheduled timing of completion of plans to increase pipeline
    connectivity and construction of two 300,000-barrel storage tanks at the
    Hardisty terminal; and plans for the expansion of the South Saskatchewan
    Gathering System for the Rush Lake, Edam West, Edam East and Vawn
    projects; and

--  with respect to the Company's Downstream operating segment: the
    anticipated benefits from and scheduled timing of completion of the
    Lima, Ohio refinery reconfiguration and the anticipated processing
    capacity once reconfiguration is complete; and scheduled timing of
    completion of a Hydrotreater Recycle Gas Compressor Project at the
    Toledo Refinery;

Although the Company believes that the expectations reflected by the forward-looking statements presented in this news release are reasonable, the Company's forward-looking statements have been based on assumptions and factors concerning future events that may prove to be inaccurate. Those assumptions and factors are based on information currently available to the Company about itself and the businesses in which it operates. Information used in developing forward-looking statements has been acquired from various sources including third-party consultants, suppliers, regulators and other sources.

Because actual results or outcomes could differ materially from those expressed in any forward-looking statements, investors should not place undue reliance on any such forward-looking statements. By their nature, forward-looking statements involve numerous assumptions, inherent risks and uncertainties, both general and specific, which contribute to the possibility that the predicted outcomes will not occur. Some of these risks, uncertainties and other factors are similar to those faced by other oil and gas companies and some are unique to Husky.

The Company's Annual Information Form for the year ended December 31, 2013 and other documents filed with securities regulatory authorities (accessible through the SEDAR website www.sedar.com and the EDGAR website www.sec.gov) describe the risks, material assumptions and other factors that could influence actual results and are incorporated herein by reference.

Any forward-looking statement speaks only as of the date on which such statement is made, and, except as required by applicable securities laws, the Company undertakes no obligation to update any forward-looking statement to reflect events or circumstances after the date on which such statement is made or to reflect the occurrence of unanticipated events. New factors emerge from time to time, and it is not possible for management to predict all of such factors and to assess in advance the impact of each such factor on the Company's business or the extent to which any factor, or combination of factors, may cause actual results to differ materially from those contained in any forward-looking statement. The impact of any one factor on a particular forward-looking statement is not determinable with certainty as such factors are dependent upon other factors, and the Company's course of action would depend upon its assessment of the future considering all information then available.

Disclosure of Oil and Gas Information

Unless otherwise noted, historical production numbers given represent Husky's share.

The Company uses the terms barrels of oil equivalent ("boe"), which is calculated on an energy equivalence basis whereby one barrel of crude oil is equivalent to six thousand cubic feet of natural gas. Readers are cautioned that the term boe may be misleading, particularly if used in isolation. This measure is primarily applicable at the burner tip and does not represent value equivalence at the wellhead.

Contacts:
Investor Inquiries:
Dan Cuthbertson
Manager, Investor Relations
Husky Energy Inc.
403-523-2395

Media Inquiries:
Mel Duvall
Manager, Media & Issues
Husky Energy Inc.
403-513-7602

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

Latest Stories
"There is a natural synchronization between the business models, the IoT is there to support ,” explained Brendan O'Brien, Co-founder and Chief Architect of Aria Systems, in this SYS-CON.tv interview at the 15th International Cloud Expo®, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
SYS-CON Events announced today that Gridstore™, the leader in hyper-converged infrastructure purpose-built to optimize Microsoft workloads, will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Gridstore™ is the leader in hyper-converged infrastructure purpose-built for Microsoft workloads and designed to accelerate applications in virtualized environments. Gridstore’s hyper-converged infrastructure is the ...
This builds on Puppet Labs' first class Windows support, including native .MSI packages for x32 and x64 operating systems, modules to extend common Windows server management tools, including Powershell, and integrations with Microsoft Azure and Visual Studio. By automating common Windows administration tasks, Puppet Labs is enabling users to adopt DevOps practices, thereby reducing the time needed to deploy applications from weeks to hours.
DevOps Summit 2015 New York, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that it is now accepting Keynote Proposals. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long development cycles that produce software that is obsolete...
WebRTC defines no default signaling protocol, causing fragmentation between WebRTC silos. SIP and XMPP provide possibilities, but come with considerable complexity and are not designed for use in a web environment. In his session at @ThingsExpo, Matthew Hodgson, technical co-founder of the Matrix.org, discussed how Matrix is a new non-profit Open Source Project that defines both a new HTTP-based standard for VoIP & IM signaling and provides reference implementations.
"SAP had made a big transition into the cloud as we believe it has significant value for our customers, drives innovation and is easy to consume. When you look at the SAP portfolio, SAP HANA is the underlying platform and it powers all of our platforms and all of our analytics," explained Thorsten Leiduck, VP ISVs & Digital Commerce at SAP, in this SYS-CON.tv interview at 15th Cloud Expo, held Nov 4-6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
SAP is delivering break-through innovation combined with fantastic user experience powered by the market-leading in-memory technology, SAP HANA. In his General Session at 15th Cloud Expo, Thorsten Leiduck, VP ISVs & Digital Commerce, SAP, discussed how SAP and partners provide cloud and hybrid cloud solutions as well as real-time Big Data offerings that help companies of all sizes and industries run better. SAP launched an application challenge to award the most innovative SAP HANA and SAP HANA...
There's Big Data, then there's really Big Data from the Internet of Things. IoT is evolving to include many data possibilities like new types of event, log and network data. The volumes are enormous, generating tens of billions of logs per day, which raise data challenges. Early IoT deployments are relying heavily on both the cloud and managed service providers to navigate these challenges. In her session at Big Data Expo®, Hannah Smalltree, Director at Treasure Data, discussed how IoT, Big D...
Connected devices and the Internet of Things are getting significant momentum in 2014. In his session at Internet of @ThingsExpo, Jim Hunter, Chief Scientist & Technology Evangelist at Greenwave Systems, examined three key elements that together will drive mass adoption of the IoT before the end of 2015. The first element is the recent advent of robust open source protocols (like AllJoyn and WebRTC) that facilitate M2M communication. The second is broad availability of flexible, cost-effective ...
Scott Jenson leads a project called The Physical Web within the Chrome team at Google. Project members are working to take the scalability and openness of the web and use it to talk to the exponentially exploding range of smart devices. Nearly every company today working on the IoT comes up with the same basic solution: use my server and you'll be fine. But if we really believe there will be trillions of these devices, that just can't scale. We need a system that is open a scalable and by using ...
DevOps Summit 2015 New York, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that it is now accepting Keynote Proposals. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long development cycles that produce software that is obsolete...
Explosive growth in connected devices. Enormous amounts of data for collection and analysis. Critical use of data for split-second decision making and actionable information. All three are factors in making the Internet of Things a reality. Yet, any one factor would have an IT organization pondering its infrastructure strategy. How should your organization enhance its IT framework to enable an Internet of Things implementation? In his session at Internet of @ThingsExpo, James Kirkland, Chief Ar...
The term culture has had a polarizing effect among DevOps supporters. Some propose that culture change is critical for success with DevOps, but are remiss to define culture. Some talk about a DevOps culture but then reference activities that could lead to culture change and there are those that talk about culture change as a set of behaviors that need to be adopted by those in IT. There is no question that businesses successful in adopting a DevOps mindset have seen departmental culture change, ...
The 3rd International Internet of @ThingsExpo, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that its Call for Papers is now open. The Internet of Things (IoT) is the biggest idea since the creation of the Worldwide Web more than 20 years ago.
The 4th International DevOps Summit, co-located with16th International Cloud Expo – being held June 9-11, 2015, at the Javits Center in New York City, NY – announces that its Call for Papers is now open. Born out of proven success in agile development, cloud computing, and process automation, DevOps is a macro trend you cannot afford to miss. From showcase success stories from early adopters and web-scale businesses, DevOps is expanding to organizations of all sizes, including the world's large...